Following long term engineering work between Piccadilly Gardens and Piccadilly Station severing the Ashton line from the rest of the Metrolink tram network (from Tue 03 Jun, 4:00am - Mon 11 Aug, 1:00am)
Planned arrangements were made for defective / maintenance trams, to allow trams to connect to the main network through the track works, every three weeks during the closure.
Looks like the Ashton Metrolink branch line lost another tram on Thursday 7th afternoon
Until last tram on Sunday 10th, there are now only 5 operational trams on the Ashton line which needs 6 to maintain the 12 min frequency. and thus a gap in service of 24mins with ticket acceptance on local buses.
No Etihad - Piccadilly extras appear to have been working when events are on at Co-op Live arena
Ashton Line - Minor Delay
Fri 08 Aug, 5:00am - Sun 10 Aug, 11:59pm
Due to an earlier tram fault, we are experiencing a minor delay to some services on the Ashton line. Metrolink tickets are being accepted on the 7, 53, 76, 76A, 171, 172, 216, 219, 220, 221, 230 & 231 Bus services.
Some passengers may experience and additional wait for a service, we apologise for any inconvenience caused to your journey.
The Ashton line is linked back up to the Network from first tram on Monday 11th - as is the Trafford Centre line which is curtailed at Wharfside this week
Meanwhile on the Altrincham trams dropped the Network Rail operated Timperley - Altrincham section from around 1830 for 3 hrs on Friday evening:
Due to a signalling fault on the Altrincham line, there is currently no tram service between Timperely - Altrincham.
Tram ticket acceptance is in place on the following local bus services: 15, 23, 25, 245,248, 249, 250, 255, 256, 263, 281, 285, 286, 370, 371.
Looks like a good list of buses taking tickets: but only 249 263 285 286 run anywhere near Timperley tram stop on an evening with 285 286 only every 2hrs!