Hi swt
I suspect when the approval for electrification was only to Mkt Hbro, the idea was to go sufficiently past the station to allow the cross over to be used if required.
However, now the approval is to Leicester (well - Wigston so far), I think the wires will go live all the way from Kettering to Wigston at the same time. There are a lot of masts and cantilevers etc all the way to Kibworth, and now beyond.
Looking at your photo (thanks) it appears the final portal is between the 2nd and 3rd drain cover between the lines. Comparing with Bing satellite pictures (which show them more clearly than Google) suggests the wires would have run out at this point, which is about 300 m North of the more southerly crossovers.
52.485701, -0.907781
https://www.bing.com/maps/?cp=52.485605~-0.9077&lvl=19.7&style=a#
So, subject to signalling etc, it is at least *theoretically* possible to reverse an electric train on the down line North of the station.
Not sure why you'd want to in normal ops. Somebody here may know whether and why this was envisaged, but if it's just speculation then probably best to take that to a new thread.
Back on topic, there are some blue/green cables have appeared, apparently linking the catenary wires to the steelwork. Earthing I assume?