Over the past few weekends, engineering works has been taking place around Chesterfield....what I am slightly bemused and puzzled with is that a 'limited service' is still being provided for passengers heading north from Chesterfield (Northern,EMR and XC at various times throughout the day using platform 3) via the Old Road but strangely a Southbound service is not and everything is using the UBH.....is there a reason for this and why cant trains stop heading south to provide a service either way???

Dudz
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

yorkie

Forum Staff
Staff Member
Administrator
Joined
6 Jun 2005
Messages
78,508
Location
Yorkshire
Over the past few weekends, engineering works has been taking place around Chesterfield....what I am slightly bemused and puzzled with is that a 'limited service' is still being provided for passengers heading north from Chesterfield (Northern,EMR and XC at various times throughout the day using platform 3) via the Old Road but strangely a Southbound service is not and everything is using the UBH.....is there a reason for this and why cant trains stop heading south to provide a service either way???

Dudz
Could this be due to capacity constraints? It's a 4 track railway but if you send everything through just one track at Chesterfield station, it may be difficult to fit everything in. Any southbound passenger train calling at Chesterfield would block all northbound trains for a few minutes.
 

LowLevel

Established Member
Joined
26 Oct 2013
Messages
8,928
As mentioned - pathing is too tricky because trains can only use platform 3.
 

johnnychips

Established Member
Joined
19 Nov 2011
Messages
3,826
Location
Leeds
Over the past few weekends, engineering works has been taking place around Chesterfield....what I am slightly bemused and puzzled with is that a 'limited service' is still being provided for passengers heading north from Chesterfield (Northern,EMR and XC at various times throughout the day using platform 3) via the Old Road but strangely a Southbound service is not and everything is using the UBH.....is there a reason for this and why cant trains stop heading south to provide a service either way???

Dudz
What is UBH?
 

Dood75

Member
Joined
8 May 2019
Messages
307
What is UBH?
Up Barrow Hill

== Doublepost prevention - post automatically merged: ==

Maybe it’s a platforming issue as they can only use platform 3 I believe?
Looking at RTT for this weekend for example, most if not all hours between roughly 20/25 past the hour to 10 to the hour, nothing passes Chesterfield....what I cant work out is why say 2 or 3 trains northbound stop , but none south...why not drop a northbound stopper to allow at least 1 southbound stopper to balance things up...its pointless providing a service to go north if you cant get back other than via rail replacement
 
Last edited:

Llandudno

Established Member
Joined
25 Dec 2014
Messages
2,753
Location
Matlock
Up Barrow Hill

== Doublepost prevention - post automatically merged: ==


Looking at RTT for this weekend for example, most if not all hours between roughly 20/25 past the hour to 10 to the hour, nothing passes Chesterfield....what I cant work out is why say 2 or 3 trains northbound stop , but none south...why not drop a northbound stopper to allow at least 1 southbound stopper to balance things up...its pointless providing a service to go north if you cant get back other than via rail replacement
Freight?
 

Mugby

Established Member
Joined
25 Nov 2012
Messages
2,138
Location
Derby
I passed through Chesterfield on both days, going north on Saturday and returning on Sunday.

On Saturday afternoon about 1400, I saw no work of any description being carried out. On Sunday, the Up Main through the platform was being relayed.
Couldn't help wondering why Platforms 1 and 2 were not being used on Saturday when there was no work going on.
 

syorksdeano

Member
Joined
7 Jan 2011
Messages
780
I passed through Chesterfield on both days, going north on Saturday and returning on Sunday.

On Saturday afternoon about 1400, I saw no work of any description being carried out. On Sunday, the Up Main through the platform was being relayed.
Couldn't help wondering why Platforms 1 and 2 were not being used on Saturday when there was no work going on.
Could be the work happening around the Dore area
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,664
On Saturday afternoon about 1400, I saw no work of any description being carried out. On Sunday, the Up Main through the platform was being relayed.
Couldn't help wondering why Platforms 1 and 2 were not being used on Saturday when there was no work going on.
Probably the way the possession was laid out for protection limits. It would be a lot of trouble to split the possessions north and south of Chesterfield.
 

Mugby

Established Member
Joined
25 Nov 2012
Messages
2,138
Location
Derby
Probably the way the possession was laid out for protection limits. It would be a lot of trouble to split the possessions north and south of Chesterfield.
What I was wondering was; if trains had to go via Barrow Hill (due to work at Dore on Saturday) why not let them use Platforms 1 and 2 at Chesterfield and cross them over at Tapton Junction?
There was nothing at all going on South of Chesterfield on Saturday afternoon.
 

Townsend Hook

Member
Joined
3 Aug 2011
Messages
932
Location
GB
What I was wondering was; if trains had to go via Barrow Hill (due to work at Dore on Saturday) why not let them use Platforms 1 and 2 at Chesterfield and cross them over at Tapton Junction?
There was nothing at all going on South of Chesterfield on Saturday afternoon.

It’s possible that the up and down main through the station were within the possession limits. There wouldn’t necessarily be any visual clues at the station to indicate this.
 

class397tpe

Member
Joined
22 Jan 2022
Messages
172
Location
Cambridge
What I was wondering was; if trains had to go via Barrow Hill (due to work at Dore on Saturday) why not let them use Platforms 1 and 2 at Chesterfield and cross them over at Tapton Junction?
There was nothing at all going on South of Chesterfield on Saturday afternoon.
Yeah, this is what the trains which are regularly booked to use barrow hill do - e.g. Weekdays 0752 EMR Sheffield - St Pancras crosses over and uses Platform 2 southbound.
Perhaps the possession could be adjusted to be just north of Tapton Junction?
 