Bletchleyite
Veteran Member
Where are you going to put the extra trains? Central is pretty full as it is!
Send them to South Parkway or Hunts Cross. Or the reversing siding, which until the most recent timetable change was basically totally unused.
Where are you going to put the extra trains? Central is pretty full as it is!
No news from Merseyrail or Stadler regarding 777s for a while - anyone know whats going on at the moment and when one will make an appearance?
Thanks
My understanding is that the first unit was due to be delivered to Merseyside in June this year. I seem to remember reading something recently that the first unit was in the final assembly stage, which suggests they may be behind schedule with the build.
The plan changed so the first units are to go to Wildenrath in Germany. If all goes well gauge testing will happen in the Autumn.
Has the suggestion that 507s will need to be retained been officially confirmed anywhere yet? It's been a couple of months since that issue was reported.Apparently they are too long for the reversing siding at Central too.
They might keep them for a couple more years until the 777's are all in full serviceHas the suggestion that 507s will need to be retained been officially confirmed anywhere yet? It's been a couple of months since that issue was reported.
The simulator suite (building) was completed and handed over almost 2 months ago. Not a single driver has been on the machine, make of that what you will.
I am just presuming here, that simulator training would be done along side driver training of the real thing, which is obviously hard with no trains.
Also if it counts towards any kind of competency this has an expiry date of around 6 months usually if its not used.
My understanding is that they have always been scheduled to do so fron 2020 earliest?I'm afraid heads are in the clouds if anyone expects one of these turning a wheel in passenger service anytime soon
The seats look like there made out of wood and everything else looks too flimsy.
The Anglia units were ordered (contract signed) 5 months before the Merseyrail ones and Abellio/Rosco were in talks for 18months before that with Stadler (not a public procurement competition like Merseyrail)Hopefully the head rests won't be, otherwise I can imagine what well ending up happening to them.
My recollection is that first unit was to appear this year, with the roll out compete by end of 2020.
How is it the Anglian flirts seem to have been delivered faster, despite being ordered later?
Hopefully the head rests won't be, otherwise I can imagine what well ending up happening to them.
The first 2 units (001/002) will go to Wildenrath by November - with 003 arriving in Liverpool in November - the first units could be in service as early as February.
Theres yet to be even one word discussed with Aslef over drivers training on the new stock let alone driving it. Plus multiple issues with signalling and ongoing platform issues in a network that just isn't suited for 4/8 car units.
But just that little bit longer sufficient to cause problems at few locations (which JamesSt is referring to)Remember they are short vehicles and so aren't much longer than 3/6 car 50x.
But just that little bit longer sufficient to cause problems at few locations (which JamesSt is referring to)
777001 is through static testing and is now en route to the test track at Wildenrath in Germany to start dynamic testing. Congrats to Stadler.