Seeing as you all seem to think it would be better to have the speed improvments on the District Line (despite there only be 1 train per 2-hours over that line in the plan I suggested whereas there's be more on the Llanelli-Carmarthen stretch) how much would it be to improve Llangennech to Morriston to 90mph? How much cheaper for a less drastic upgrade to 75mph?
The going rate just to answer that question to within +/-50% tolerance is £25k. Happy to oblige if anyone fancies a whip round. Although I would suggest there are other lines more deserving of this sort of study than this one.
Anyway, these are the things that need to be studied (in this example), and solutions found if the existing infrastructure is not suitable for the higher speed:
Track (pretty simple as there's no pointwork AFAIK)
1) Geometry
2) full assessment of current condition of all components
3) current track quality, and effect of higher speeds on this
4) additional maintenance requirements
Signalling
1) sighting distances
2) spacing between signals for braking distances
3) location of TPWS grids and AWS magnets
4) reassessment of signal risk assessment for each signal that protects a junction or LX
5) types of LX
5) LX strike in locations
6) LX sighting on approach (for unsupervised crossings) to allow sufficient crossing time
7) Re-evaluate risk assessment for every LX
Structures
1) assessment of strength of all underbridges and embankments
2) assessment of underbridges for resonance effects (unlikely in this case)
3) assessment of gauge clearance at every lineside structure to allow for increased kinematic envelope at greater speed. This is also required for train:train passing clearances.
4) check of tunnels to confirm aerodynamic affect of increased speed on passenger comfort, tunnel lining, and passing freight trains
5) re-evaluate risk for any underbridges that are regularly struck by road vehicles, and an locations on the known risk register for lineside incursions (i.e. road vehicles coming through the fence)
Other
1) check of all workforce safety arrangements to provide sufficient warning time for on track staff
2) check of all operational documentation relating to the line