Network Rail Operational Rules

Peter749

Member
Joined
27 Apr 2016
Messages
262
Location
Salford
I found a link in a thread that is now closed to the NR Operational Rules

I found the section 7 entries that I'm interested in but there only seems to be half the years as they run from Week 27 to Week 1
Not sure where the Week 1 to 26 or 27 might be?

Anu ideas please?

Peter
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,638
I found a link in a thread that is now closed to the NR Operational Rules

I found the section 7 entries that I'm interested in but there only seems to be half the years as they run from Week 27 to Week 1
Not sure where the Week 1 to 26 or 27 might be?

Anu ideas please?

Peter
For what year?
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,403
Location
Northampton
I found the section 7 entries that I'm interested in but there only seems to be half the years as they run from Week 27 to Week 1
Not sure where the Week 1 to 26 or 27 might be?

Anu ideas please?

Peter
For 26/27 and 27/28:
Up to Week 27 is V2 or latest child version (2.1, etc).
After Week 27 is V4 or latest child version.

V1 is the draft for V2.
V3 is the draft for V4.

No, I don't know why it was set up this way.

The same versioning is also used for the TPRs, although obviously the validity date of the TPRs is aligned to the Timetable operation dates, not the EAS dates.

It's confusing because the 25/26 V2 covers Week 26 onwards.
 

Peter749

Member
Joined
27 Apr 2016
Messages
262
Location
Salford
For 26/27 and 27/28:
Up to Week 27 is V2 or latest child version (2.1, etc).
After Week 27 is V4 or latest child version.

V1 is the draft for V2.
V3 is the draft for V4.

No, I don't know why it was set up this way.

The same versioning is also used for the TPRs, although obviously the validity date of the TPRs is aligned to the Timetable operation dates, not the EAS dates.

It's confusing because the 25/26 V2 covers Week 26 onwards.
Thanks

Found the one I was after - S7 FINAL EAS ARP 2627 LNW

Peter
 
Last edited:

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,638
For 26/27 and 27/28:
Up to Week 27 is V2 or latest child version (2.1, etc).
After Week 27 is V4 or latest child version.

V1 is the draft for V2.
V3 is the draft for V4.

No, I don't know why it was set up this way.

The same versioning is also used for the TPRs, although obviously the validity date of the TPRs is aligned to the Timetable operation dates, not the EAS dates.

It's confusing because the 25/26 V2 covers Week 26 onwards.
EAS was altered to financial dates to help with financial planning for renewals etc so runs 1-26.
 

Vexed

Member
Joined
12 Jan 2020
Messages
639
Location
Herts / Hants
Is there something that shows the midweek blocks?
What you're looking at already does - each weekend includes work in the week after it. It's on the GW, but look at P4250567 for example in the same period you're looking at (V4 2026 to 2027) near Bristol which is in week 30. It's a midweek posession running Monday to Friday. Network Rail weeks start on Saturday and end on Friday.
1781017989068.png
Screenshot from the V4.1 NAT MAPS Week 30 showing a midweek posession

Other websites available, here is a calendar for 2026 showing weeks running Sat-Fri https://paperlessconstruction.co.uk/resources/rail-calendars/network-rail-calendar-2026/
1781017934876.png
 

Peter749

Member
Joined
27 Apr 2016
Messages
262
Location
Salford
What you're looking at already does - each weekend includes work in the week after it. It's on the GW, but look at P4250567 for example in the same period you're looking at (V4 2026 to 2027) near Bristol which is in week 30. It's a midweek posession running Monday to Friday. Network Rail weeks start on Saturday and end on Friday.
View attachment 205647
Screenshot from the V4.1 NAT MAPS Week 30 showing a midweek posession
Thanks

Peter
 

Peter749

Member
Joined
27 Apr 2016
Messages
262
Location
Salford
As in cyclical blocks or disruptive? Section 5 are cyclical opportunities.
I know of the Cyclic blocks - they tend to be midweek overnight - used to them around the North West.

I'm interested in the sort of blocks that just appear for a week or more
Like the Week 13 Miles Platting block that is Monday to Friday
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,638
I know of the Cyclic blocks - they tend to be midweek overnight - used to them around the North West.

I'm interested in the sort of blocks that just appear for a week or more
Like the Week 13 Miles Platting block that is Monday to Friday
Then its the maps and advance register of posessions then.
 

Vexed

Member
Joined
12 Jan 2020
Messages
639
Location
Herts / Hants
is the advance register of possessions available?
Yes it's usually abbreviated to ARP on the Network Rail website and pdf files.

I haven't properly integrated it into my website yet, but I have a copy of the S7 maps and I try to keep it updated with new ones (though I haven't removed the old ones from 2025!)

I will make it so it keeps the same position on a page when flicking through weeks soon as this would be useful.

 

Peter749

Member
Joined
27 Apr 2016
Messages
262
Location
Salford
Yes it's usually abbreviated to ARP on the Network Rail website and pdf files.

I haven't properly integrated it into my website yet, but I have a copy of the S7 maps and I try to keep it updated with new ones (though I haven't removed the old ones from 2025!)

I will make it so it keeps the same position on a page when flicking through weeks soon as this would be useful.

That is very handy :)
I notice the work taking place at Miles Platting is not included so that must have been a later change

Peter
 