This morning a fire destroyed about 100 cables near Rotterdam Stadion including the cables needed to control the points and signals at this major junction which connects the main line with the freight and high speed lines.
The current estimation is that they need until Thursday 18:15 to repair the cables. All Eurostar trains between Amsterdam and London are cancelled between Amsterdam and Brussels, the Eurostar trains between Amsterdam and Paris are diverted via Utrecht and suffer from significant delays.
The freight line itself is still in operation, but freight trains from the port of Rotterdam heading north will have to be diverted the next days as well.
The incident was at a very vital point in the Dutch rail network as all lines converge on the one tunnel under the river here, the next river crossing being 50km upstream.
A few pictures are on the site of the infrastructure manager ProRail: https://www.prorail.nl/nieuws/geen-treinen-rond-rotterdam-stadion-door-stroomstoring
The current estimation is that they need until Thursday 18:15 to repair the cables. All Eurostar trains between Amsterdam and London are cancelled between Amsterdam and Brussels, the Eurostar trains between Amsterdam and Paris are diverted via Utrecht and suffer from significant delays.
The freight line itself is still in operation, but freight trains from the port of Rotterdam heading north will have to be diverted the next days as well.
The incident was at a very vital point in the Dutch rail network as all lines converge on the one tunnel under the river here, the next river crossing being 50km upstream.
A few pictures are on the site of the infrastructure manager ProRail: https://www.prorail.nl/nieuws/geen-treinen-rond-rotterdam-stadion-door-stroomstoring
An inspection has revealed that at least 100 cables require repair. This means the cables must be sorted individually and then welded. While the work is not particularly complex, it is time-consuming. Four welders will work in two shifts—the maximum operational capacity possible on-site. The necessary equipment is also available.
Once the repair work is complete, the cables—each serving a different function—must be tested. This process also takes a considerable amount of time.
No trains
Nothing is yet known about the cause of the fire that resulted in the damage. In any case, the consequence is that no trains are running between Rotterdam and Barendrecht, between Rotterdam and Breda, or towards the Kijfhoek freight yard. This also applies to high-speed trains. We sincerely regret the inconvenience caused to passengers, shippers, and transport operators.