InTheEastMids
Established Member
- Joined
- 31 Jan 2016
- Messages
- 1,382
The new Newtons bridge at Braybrooke has recently had its deck installed at some point.
Lovely jubbly! Based on w3w, that puts it slightly beyond the LR221-LR224 signal gantry. Are these mainly on the DM or UM side?As promised. Drove along the route today, and I can confirm that piling is in place from the A6 bridge at Great Bowden, extending northwards round the bend and along the straight for approximately a quarter of a mile to a location in the area of What3words reference:- "Fatherly.Puddles.Photo"
The protruding pile appears to have been driven down fully now.
Both sides. Even if TTCs are planned, they "change sides" every so often.Lovely jubbly! Based on w3w, that puts it slightly beyond the LR221/LR223 signal gantry. Are these mainly on the DM or UM side?
Traveling north on Friday I counted 18 piles on the up side.As promised. Drove along the route today, and I can confirm that piling is in place from the A6 bridge at Great Bowden, extending northwards round the bend and along the straight for approximately a quarter of a mile to a location in the area of What3words reference:- "Fatherly.Puddles.Photo"
The protruding pile appears to have been driven down fully now.
View from Braybrooke Bridleway Bridge (SPC3/35AA):
Looking west - not much change in the mast/pile situation but work to replace Newtons Bridge (SPC3/35) in the distance is evident.View attachment 119529View attachment 119530
Looking east - looks like all cantilever stovepipes are in, along with all EW clamps and pipes (at least as far as the overlap at bridge SPC3/37). Several TTCs didn't have their EW pipes in, but this has been resolved now.
The only TTC without both EW clamps is the one nearest bridge 35AA - namely SPC3/129.381/UM, which currently lacks a DM stovepipe for the EW.
View attachment 119531View attachment 119532
== Doublepost prevention - post automatically merged: ==
Lastly, an update on the embankment east of Rushton (generally the Station Rd U/B (SPC3/45) area).
Cantilevers are going in from just before the overlap to the MPA portal.View attachment 119534View attachment 119535








No problem at all Phil!Thanks for that detailed update and pictures 59CosG95.
Does anyone know the future of this footbridge in Great Bowden, Market Harborough. I'm hoping they can just upgrade it and not have to replace it, it fits well with the surrounding scenery.
Oh wow. OK. Thanks for that info.It’s coming down. Recon next year.
Pity its been there for over 120 years, got a book with a pic. taken about 1900 with the foot bridge in the backgroundIt’s coming down. Recon next year.
It will be sad to see the current bridge go, it's great fun climbing it and standing over the tracks when a train thunders under, although I do understand the reasoning for replacing it.It’s coming down. Recon next year.
Does anyone know the future of this footbridge in Great Bowden, Market Harborough. I'm hoping they can just upgrade it and not have to replace it, it fits well with the surrounding scenery.
It’s coming down. Recon next year.
I wonder how the locals felt when the railway was first built.The “Meccano bridge”!
Such a pity. I know electrification has its benefits but it’s a shame that what is an attractive rural route is being well and truly spoiled. That’s the cost of progress, I suppose!
I wonder if a nice structure like that would be attractive to a preserved railway. Probably only if they desperately needed a footbridge.It’s coming down. Recon next year.
Market Harborough to Wigston Jns is committed. There also tenders for the entire MML from Wigston to Sheffield via Derby and from Trent Jns to Nottingham, although exactly how firmly that is set I do not know.Any chance of the wires going further north than Market Harborough?
Apologies once again for my ignorance but how far of a stretch is that from MH up to Wigston? I suppose if these chunks of route are completed successfully that will give central government more confidence to invest in these projects.Market Harborough to Wigston Jns is committed. There also tenders for the entire MML from Wigston to Sheffield via Derby and from Trent Jns to Nottingham, although exactly how firmly that is set I do not know.
Apologies once again for my ignorance but how far of a stretch is that from MH up to Wigston?
Ah ok. That's a decent chunk of route. I hope we get a decision soon around further expansion towards Leicester, Nottingham, Derby and Sheffield.Just a shade over 12 miles.
Wouldn't that leave a gap with no wires between wired sections?August 2022 edition of Modern Railways (pages 36-38 ) Roger Ford states that RS3 will have high priority because of the diversionary route capabilities it brings.
These are extracted from this article. RS = Route Section I believe
RS1 - Kettering to Wigston South (includes Market Harborough and Braybrooke grid feeder)
RS2 – Wigston South to Syston
RS3 – Syston to Trent Junction
RS4 – Sheet Stores Junction to Chaddesden Sidings (Derby)
RS5 – Trent Junction to Nottingham
RS6 – Chaddesden Sidings (Derby) to Toadmoor Tunnel
RS7 – Toadmoor Tunnel to London Road
RS8 – London Road to Sheffield North
The September 2022 Mini-Budget has RS3 as a project with high potential to move to construction at an accelerated pace
This very question was discussed at length back in May:Wouldn't that leave a gap with no wires between wired sections?
What diversionary capabilities would those be? Until the whole of the MML is done, anything using RS3 OHLE would have to be bimode, surely?RS3 will have high priority because of the diversionary route capabilities it brings
Wouldn't that leave a gap with no wires between wired sections?
I think the gap being referred to was Wigston to Syston, i.e. RS2This very question was discussed at length back in May: