Going back to the "SPAD" episode. There wasn't actually a SPAD at all. The points on 10B were run through but no signal was passed at danger. The platform staff instructed the driver to draw down the platform which is permissible at New Street. The driver drew down but unfortunately ran through the points. Not sure why the programme thought it necessary to suggest a SPAD had taken place.
Looking at CCF, and P10 at New Street, I cannot fathom out, if the train arrived from Coventry, and was going back that way, and stopped half way down, why the points to what looks like No 3 siding were reversed ? and ifthe train stood foul of the mid platform signal, how did that allow the points to be moved ? ( and further, if you can signal to / from No3 sdg, why no one saw it ! )