They have also in the past timed the line conversions (Oldham track and signalling, for phase 1 electrification renewal) at the point NR would have to renew the line anyway
So is that why a scheme that was supposed to happen before Northern Rail took over has only recently happened as the track wasn't due for renewal for another 10 years?