There was a failure of a Network Rail Test Unit? on the Down main line just East of Manningtree Station today Monday, the unit I assume was a 153 (looked to be when went past it), caused delays of up to 150 minutes to mainline services and the Unit looks to have been stuck for around 6 hours on the down main with single line working in place, just wondering why such a time length, is there anything special about the unit or failure or just wrong place wrong time?

== Doublepost prevention - post automatically merged: ==

PS This is probably the service involved https://www.realtimetrains.co.uk/service/gb-nr:R07588/2023-07-03/detailed
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,839
Location
East Anglia
153s running in an area with nothing that could possibly rescue them was never going to be a good idea. The cost of delays yesterday will be enormous as the disruption was so bad.

== Doublepost prevention - post automatically merged: ==

I’m just surprised it’s taken this long before that is realised.
 

Freightmaster

Verified Rep
Joined
7 Jul 2009
Messages
4,434
153s running in an area with nothing that could possibly rescue them was never going to be a good idea....
...and yet the Track Recording Unit (950001) has been wandering the length and breath of the country
for over 30 years now, seemingly without issue?



MARK
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,839
Location
East Anglia
...and yet the Track Recording Unit (950001) has been wandering the length and breath of the country
for over 30 years now, seemingly without issue?



MARK

I wouldn’t say without issue but not in an area where there is literally nothing that can assist it. This was bound to happen & being the one engine can’t even limp out of the way. You missed my point.
 

TheBigD

Established Member
Joined
19 Nov 2008
Messages
2,043
66177 on route learning duties between Peterborough and Ipswich rescued it, before returning back light engine to Peterborough.

There's some Facebook photos of it at Manningtree...

(You may have to he a member to veiw it)


== Doublepost prevention - post automatically merged: ==

Believe the delay was something to do with incompatible couplers.

Waiting for a fitter to come from Derby to assist...
 
Last edited:

TheBigD

Established Member
Joined
19 Nov 2008
Messages
2,043
Team effort involving a number of different companies! Still shafted the GEML for most of the day! The log makes interesting reading!
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,839
Location
East Anglia
Team effort involving a number of different companies! Still shafted the GEML for most of the day! The log makes interesting reading!

I bet lol. Would love to know the final cost for this farce. I’ve known many in my time one being not bothering to dig the Thunderbird 47 out of a siding one morning as it was buried only for the 05:30up to fail at Manningtree. That was a mere £38,000 so this with throw that into a cocked hat.
 

TheBigD

Established Member
Joined
19 Nov 2008
Messages
2,043
No idea about the cost but there's currently over 1900 delay minutes and 23 cancellations (full and part) attributed to it.
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
153s running in an area with nothing that could possibly rescue them was never going to be a good idea. The cost of delays yesterday will be enormous as the disruption was so bad.

== Doublepost prevention - post automatically merged: ==

I’m just surprised it’s taken this long before that is realised.

Perhaps but it may well be a better way than blocking the lines week in week out just to undertake patrolling
 

Class15

Established Member
Joined
30 Dec 2021
Messages
4,119
Location
North London or Mildmay line
153s running in an area with nothing that could possibly rescue them was never going to be a good idea. The cost of delays yesterday will be enormous as the disruption was so bad.

== Doublepost prevention - post automatically merged: ==

I’m just surprised it’s taken this long before that is realised.
There is Ipswich depot?
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,839
Location
East Anglia
Providing a rescue loco.

The rescue loco wasn’t the problem. It was attaching it to the 153. There are no longer any BSI coupler fitted units or emergency couplers readily available as nothing needs them now along the GEML or anywhere on GA.
 

357

Established Member
Joined
12 Nov 2018
Messages
2,283
I drive trains that nothing can couple to. We have an emergency coupling adapter onboard.

For us, we can get a competent person into place pretty quickly to use it.

In this case, perhaps it's worth training the train crew how to do it?
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,839
Location
East Anglia
I drive trains that nothing can couple to. We have an emergency coupling adapter onboard.

For us, we can get a competent person into place pretty quickly to use it.

In this case, perhaps it's worth training the train crew how to do it?

That would be something for the Network Rail organised crew to sort & something I’m gobsmacked wasn’t done in the first place considering the immense disruption it could cause always being so far away from home.

== Doublepost prevention - post automatically merged: ==

I can only assume (something I don’t advocate) that most areas of the UK except perhaps much of the Southern Region and now Anglia still operate some sort of 2nd gen DMUs that could be used to assist.
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
What I don't get is why it wasn't considered turning Intercity services in the Up Platform at Manningtree from Norwich and sending them back to Norwich and conveying people to / from London using Ipswich services terminating at Manningtree from the south, then sending them ECS via Harwich International with passengers swapping between platforms for the through journey.
 

66701GBRF

Member
Joined
3 Jun 2017
Messages
913
What I don't get is why it wasn't considered turning Intercity services in the Up Platform at Manningtree from Norwich and sending them back to Norwich and conveying people to / from London using Ipswich services terminating at Manningtree from the south, then sending them ECS via Harwich International with passengers swapping between platforms for the through journey.
Maybe it was considered? I doubt anyone here knows the full circumstances of the incident and what decisions were taken and why.
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,839
Location
East Anglia
What I don't get is why it wasn't considered turning Intercity services in the Up Platform at Manningtree from Norwich and sending them back to Norwich and conveying people to / from London using Ipswich services terminating at Manningtree from the south, then sending them ECS via Harwich International with passengers swapping between platforms for the through journey.
Up trains continued to operate normally until they ran out then as SLW was planned from Colchester Station to Manningtree it would not have been possible.
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
Up trains continued to operate normally until they ran out then as SLW was planned from Colchester Station to Manningtree it would not have been possible.
That was never needed that far. the failed train was between Mannningtree South and North Jns. SLW over the short distance was all that was needed (and indeed used).
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,839
Location
East Anglia
That was never needed that far. the failed train was between Mannningtree South and North Jns. SLW over the short distance was all that was needed (and indeed used).
Would still have impeded SLW had terminating trains arrived from the Ipswich direction. Did trains reverse over the Colchester end crossover?

== Doublepost prevention - post automatically merged: ==

Only unsignalled move I've done at Manningtree is passing through the station on the down in the up direction. Thankfully then a position light to get back onto the up.
 
Last edited:

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
Would still have impeded SLW had terminating trains arrived from the Ipswich direction.
Correct but SLW wasn't implemented for over 3 hours after the train failed.
Did trains reverse over the Colchester end crossover?
No, when SLW was implemented it appears it was from the Manningtree Station northbound starter signal (CO197) to Manningtree North Jn (CO209). So appearing to be a straight on move crossing over to the Up Main.

Before SLW was implemented Ipswich services were diverted to Harwich International (ECS Manningtree to Harwich International) passing CO197 signal normally it seems.
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,839
Location
East Anglia
Correct but SLW wasn't implemented for over 3 hours after the train failed.

No, when SLW was implemented it appears it was from the Manningtree Station northbound starter signal (CO197) to Manningtree North Jn (CO209). So appearing to be a straight on move crossing over to the Up Main.

Before SLW was implemented Ipswich services were diverted to Harwich International (ECS Manningtree to Harwich International) passing CO197 signal normally it seems.
Sounds an interesting one. Unfortunately not a signalled move which complicates things so much. I'm sure control did everything possible but the longer it took the more chaos was ensued with freight as well as passenger. I disappeared down the East Suffolk after getting off the 10:00 ex-Norwich at Ipswich just as it all kicked off.
 
Status
Not open for further replies.

Top