I presume that if the OHLE is live on 03/08/2013, have the remaining missing sections been completed?
I presume that if the OHLE is live on 03/08/2013, have the remaining missing sections been completed?
I presume that if the OHLE is live on 03/08/2013, have the remaining missing sections been completed?
Nope, doubt they will be completed for another couple of weeks!!!!
Alot around Kenyon and NLW has been registered, but the vast majority of the rest still has to be done, with alot still tied up with temp droppers and no reg arms. Several wire runs only on temporary anchors not the tensioners. Still some cantelevers missing and earth and ATF wiring to do.
Currently NWR are doing the main wiring at 4 times the cost of the original team and doing less per night.
Current word on site is completed around 6th September, but can't see it myself. There are alot of machines and staff on everynight trying to get it completed, and may see an improvement after the weekend block.
So perhaps we should not complain if they meet that date.From 3rd July, Network Rail started to commission and test the electrical equipment with the aim of having the whole system energised by 2nd September
Currently NWR are doing the main wiring at 4 times the cost of the original team and doing less per night.
I think we should consider Saturday as a major milestone. A point in railway history. The first completed electrification project (treating each phase separate in my eyes as they all allow changes to services) of what could be 40 years of continuous electrification. Well done to Network Rail and all the contractors... Lets hope this is only the beginning!
Or Airdrie to Bathgate and Haymarket in 2010. Or Crewe Kidsgrove in 200e. Or HS1 in 2003. Or. ...
Yes but there were gaps between those schemes.
I'm saying that the start of the current long continuous period of electrification was the start of the works on the Paisley Canal branch in early 2012. By the time that was finished, the Chat Moss works had started, and by the time the Chat Moss is finished, GWML works will have started, and by the time that's finished something else will have already started, and so on.
Fair play, apologies i forgot about that scheme. (which is annoying as i did my dissertation on electrification and talked alot about it!)
Yes but there were gaps between those schemes.
I'm saying that the start of the current long continuous period of electrification was the start of the works on the Paisley Canal branch in early 2012. By the time that was finished, the Chat Moss works had started, and by the time the Chat Moss is finished, GWML works will have started, and by the time that's finished something else will have already started, and so on.
In fact, there might be 5 or more schemes running concurrently in CP5.
We already have: EGIP/Whifflet, North West and GW.
Then add TP and MML from 2015.
You also have to add E-W, local stuff in the Midlands (Bromsgrove, Rugeley) and the electric spine work, the Cardiff Valleys, and now GOBLIN and perhaps Windermere.
I still worry that this will stretch Network Rail and the contractors beyond what's manageable.
It's not that long since there were posts on this forum saying all the electrification skills had left the country (around the time of the Rugby/Liverpool St overrun fiascos).
I thought I read somewhere that MML was being accelerated because some thinking had already been done on how to do it, in contrast to the electric spine which was sprung out of nowhere and will be decelerated.
What's the goblin scheme?
I thought I read somewhere that MML was being accelerated because some thinking had already been done on how to do it, in contrast to the electric spine which was sprung out of nowhere and will be decelerated.
I also suspect that there's simply less demand for the Electric Spine. I'm sure I've seen numerous reports about freight operators being pretty 'meh' about the whole thing. The only passenger service that might benefit from it would be XC's Bournemouth-Manchester, and there's no plans to acquire any EMUs to take advantage of it.
Yep, another comment from my dissertation saying we need to maintain steady no rushing and keep a solid skills base. I think network rail have been pushed too far personally and some of the projects will be finished not early but mid CP6, especially MML.
Wiring update:
A single wire run (the earth wire?) on each side now extends across the gap between the old and new wires either side of Parkside.
At Ordsall Lane, another short single wire extension from the west has been put in place on the Down line.
But there are still about 12 structures there without any wires, ironically right by the electrification depot.
The gap at Glazebury is as long as ever. About 30-odd structures are devoid of wires.
On the Wigan line, foundations have appeared on the north side of the embankment through the Pilkington works area, west of St Helens Central.
Any more progress east of St Helens?
Great to be hearing this!
I wonder if they will be putting up gantries on the Carr Mill bridge, like those in the Castlefield viaduct?
Mind you, they would have to do the same with the Sankey Valley viaduct at Earlestown.
Sorry for the delay, I wasn't ignoring your post but wondering much the same. St Helens and Garswood has been mostly complete base wise for a couple of weeks but I noticed the odd one or two extra kept popping up. A couple of standard concrete bases are now on Carr Mill bridge over the East Lancs, however nothing at the viaduct over the dam itself. There probably isn't space and it'll be something fancy as you suggest!
In other news, work equipment and teams still seem in place by Arch Lane bridge at Garswood.