Is there a ban of extending 3rd rail or installing new 3rd rail routes?

Just wondering on the ELL to Dalston Junction got done that's all.

Is there isn't such a ruling then could not the North Downs be electrified to the 3rd rail system?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

yorksrob

Veteran Member
Joined
6 Aug 2009
Messages
44,312
Location
Yorks
I'm sure there's not a ban on extending the third rail. It was being extended regularly on the Southern into NSE years. They certainly don't like putting it anywhere totally new though.

I think it's just a matter of funding problems and different priorities as to why the gaps on the Southern and the extremities of Merseyrail haven't been done yet.
 

Wyvern

Established Member
Joined
27 Oct 2009
Messages
1,573
I believe ground level supply rails are not allowed under EU regulations.

Existing British third rail has grandfather rights for possibly extensions but certainly "filling in".
 

MikeWh

Established Member
Associate Staff
Senior Fares Advisor
Joined
15 Jun 2010
Messages
8,555
Location
Crayford
I believe ground level supply rails are not allowed under EU regulations.

Existing British third rail has grandfather rights for possibly extensions but certainly "filling in".

Interesting. Is that any kind of ground level supply, or just upward facing? Was the DLR started before the regulations were made?
 

WatcherZero

Established Member
Joined
25 Feb 2010
Messages
10,272
As I understood it was just a Dft moratorium on new 3rd rail routes to limit its spread because of wider network compatability and general feeling it is inferior while extending existing lines is allowed.
 

jopsuk

Veteran Member
Joined
13 May 2008
Messages
12,774
If it is banned by the EU, there will be an EC directive. They are all, as far as I know, publicly available in the internet. Why not go and find it? It'll help back up your argument...
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,257
Or just read the Network Rail 'Electrification RUS'. It clearly identifies which lines would be electrified with third rail, which OHL, and which are 'to be decided'. The latter includes Salisbury - Exeter - where they intimate that it would probably be AC, but don't say it MUST be AC, so I'd suggest relatively long extensions might be allowed.

But for the North Downs route, which started the original discussion:

Gap A3.1 Wokingham to Ash and Shalford to Reigate
Option A3.1 Electrify Wokingham to Ash and Shalford to Reigate with DC electrification. Convert Reading to Gatwick Airport and Reading to Redhill local services to electric traction.
 

tbtc

Veteran Member
Joined
16 Dec 2008
Messages
18,052
Location
Reston City Centre
Would we be allowed to "fill in" the stretch between Basingstoke and Chester then? ;)

This could be one of those bits of "received wisdom", like "Pacers aren't allowed on Third Rail lines, where nobody knows the real source to "confirm"...
 

Lampshade

Established Member
Joined
3 Sep 2009
Messages
3,777
Location
South London
This could be one of those bits of "received wisdom", like "Pacers aren't allowed on Third Rail lines, where nobody knows the real source to "confirm"...

We all know that's rubbish, 142s go through Hunts Cross all the time. It's an excuse to keep them away from London.
 

Old Timer

Established Member
Joined
24 Aug 2009
Messages
3,702
Location
On a plane somewhere at 35,000
3rd rail electrification by its very nature is very expensive when compared to OHL Equipment.

Any long distance expansions would take a long time to recover the investment, and would increase considerably the track access costs.

There is no easy solution I am afraid.
 

yorksrob

Veteran Member
Joined
6 Aug 2009
Messages
44,312
Location
Yorks
I suppose at least all of the prospective third rail routes are relatively short infills (with the exception of Basingstoke - Exeter of course. Perhaps they could electrify as far as Salisbury and develop some sort of push - pull operation again for anything further west :idea:).
 

asylumxl

Established Member
Joined
12 Feb 2009
Messages
4,260
Location
Hiding in your shadow
It is my uninformed opinion that it'd make sense just to go all the way 3rd rail to Exeter. It would mean SWT could utilise their existing stock to the best possible. Also, 444s would be nice on the route :).
 

jopsuk

Veteran Member
Joined
13 May 2008
Messages
12,774
Or, if the GWML electrification goes to Exeter, wire up the south west route and add the OHL equipment to the appropriate stock.
 

yorksrob

Veteran Member
Joined
6 Aug 2009
Messages
44,312
Location
Yorks
Yes, come to think of it, dual voltage electrics are a tried and tested technology. Have the changeover at Salisbury then most of the stoppers wouldn't need altering.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,257
It is my uninformed opinion that it'd make sense just to go all the way 3rd rail to Exeter. It would mean SWT could utilise their existing stock to the best possible. Also, 444s would be nice on the route :).

There isn't any existing electric stock sitting around spare for use on newly electrified routes. That's the main reason SWT use 158s and 159s on third rail only routes already.

Your suggestion might have made sense if you'd simply said that more 444s and 450s should be obtained for Exeter and Salisbury stoppers respectively, allowing existing DMUs to be cascaded.
 

WatcherZero

Established Member
Joined
25 Feb 2010
Messages
10,272
Since im sure Merseyrail wont get new rolling stock in present climate, are the 508's going to go back to the Mersey?
 

Jan

Member
Joined
22 Dec 2008
Messages
75
Interesting. Is that any kind of ground level supply, or just upward facing? Was the DLR started before the regulations were made?
I these regulations don't apply to the DLR because it uses bottom-contact 3rd rail.
 

Class377/5

Established Member
Joined
19 Jun 2010
Messages
5,594
I these regulations don't apply to the DLR because it uses bottom-contact 3rd rail.

And its encased in plastic (except the underneath) so you can safely cross it where as the 3rd rail on the rest of the network is all exposed.
 

scrapy

Established Member
Joined
15 Dec 2008
Messages
2,304
Would we be allowed to "fill in" the stretch between Basingstoke and Chester then? ;)

This could be one of those bits of "received wisdom", like "Pacers aren't allowed on Third Rail lines, where nobody knows the real source to "confirm"...

Pacers are used on 3rd rail at Hunts Cross and Chester without any problem.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,257
Pacers are used on 3rd rail at Hunts Cross and Chester without any problem.

Yes, but Basingstoke is in the South East .

We have much higher standards expected of our rolling stock round here, I'll have you know... :lol:
 

tbtc

Veteran Member
Joined
16 Dec 2008
Messages
18,052
Location
Reston City Centre
Pacers are used on 3rd rail at Hunts Cross and Chester without any problem.

Yeah, I was meaning that lots of people believed that they weren't allowed on 3rd rail lines (despite the evidence), and it becomes a kind of "received wisdom" where we accept information as fact without having anything to back it up...

...similarly, I'd not actually seen anything saying more 3rd rail wasn't allowed (apart from infills), so wasn't sure if there was evidence it wasn't allowed, or other reasons for it not happening (e.g. cost)
 

Kneedown

Established Member
Joined
29 Dec 2007
Messages
1,837
Location
Nottinghamshire
Yeah, I was meaning that lots of people believed that they weren't allowed on 3rd rail lines (despite the evidence), and it becomes a kind of "received wisdom" where we accept information as fact without having anything to back it up...

I knew what you meant ;)

As regards expanding the third rail, i believe the main argument against it is the cost, as OT already pointed out. I'm not an electrical expert but apparently you need a lot more feeder stations with a 3rd rail dc network than you do with an ac overhead system. I can see why that would cost more, but on the other hand i'd have thought that the live rail would be a set distance from the running rail, and so less planning on where it's going to go (as opposed to deciding how many overhead gantries and their postioning for instance, raising bridges etc) would be required as well as less basic infrastructure, but there you go.
Having said that it would surely be more economical to extend electrification on the Southern and Mersey systems, than it would to rip the whole lot up and replace with overhead.
 

daikilo

Established Member
Joined
2 Feb 2010
Messages
1,623
Would we be allowed to "fill in" the stretch between Basingstoke and Chester then? ;)

This could be one of those bits of "received wisdom", like "Pacers aren't allowed on Third Rail lines, where nobody knows the real source to "confirm"...

Basingstoke to Chester: No. It won't work as you are suggesting linking 2 completely independent networks with no obvious significant traffic flows and not a fill-in extension. That said, e.g extending Mersyrail or Southern Electrics beyond their current boundaries might work for the same reason.
 

A60K

Member
Joined
26 Jun 2008
Messages
1,030
Location
Kilburn
I'm not an electrical expert but apparently you need a lot more feeder stations with a 3rd rail dc network than you do with an ac overhead system.
It's basically because the current on a third rail system is so much lower than on overhead - 750V against 25,000V. AIUI the lower power means more current needs to be supplied, in turn meaning more frequent feeder stations. I'm not sure of the exact distances between feeder stations, and they'll vary according to the number of trains expected in section, but I think it's something like every 3-5 miles on 750V DC, compared to perhaps every 10-25 miles on 25kV AC.
 

button_boxer

Established Member
Joined
12 Nov 2009
Messages
1,271
It's basically because the current on a third rail system is so much lower than on overhead - 750V against 25,000V. AIUI the lower power means more current needs to be supplied, in turn meaning more frequent feeder stations. I'm not sure of the exact distances between feeder stations, and they'll vary according to the number of trains expected in section, but I think it's something like every 3-5 miles on 750V DC, compared to perhaps every 10-25 miles on 25kV AC.

You've got your voltage, current and power mixed up but basically yes.

Power = voltage x current - the voltage is lower on third rail, so trains draw much higher current for the same amount of power. The higher the current the lower the transmission efficiency. At higher current a lot more energy is wasted in transmission (as heat, essentially you're heating up the transmission cables), which is why the feeders have to be closer together.
 