I've been trying to find this out, but I'm wondering which signalling control centre in the UK has the largest control area in terms of miles covered from entrance to exit? I would say it would be Doncaster. Anybody know?
Surely the new Thames Valley centre will soon be the daddy of miles covered?
What about the East Midlands Signalling Centre or the much rumoured merger of Kings Cross and Peterborough PSBs?
Railtrack will know. Think I'll blast off an email to them and see what I get in return
Railtrack will know.
Dont expect a reply from that shower, they dissapeared 9 years ago.
RT Group PLC wasn't disolved until June 2010.I doubt it seeing as they haven't been in existence for the better part of 10 years!
West Mids area here on last page
http://www.networkrail.co.uk/browse...rns/west midlands and chilterns rus scope.pdf
You could send an email to this Railtrack to see if they know?![]()
May we start by observing that in our days on the track, the railway environment was
frequently dirty, oily, greasy and slimy. It was something that you learned to live with and
didn’t moan your face off if you went on your arse whilst carrying out Rule 55. But, we
suppose that days have changed and if your ambulance chasing solicitors can get you a
few bob for you, then so be it. After all, with what the private sector is screwing out of what
should still be a nationalised industry, your £20,000 is but a fart in the sweety jar in which
they all seem to have their fingers firmly wedged.
They dont appear to be that far out. Oxley went over at the end of last year as did the North Warwicks. Water Orton hasnt slipped as far as I know. Kidderminster and the re-control up to Smethwick is next year. Walsall is possibly 2013 now. Banbury is still up in the air but still said to be 2014 and New St may slip a little and will include the Stechford - International re-control. Madeley doesnt have a date and Worcester will probably be later than 2018 too.
Rugby SCC covers approx 100 miles of the WCML, gotta be worth a shout?
You could send an email to this Railtrack to see if they know?![]()
But will any of this actually achieve any benefit? Apparently some of the equipment being installed is not as reliable as the kit being removed. Axle counters do not have the same reliabilty as track circuits. HPSA and clamp lock point machines are far inferior to electro-pneumatic actuators which have worked well for over 40 years.
All seperate pots of cash to these schemes and still moving forward, Walsall to Lichfield is a long way off though I admit.Surely the cost of these schemes would be better spent on reactivating routes that were needlessly closed in the BR era, Walsall to Stourbridge via Dudley and Walsall to Lichfield are the two glaring examples.
As for New St, there is no way that station can be signalled by anything other than the present NX panel, unless the capacity of the station is reduced rather a lot...
They dont appear to be that far out. Oxley went over at the end of last year as did the North Warwicks. Water Orton hasnt slipped as far as I know. Kidderminster and the re-control up to Smethwick is next year. Walsall is possibly 2013 now. Banbury is still up in the air but still said to be 2014 and New St may slip a little and will include the Stechford - International re-control. Madeley doesnt have a date and Worcester will probably be later than 2018 too.
Secondly when the West of Scotland SC is complete, how much would it cover?
I expect ARS would be used though so as long as everything runs as booked the signalmen would not have to set many routes.In which case forget the current flexibilty and capacity at Birmingham New Street. Setting a route on MCS/VDU systems is like waiting for a slow boat to China....
ARS was considered for BNS some years ago. The system at the time could not manage traffic as efficiently as a Signaller operating an NX panel.