Following LNW-GW Joint's information in #2364 that the autotransformers are not yet commissioned, I suppose it could even be a temporary arrangement.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
20,302
If you don't have some means of coupling the autotransformer centre taps together and for some reason rail continuity breaks due to a failed bond you could you potentially short the two feeders together and boom goes your autotransformer.

So I think this might just be a 0V conductor to ensure that the zero volt centre taps are all shorted together and thus stay at zero volts.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,637
Location
Nottingham
I guess it's analogous to the neutral of a three-phase supply, which normally stays near earth potential but can go way off if there is a big load imbalance or one of the phases goes down. If there's any circumstance where large currents might flow through it then it needs to be insulated because it's a bad idea to have large currents flowing through the earth.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
16,029
Location
St Albans
I guess it's analogous to the neutral of a three-phase supply, which normally stays near earth potential but can go way off if there is a big load imbalance or one of the phases goes down. If there's any circumstance where large currents might flow through it then it needs to be insulated because it's a bad idea to have large currents flowing through the earth.

I think that it's insulated (say to 1kV) so that surges are controlled along the cable and not able to lift the voltage of local support hardware wrt the track. Don't forget that track circuits have isolation components, so bonding at every mast/portal would create disturbances in the track circuits.
 

Olaf

Member
Joined
29 Mar 2014
Messages
1,054
Location
UK
Correct :D:D
--- old post above --- --- new post below ---


You don't have return conductor(rc) on a auto transformer system (atf), the extra wire on the side of the masts is an arieal earth. The main difference between the 2 system to tell them apart is the size of the insulator pots. RC pots are small single dish and usually bolted to the back of the mast/boom. The ATF one are 5/6 dish and mounted higher up on poles or dangling above high above the cantenary. The earth has no insulator and is bolted direct to the mast.

I'm still trying to get my head round how the ATF system works, even a trainer on a recent lineman course wasn't too sure. All I know is the ATF system alows more trains/electrical section than a RC system

There is a section in the old Electrification RUS (2009) that gives a reasonable explanation:
http://www.networkrail.co.uk/browse...ation strategy/networkrus_electrification.pdf
 

PDG1949

Member
Joined
21 May 2014
Messages
323
Location
St. Helens, Merseyside
Were the 319s just out of service equipped with 205 MHz NR VHF NRN (National Radio Network) radios or the UHF 450 MHz CSR ( Cab Secure Radio) system ? If the latter case it will require changing out to the new GSM-R Radio system and therefore this might be one of the Wolverton jobs?
 

Joseph_Locke

Established Member
Joined
14 Apr 2012
Messages
1,878
Location
Within earshot of trains passing the one and half
If you don't have some means of coupling the autotransformer centre taps together and for some reason rail continuity breaks due to a failed bond you could you potentially short the two feeders together and boom goes your autotransformer.

So I think this might just be a 0V conductor to ensure that the zero volt centre taps are all shorted together and thus stay at zero volts.

*edit* covered in #2366 - should have scrolled up a bit further, but anyway:

(All text in quotes are descriptive but gross simplifications)

No, the ATF (or AF) is effectively the "negative" 25kV side of the system, where the OLE is the "positive" 25kV side and the rail is nominally the "zero". The autotransformer system keeps the "positive" 25kV side at 25kV by "borrowing" off the "negative" 25kV side by effectively shifting where "zero" is.

They may also be an earth wire, but this would be connected to the masts, not insulated from them. AF systems will also have a retrun screening conductor (RSC), but that lives in the cable rough, normally.
 
Last edited:

nw-sparks

Member
Joined
10 Oct 2013
Messages
271
Location
Liverpool
Well its easier to start from the beginning - there are three basic types of 25kV installations - rail return, booster transformer and autotransformer.
...

Wow, thanks for that explanation. I had been planning a post on my blog for some time explaining the different electrification systems because I knew we were sometimes using the phrases "earth wire" and "return wire" wrongly.

I held off because I didn't know enough to write a proper explanation. Now you've covered it all clearly.

Thanks again.

Phil
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
The current (pun accidental) autotransformer discussion was started by #2350. Can somebody point us to some pictures of phase 1 where we can see the conductors in question and see whether they're connected directly to the masts or on small insulators?

This question is NOT about autotransformer feeds which we all know are on big insulators just like those used for the contact and catenary wires.
 
Last edited:

Class377/5

Established Member
Joined
19 Jun 2010
Messages
5,594
Were the 319s just out of service equipped with 205 MHz NR VHF NRN (National Radio Network) radios or the UHF 450 MHz CSR ( Cab Secure Radio) system ? If the latter case it will require changing out to the new GSM-R Radio system and therefore this might be one of the Wolverton jobs?

The 319s were the first Thameslink units fitted with GSM-R.
 

steverailer

Member
Joined
15 Feb 2013
Messages
169
The current (pun accidental) autotransformer discussion was started by #2350. Can somebody point us to some pictures of phase 1 where we can see the conductors in question and see whether they're connected directly to the masts or on small insulators?

This question is NOT about autotransformer feeds which we all know are on big insulators just like those used for the contact and catenary wires.

On Phase 1 the earth wire is direct onto the mast not on an insulator. No pics, but know how it is because I fastened some of the bolts :D:D Its a u shapped saddle bolted to the mast with 1 bolt and holds the wire in with 2 clamps and 4 bolts.
 

driver_m

Established Member
Joined
8 Nov 2011
Messages
2,248
Been mentioned previously but Allerton depot should be getting the juice back on this Sunday, also heard something about a neutral section getting put in too at Wavertree on the Chat Moss line, don't know how true this is, but the Slow lines at Edge Hill are de-wired at the moment. 221's are running in and out of Lime St for the first time in ages on Sunday as a result of the OHLE being off as mentioned elsewhere.
 

Geeves

Established Member
Joined
6 Jan 2009
Messages
2,631
Location
Rochdale
How about this for a neutral section!

[Youtube]q55EfuVYNW0[/Youtube]

Back in Manchester they were busy attaching the droppers and registration arms near to the station today but they are still short of the stanchions on the way into the station, not even any sign of the foundations on a couple.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,492
Location
Preston Lancs
Back in Manchester they were busy attaching the droppers and registration arms near to the station today but they are still short of the stanchions on the way into the station, not even any sign of the foundations on a couple.

Victoria I assume?
 

PDG1949

Member
Joined
21 May 2014
Messages
323
Location
St. Helens, Merseyside
How about this for a neutral section!

Back in Manchester they were busy attaching the droppers and registration arms near to the station today but they are still short of the stanchions on the way into the station, not even any sign of the foundations on a couple.

When putting in the metalwork west of Victoria, do they appear to have made any provision for the intended Ordsall Chord link-up ?
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
When putting in the metalwork west of Victoria, do they appear to have made any provision for the intended Ordsall Chord link-up ?

If I remember correctly, and if I observed correctly (I was actually trying to look while driving a car on Trinity Way), as you look along the viaduct going from Ordsall Lane Junction towards Salford Central, at the point where the Chord will begin to come in from the right, the supports switch to being cantilevers with supports on the left.

Now I think about it, I remember that the Chord plans in the first round of public consultation showed "proposed OHLE supports" and "existing OHLE supports" in that area. This was confusing as there were no supports in place at the time. I concluded that the supports shown as "existing" were the ones that it was originally proposed to put in, before the electrification design was changed to allow for the Chord.
 
Last edited:

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,637
Location
Nottingham
It could be that some supports will turn out to be in the wrong places for the Chord, simply because the new viaduct is still being designed so nobody knows exactly where the OLE supports either need to go or are able to be supported by the new structure. So "existing" on that drawing could have meant "pre-existing" or "previously proposed". When different projects in the same place are authorised at different times, this sort of thing is likely to arise at the interfaces.

However the twin track cantilevers sound like the right way to go. Even if they need moving eventually, they should be able to keep the existing OLE operational while the Chord viaduct and junction are being built on the other side of the line.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
16,029
Location
St Albans
It could be that some supports will turn out to be in the wrong places for the Chord, simply because the new viaduct is still being designed so nobody knows exactly where the OLE supports either need to go or are able to be supported by the new structure. So "existing" on that drawing could have meant "pre-existing" or "previously proposed". When different projects in the same place are authorised at different times, this sort of thing is likely to arise at the interfaces.

However the twin track cantilevers sound like the right way to go. Even if they need moving eventually, they should be able to keep the existing OLE operational while the Chord viaduct and junction are being built on the other side of the line.

It's that expression again, just what does 'pre-existing' mean, (in the UK)?
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,637
Location
Nottingham
I take "pre-existing" to mean not necessarily existing at the time of producing a particular design drawing/document, but expected to be existing prior to whatever the drawing/document is seeking to change. Another useful one is that "removed" means that something is physically taken away, and "deleted" means it was previously intended to be installed but is now intended not to be installed.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
16,029
Location
St Albans
I take "pre-existing" to mean not necessarily existing at the time of producing a particular design drawing/document, but expected to be existing prior to whatever the drawing/document is seeking to change. Another useful one is that "removed" means that something is physically taken away, and "deleted" means it was previously intended to be installed but is now intended not to be installed.

The expression seems to be from the US and relates normally to insurance policy maschinations. The OED mentions it in that context only. What's wrong with previous(ly) or even prior, (depending on the grammar context?
This is not a whinge at you, just an observation about English usage and inheriting made-up wording that can confuse where words that we have been using for years can do the job.
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,906
Location
North
The expression seems to be from the US and relates normally to insurance policy maschinations. The OED mentions it in that context only. What's wrong with previous(ly) or even prior, (depending on the grammar context?
This is not a whinge at you, just an observation about English usage and inheriting made-up wording that can confuse where words that we have been using for years can do the job.

I hate this creeping Americanisation of the UK, language, limos, proms, butt.
 

8A Rail

Established Member
Joined
6 Dec 2012
Messages
1,351
Location
Mars
Just a quick one - a mast put up at Whiston Station about 2 months ago was taken down yesterday! Strange put true!
 

Geeves

Established Member
Joined
6 Jan 2009
Messages
2,631
Location
Rochdale
In regards to my 'air-gap' link, its actually of trains in Queensland rather than Victoria :D

Here is a photo I took of the location of the future chord. As Snowball previously explained you will notice the metal work switching from one side to the other. All ready for the construction of the chord

IMG_20140701_155347881_zpse0798c1b.jpg


As far as I know and the plans Ive seen the chord design is done, they just need the money and English heritage to get there arses in gear.
 