Are vehicle level crossings with height restrictions allowed under overhead line equipment?
I suspect not, certainly for new lines/new electricification?
So does this mean that any roads crossing the Midland Mainline on the level would need to be replaced with bridges prior to electrification?
would be interesting in the Long Eaton / Attenborough area...
(no mention of crossing closures on Nottingham spur in the CP document that I'm aware of).
I suspect not, certainly for new lines/new electricification?
So does this mean that any roads crossing the Midland Mainline on the level would need to be replaced with bridges prior to electrification?
would be interesting in the Long Eaton / Attenborough area...
(no mention of crossing closures on Nottingham spur in the CP document that I'm aware of).
) . What they do is stop the wires just before and restart them just after, so that there are no wires over the obsticle (in this case an LC) and the train just coasts along the un-wired section which in the case of an LC would be 10 maybe 20 metres.