Hello all.
Looking for a bit of advice as it's been a while since I've had a Delay Repay dispute and before I get all "Outraged, Tunbridge Wells" and start email the chairman's office.
Back on the 5th July I was travelling from Portlethen to Meadowhall. I was alone on that part of the journey and went via Stirling where I was meeting my cousin and we were continuing our journey.
Tickets held for the outbound journey were:-
Portlethen - Arbroath (Advance single)
Arbroath - Stirling (Advance single)
Stirling - Alnmouth (Two Together advance single)
Alnmouth - Meadowhall (Two Together advance single)
Return journey tickets:-
Meadowhall - Newcastle (Two Together advance single)
Newcastle - Stirling (Two Together advance single)
Stirling - Arbroath (advance single)
Arbroath - Portlethen (advance single)
On the day in question all trains heading south out of Newcastle were off for about 4 hours after someone was hit by a train just outside Newcastle.
My understanding was that due to the length of delay I should be entitled to a full refund of the return journey however LNER are saying that this is not the case as I used split tickets.
So far they have refunded me £58.10 which is the cost of the tickets between Stirling and Meadowhall however this makes no sense to me as in the email they sent they've said "On review of your claim, I can see that your tickets are advance single tickets, and under the conditions of travel, you are entitled to 100% of the cost of a single ticket if your delay was over 60 minutes" and my Stirling to Alnmouth section of the journey wasn't delayed.
The initial email from LNER was on 20th July and I responded telling them then I thought that the calculation was wrong, they then responded on 30th July saying that the calculation was correct so I emailed back saying I still didn't agree and asking them to escalate my dispute. So far I've had no further response to my request.
It is worth continuing or am I chasing a lost cause as I'm not entitled to any further refund?
Looking for a bit of advice as it's been a while since I've had a Delay Repay dispute and before I get all "Outraged, Tunbridge Wells" and start email the chairman's office.
Back on the 5th July I was travelling from Portlethen to Meadowhall. I was alone on that part of the journey and went via Stirling where I was meeting my cousin and we were continuing our journey.
Tickets held for the outbound journey were:-
Portlethen - Arbroath (Advance single)
Arbroath - Stirling (Advance single)
Stirling - Alnmouth (Two Together advance single)
Alnmouth - Meadowhall (Two Together advance single)
Return journey tickets:-
Meadowhall - Newcastle (Two Together advance single)
Newcastle - Stirling (Two Together advance single)
Stirling - Arbroath (advance single)
Arbroath - Portlethen (advance single)
On the day in question all trains heading south out of Newcastle were off for about 4 hours after someone was hit by a train just outside Newcastle.
My understanding was that due to the length of delay I should be entitled to a full refund of the return journey however LNER are saying that this is not the case as I used split tickets.
So far they have refunded me £58.10 which is the cost of the tickets between Stirling and Meadowhall however this makes no sense to me as in the email they sent they've said "On review of your claim, I can see that your tickets are advance single tickets, and under the conditions of travel, you are entitled to 100% of the cost of a single ticket if your delay was over 60 minutes" and my Stirling to Alnmouth section of the journey wasn't delayed.
The initial email from LNER was on 20th July and I responded telling them then I thought that the calculation was wrong, they then responded on 30th July saying that the calculation was correct so I emailed back saying I still didn't agree and asking them to escalate my dispute. So far I've had no further response to my request.
It is worth continuing or am I chasing a lost cause as I'm not entitled to any further refund?
Last edited: