Lostock- Wigan electrification

Status
Not open for further replies.

Bovverboy

Established Member
Joined
1 Dec 2013
Messages
2,098
Bearing in mind that Springs Branch is being trumpeted as the new principal base for the 319s, does anyone know what the future holds for Allerton?

Allerton is the main depot for the electric fleet on the west side - Springs Branch will be a servicing point, in the same way as Blackpool is.

I see that, according to Wikipedia, Springs Branch is going to provide 'maintenance, fuelling, and train washing facilities'. What sort of 'maintenance' is likely to take place?
I'm certainly dubious when it comes to the totals quoted, i.e. facilities for twenty-four EMUs and eight DMUs. Twenty-four EMUs implies that the entire Northern 319 fleet is going to be based there, which, according to AMD (above), it is not. Eight DMUs, well that's pretty well the total which currently stable at North Western/Wallgate/Up Sidings. I would have thought that DMU stabling would be increased by at least 50%, to eliminate unnecessary running which now takes place between Newton Heath and various points to the west.
https://en.wikipedia.org/wiki/Wigan_Springs_Branch_TMD
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Greybeard33

Established Member
Joined
18 Feb 2012
Messages
4,335
Location
Greater Manchester
I see that, according to Wikipedia, Springs Branch is going to provide 'maintenance, fuelling, and train washing facilities'. What sort of 'maintenance' is likely to take place?
I'm certainly dubious when it comes to the totals quoted, i.e. facilities for twenty-four EMUs and eight DMUs. Twenty-four EMUs implies that the entire Northern 319 fleet is going to be based there, which, according to AMD (above), it is not. Eight DMUs, well that's pretty well the total which currently stable at North Western/Wallgate/Down Sidings. I would have thought that DMU stabling would be increased by at least 50%, to eliminate unnecessary running which now takes place between Newton Heath and various points to the west.
https://en.wikipedia.org/wiki/Wigan_Springs_Branch_TMD
The Wikipedia article references this Manchester Evening News story, dated April 2018, as the source. That stated:
Network Rail is adapting an existing freight yard at Springs Branch railway sidings in Ince-in-Makerfield to stable and maintain 24 electric and eight diesel trains.
I suspect that "eight diesel trains" meant the eight 769s, rather than 15x DMUs. So implying the plan (at that time) was to dedicate Springs Branch to the stabling and light maintenance of the fleet of 32 x 319s/769s (128 carriages).

I do not think that implied that every unit would be stabled there every night, nor did it rule out heavy maintenance remaining at Allerton.

And plans may well have evolved over the intervening 15 months....
 

WatcherZero

Established Member
Joined
25 Feb 2010
Messages
10,272
Light maintenance generally means external and internal cleaning, emptying and flushing of effluent and other fluid tanks, refuelling and possibly an inspection pit/shed.
 

Glenn1969

Established Member
Joined
22 Jan 2019
Messages
1,983
Location
Halifax, Yorks
A post on another thread mentions March as a possible date for the 769s to enter service but I doubt we are going to see Lostock to Wigan wired any time soon
 

Gathursty

Established Member
Joined
31 May 2011
Messages
2,649
Location
Wigan
I imagine if Wigan Wallgate tunnel/bridge etc.. had a higher clearance, electrification would be a formality. I imagine that's why it's put in the 'too hard to fix right now' pile.

To raise the height of Wallgate at the station, you'd basically have to rebuild the southern entrance to Wigan town centre affecting several buildings and businesses, not to mention probable issues with access to Wigan North Western and utility works.
 

WatcherZero

Established Member
Joined
25 Feb 2010
Messages
10,272

ic31420

Member
Joined
23 Aug 2017
Messages
392
Location
United Kingdom
O
I imagine if Wigan Wallgate tunnel/bridge etc.. had a higher clearance, electrification would be a formality. I imagine that's why it's put in the 'too hard to fix right now' pile.

To raise the height of Wallgate at the station, you'd basically have to rebuild the southern entrance to Wigan town centre affecting several buildings and businesses, not to mention probable issues with access to Wigan North Western and utility works.

I believe the Wallgate bridge suffered a minor collapse a fee years back and is currently propped.

About 20 years ago my old man was a site engineer for a railtrack subbie. One job he worked on was around Wallgate. I remember him saying then that the bridge was knackered. When I told him about the props he reiterated it. He thinks the buildings atop and either side are owner by the railway and let. It was proposed then to slowly not renew he leases and complete significant works in partnership with the council who harbour(D)a desire to regenerate that area. A lot has changed since then
 

Mathew S

Established Member
Joined
7 Aug 2017
Messages
2,167
O


I believe the Wallgate bridge suffered a minor collapse a fee years back and is currently propped.

About 20 years ago my old man was a site engineer for a railtrack subbie. One job he worked on was around Wallgate. I remember him saying then that the bridge was knackered. When I told him about the props he reiterated it. He thinks the buildings atop and either side are owner by the railway and let. It was proposed then to slowly not renew he leases and complete significant works in partnership with the council who harbour(D)a desire to regenerate that area. A lot has changed since then
The aspiration is that both stations, and the adjoining buildings and infrastructure, will be extensively rebuilt alongside / as part of HS2. Honestly, I cannot imagine anything major happening until then.
 

a_c_skinner

Established Member
Joined
21 Jun 2013
Messages
1,699
It is certainly an area that would benefit from regeneration. Surely the climate change/air quality agenda will tip the balance for projects like electrification to Southport?
 

Bertie the bus

Established Member
Joined
15 Aug 2014
Messages
3,216
Unfortunately regeneration doesn't just happen because an area needs it. See the Preston Tithebarn redevelopment as a classic example.

Slightly more on topic, I thought the electrification was going to North Western.
 

Glenn1969

Established Member
Joined
22 Jan 2019
Messages
1,983
Location
Halifax, Yorks
But is there any plan to electrify this line at present? Thought it had been cancelled when the Windermere branch wires were cancelled ?
 

Mathew S

Established Member
Joined
7 Aug 2017
Messages
2,167
But is there any plan to electrify this line at present? Thought it had been cancelled when the Windermere branch wires were cancelled ?
I don't think it was ever actually cancelled, because I don't think it was ever actually confirmed as going ahead.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556
I don't think it was ever actually cancelled, because I don't think it was ever actually confirmed as going ahead.
It was announced as NWEP Phase 7, but never officially cancelled. Assumed to have been placed in the 'deferred' pile.
 