Liverpool Baltic Station - opening planned late 2027

Status
Not open for further replies.

karlbbb

Member
Joined
26 Jul 2009
Messages
460
Overview website: https://liverpoolcityregion-ca.gov.uk/liverpoolbaltic

About the Project​

Mayor Steve Rotheram, the Liverpool City Region Combined Authority and project partners are currently developing ambitious plans for a new station in Liverpool’s Baltic Triangle and want to hear your views.
  • Plans for Liverpool Baltic station include step-free access from street to train, passenger waiting facilities, fully accessible passenger toilets, secured monitored cycle parking and links to an enhanced local active travel network.
  • The £100m station scheme is part of Mayor Rotheram’s “Merseyrail for All” commitment to reach communities that are currently not connected to the local rail network by utilising the region’s new pioneering battery powered technology, which has made it possible to extend the lines beyond current boundaries.


Liverpool Baltic is due to be build on the site of the old St. James station. Given the station is in a cutting, it would appear that work will be extensive, with a lengthy closure of the whole line between Central and Hunts Cross (although realistically only to South Parkway as Hunts Cross West Junction and Hunts Cross will be open for traffic out of Lime Street). Work was originally penned to start in 2025 with opening late 2027, but we're already creeping into 2026 and no sign of work.

I thought I'd open this thread to separate out the station construction talk from the 777 thread under Rolling Stock.
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
113,736
Location
"Marston Vale mafia"
I've created a speculative thread to sit alongside this:

 

karlbbb

Member
Joined
26 Jul 2009
Messages
460
Do National Rail ever make plans for the track infrastructure available in the same manner as above? I'd be interested to see if there's anything past a possible resignal, perhaps adding a new turnback?
 
Joined
28 Oct 2017
Messages
253
Work was originally penned to start in 2025 with opening late 2027, but we're already creeping into 2026 and no sign of work.
This is the engineering work poster at Bromborough this evening.
(Poster says "There are no planned engineering works")
 

Attachments

  • IMG_20260115_170501Z.jpg
    IMG_20260115_170501Z.jpg
    2.5 MB · Views: 89

Bevan Price

Established Member
Joined
22 Apr 2010
Messages
8,342
Might it be better just to do most of the work at nights and weekends ?
 

jamesst

Established Member
Joined
4 May 2011
Messages
1,373
Location
Merseyside
This is the engineering work poster at Bromborough this evening.
(Poster says "There are no planned engineering works")
Don't read anything into that, they often change those last minute

== Doublepost prevention - post automatically merged: ==

Might it be better just to do most of the work at nights and weekends ?
Theres a limit to how much you can do and still have trains running during the week
 
Joined
28 Oct 2017
Messages
253
Don't read anything into that, they often change those last minute
I realise that. It was more of a response to the comment which started this thread that they had better get on with communicating such a disruptive closure to passengers. Clearly no sign of that yet!
 
Joined
28 Oct 2017
Messages
253
and hasn't been updated since November based on the text at the bottom left.
True (as a passenger you have to assume it is still current, in spite of it not saying when there is nothing planned until. Which is pretty rubbish). The Merseyrail web site says the same thing at

There are currently no planned engineering works on our network.
 

M28361M

Member
Joined
15 May 2014
Messages
684
Location
Liverpool
Don't read anything into that, they often change those last minute
True for the occasional weekend or evening closure, but I'd be very surprised if that happened for something as major as a months-long closure for building a new station.

Anyway, it looks like the station is not getting built just yet. According to the Liverpool Echo, there are significant delays with the project:-
A new £100m Liverpool train station set to serve the thriving Baltic Triangle area of the city centre is set to be significantly delayed, the ECHO understands. Plans for the flagship new station were approved by Liverpool City Council in April last year after the plans were formally submitted by Mayor Steve Rotheram's Liverpool City Region Combined Authority (CA) in November 2024.

However, the ECHO has been told that nine months on from permission for the major project being granted, the CA is still yet to appoint a main contractor. The ECHO understands there is now expected to be a significant delay in the delivery of this crucial project, which leaders had previously said would be completed by the end of next year.

Following our questions, Mayor Rotheram has told this newspaper he is not happy about the delays and is pushing his teams to find ways to move faster on the project. He said the national picture, including the fallout from HS2 has had an impact.

The planned station, seen as a key part of the Mayor's 'Merseyrail for All' pledge, will be created by redeveloping the disused former St James Station, which lies beneath the Baltic Triangle - a former industrial area now filled with creative and hospitality businesses between the city centre and the south of the city.

The application site involves an existing cutting to the Northern Line of the Merseyrail network, located midway between Liverpool Central Station and Brunswick Station, where an underground train station once stood but was closed in 1917 during the First World War.

It was hoped that work on the station could have started at the back end of last year, with a hopeful completion date of late 2027, it was later suggested that March 2028 was a more likely opening date. But having investigated the situation, the ECHO understands this could now be delayed again, with a main contractor still yet to be appointed.

This would be yet another additional delay for the key project. When it was first announced in 2022, it was estimated that construction would begin in 2024 and be completed before the end of 2025. It was also hoped the station could cost closer to £80m, before this was later revised to £100m.

As with most project delays, it is likely that an extended construction period could also result in an increased final cost of the project.

The ECHO understands when public organisations like a Combined Authority want to build train stations, they can either ask Network Rail - the owner and infrastructure manager of most of the nation's railway - to carry out the build, or they can go out externally for a different contractor.

According to a new statement from the CA, appointing the main contractor for the Liverpool Baltic Station is the 'next step in this process', and the organisation said more will be announced on this soon. It is not clear why a contractor has yet to be appointed on the project.

A Liverpool City Region Combined Authority spokesperson said: “Liverpool Baltic is a central part of Mayor Rotheram’s vision to transform public transport across the city region. It complements a programme of major investment, including our £500m publicly owned trains, taking buses back under public control, and plans for a new rapid transit system.

“Once delivered, Liverpool Baltic will be the third new Merseyrail station built since Mayor Rotheram took office in 2017, with Maghull North and Headbolt Lane already completed. A further three new stations are planned for Carr Mill in St Helens, Woodchurch on the Wirral, and Daresbury in Halton.

“Appointing the main contractor is the next key step in this process, and we have been exploring a range of delivery methods to ensure the project is delivered to the highest standard – more will be announced on this soon.

“As with any complex infrastructure scheme, particularly one that involves a new station in a deep railway cutting on an operational line, it is important the project is carefully considered. The Mayor has been actively pushing the organisation to accelerate delivery wherever possible, while ensuring the programme remains achievable and the station is delivered to the highest standards.

“Progress is continuing well, with early site preparation work scheduled to begin this year, laying the groundwork for the main construction phase to follow. New junctions and road layouts including space for active travel will also be included as part of the scheme.”

In a candid statement to the ECHO, Mayor Rotheram admitted his frustrations at further delays on the project.

He said: “When the Combined Authority first announced the station at Liverpool Baltic, we gave a target of 2028 based on what we believed was achievable - and that was a timeline set in good faith. We knew it would be a complicated job: it’s a deep-cutting site, on a live rail line, with all the engineering challenges that brings but have still tried to do all we could to bring that forward.

“But what’s changed since then is the national picture. Network Rail, who still deliver most of this country’s rail infrastructure, have seen their capacity squeezed with the fallout from HS2 tying up resources and limiting their ability to take on new work. That’s had a real impact.

“But the reality is that we’ve secured the funding, and I’ve been pushing our teams hard to find other ways to move faster, including bringing in an alternative contractor. But there are a limited number of contractors licensed to work on the railways that we are able choose from.

“I’m not someone who is ever happy about things being delayed. I wanted us on site quicker. I’d rather be up front with people now than risk overpromising and underdelivering. This project is still happening, and we will see it through to delivery.”

A Network Rail spokesperson tod the ECHO: "We work closely with the Liverpool City Region Combined Authority and all our partners in the region. Liverpool Baltic Station is an exciting project and we will be pleased to support its development."
 

FrontSideBus

On Moderation
Joined
11 Feb 2025
Messages
451
If the works on Broad Green are anything to go by, we will be waiting a LONG time for work to actually begin!
 

TheSel

Member
Joined
10 Oct 2017
Messages
1,168
Location
Southport, Merseyside
BBC News now reporting that the station's opening is delayed to 2029.

Link here

Headline quote: Liverpool's new Baltic railway station delayed.

Content quote:

Plans for a new train £100m station in part of Liverpool will be delayed, the city's region's mayor has confirmed.

Liverpool Baltic station, in the Baltic Triangle area of the city, was due to open in 2027, but is now expected to open in 2029.


(Edited at moderator's request to comply with forum rules)
 
Last edited:

Ellis101

Member
Joined
31 Aug 2022
Messages
98
Location
Liverpool
BBC News now reporting that the station's opening is delayed to 2029.

Link here

Headline quote: Liverpool's new Baltic railway station delayed.

Content quote:

Plans for a new train £100m station in part of Liverpool will be delayed, the city's region's mayor has confirmed.

Liverpool Baltic station, in the Baltic Triangle area of the city, was due to open in 2027, but is now expected to open in 2029.
The article quotes that

Speaking on BBC Radio Merseyside Metro Mayor of the Liverpool City Region said the delay was a result of Network Rail being currently unable to do the work on the Northern Line station, as it faced other demands including the Northern Powerhouse Rail and the Trans Pennine upgrade.

What?

We've seen HS2 cut in half, NPR is still in the concept stage and yet because of the railway being upgraded between Manchester-York we have to wait longer for a station we've already paid for?
 
Last edited by a moderator:

Baxenden Bank

Established Member
Joined
23 Oct 2013
Messages
4,759
The article quotes that



What?

We've seen HS2 cut in half, NPR is still in the concept stage and yet because of the railway being upgraded between Manchester-York we have to wait longer for a station we've already paid for?
Already paid for?
 

jamesst

Established Member
Joined
4 May 2011
Messages
1,373
Location
Merseyside
The article quotes that



What?

We've seen HS2 cut in half, NPR is still in the concept stage and yet because of the railway being upgraded between Manchester-York we have to wait longer for a station we've already paid for?
Notice nothing bad is ever the fault of the metro mayor...
 