• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Ilkeston Railway Station construction delayed?

Status
Not open for further replies.

snowdon63

Member
Joined
13 Sep 2013
Messages
8
Location
Ilkeston
I heard that the build of Ilkeston Railway station has been put on hold because of newts found on the site where the build is due to commence . The build should have started at the beginning of June . Could anyone shed any light on this ?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Western Lord

Member
Joined
17 Mar 2014
Messages
1,062
I heard that the build of Ilkeston Railway station has been put on hold because of newts found on the site where the build is due to commence . The build should have started at the beginning of June . Could anyone shed any light on this ?

Wouldn't it be good to hear something like "construction of new runway at Heathrow put on hold because human beings found living on the site".
 

ExRes

Established Member
Joined
16 Dec 2012
Messages
8,371
Location
Back in Sussex
How come that these amazingly rare newts, not to mention the usual equally rare bat colonies, are found at virtually every single major building site in the UK ?

Just how many do you need of something to avoid being classified as rare ?
 

Mark62

Member
Joined
3 Apr 2014
Messages
312
Recently a major road rebuilding project was halted at the Little Eaton junction on the A38. This was due to finding a rare species. The resulting delays created colossal traffic delays as this junction is the major entrance to and from the city. But work had to stop. The contractors had no choice. It will be the same with Ilkeston
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,817
How come that these amazingly rare newts, not to mention the usual equally rare bat colonies, are found at virtually every single major building site in the UK ?

Just how many do you need of something to avoid being classified as rare ?

They are rare in Europe as a whole. But rather common here, particularly at places earmarked for construction.

The fine for harming them is apparently £5k each, and I do wonder whether a callous company might not one day just take the fine.
 

Mark62

Member
Joined
3 Apr 2014
Messages
312
Its a good job its not the TOCs building the station(or any others) They would just bulldoze the site irrespectively and then expect the government to pay their fines.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,666
Location
Nottingham
More news on the newts, also a visualisation of what the station will look like.

http://www.bbc.co.uk/news/uk-england-derbyshire-28488008

Newts have set back the start of building work on a new railway station in Derbyshire by four months.

Work was due to start on Ilkeston station in June but the discovery of the great-crested newts means work cannot start until October.

The £6.5m station will now open in spring 2015, rather than December, as was originally planned, the county council said.

Councillor Andy Botham said he was "disappointed".

The county council said extra flooding prevention work also had to be carried out.
 

M7R

Member
Joined
15 Sep 2010
Messages
271
I asked my Brother in law to be about this as he is an ecologist and does newt surveys, and bat surveys among other things, and he said it quite common for people to either not both with surveys before getting planning permissions, or paying for a very cheap survey and then wondering why things turn up mid way through construction....
 

DarloRich

Veteran Member
Joined
12 Oct 2010
Messages
32,918
Location
Fenny Stratford
I asked my Brother in law to be about this as he is an ecologist and does newt surveys, and bat surveys among other things, and he said it quite common for people to either not both with surveys before getting planning permissions, or paying for a very cheap survey and then wondering why things turn up mid way through construction....

This is sadly quite close to the truth. Cutting corners on the project background work then complaining when it comes back to bite you! It simply means that measures you could have designed in on day one take more time and money to design in on day 100
 

cogload

Member
Joined
29 Jan 2012
Messages
114
They [the newts] have as much right to live on this planet as any other species. There are rules to protect them following them properly might also help.
 
Joined
29 Sep 2013
Messages
163
They are rare in Europe as a whole. But rather common here, particularly at places earmarked for construction.

The fine for harming them is apparently £5k each, and I do wonder whether a callous company might not one day just take the fine.

Or six months in prison.
--- old post above --- --- new post below ---
This is sadly quite close to the truth. Cutting corners on the project background work then complaining when it comes back to bite you! It simply means that measures you could have designed in on day one take more time and money to design in on day 100

I'm currently having a new house built - the architect recommended getting bat and wildlife surveys done before applying for planning permission which cost about £200. Yes a few mitigation steps were specified as planning conditions, but the cost of them when planned before starting building was a few hundred quid more.

Newts only live near ponds don't they? I'm rather gobsmacked that a £6.5m station can be planned without them being spotted at the design phase.
 
Joined
5 Aug 2011
Messages
791
More news on the newts, also a visualisation of what the station will look like.

http://www.bbc.co.uk/news/uk-england-derbyshire-28488008

I would have thought the car park will be bigger, given the lack of parking at Langley Mill

Newts only live near ponds don't they? I'm rather gobsmacked that a £6.5m station can be planned without them being spotted at the design phase.

Well as they were found when building Millership Way (the new road on the left of that picture) only a few years ago you would have expected them to look more closely :roll:
 
Last edited:
Joined
29 Sep 2013
Messages
163
Well as they were found when building Millership Way (the new road on the left of that picture) only a few years ago you would have expected them to look more closely :roll:

LOL. Well that peaked my interest so I checked the planning permission, submitted in November 2013 and granted in January 2014.

The ecological survey submitted with the planning permission identified that there was a large (and monitored) population of newts relocated from the road to ponds close to the site and that there was a 50% risk of an offence occurring. Despite this the surveyors had only visited the site once, in February 2013. Nothing during the summer of 2013. The council therefore put a pretty severe condition on the planning permission for more detailed ecological work.

They also put a stonking great condition about agreeing detailed plans for drainage because there was a high risk of flooding.

"The 7 Ps" comes to mind. Blaming the newts seems p*** poor to me. If they had monitored the site properly last year, they could have moved the newts before now. But in any case, they would still need to design the drainage properly before starting work.
 
Last edited:

AM9

Veteran Member
Joined
13 May 2014
Messages
16,035
Location
St Albans
Cutting corners on eco surveys is foolhardy anyway. If somebody who cares about the natural environment doesn't subsequently find anything, the NIMBYs will sure search very hard for it, often as a last resort.
That's because its the wildlife that they really care for, not their spoilt views or their house prices!
 
Joined
11 Sep 2012
Messages
748
Location
uk
Thought progress was slow. When I went past on Friday I noticed a truck and digger in the station yard so there has been some activity but obviously it is going to be limited.
If we have a very wet winter the station site will be under water anyway so a Spring opening date could easily be delayed...........
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,666
Location
Nottingham
LOL. Well that peaked my interest so I checked the planning permission, submitted in November 2013 and granted in January 2014.

The ecological survey submitted with the planning permission identified that there was a large (and monitored) population of newts relocated from the road to ponds close to the site and that there was a 50% risk of an offence occurring. Despite this the surveyors had only visited the site once, in February 2013. Nothing during the summer of 2013. The council therefore put a pretty severe condition on the planning permission for more detailed ecological work.

They also put a stonking great condition about agreeing detailed plans for drainage because there was a high risk of flooding.

"The 7 Ps" comes to mind. Blaming the newts seems p*** poor to me. If they had monitored the site properly last year, they could have moved the newts before now. But in any case, they would still need to design the drainage properly before starting work.

I agree it's not fair for the newts to take the blame, especially as they can't answer back. And a shame they didn't put the newts somewhere else when they built the road. And the applicant was... Derbyshire County Council...

(if anyone's interested it is case 1113/0013 on http://www.erewash.gov.uk/planning-...ons/search-current-planning-applications.html)
 

DarloRich

Veteran Member
Joined
12 Oct 2010
Messages
32,918
Location
Fenny Stratford
Newts only live near ponds don't they? I'm rather gobsmacked that a £6.5m station can be planned without them being spotted at the design phase.

Assuming that you looked for them!

They can live in anything that can hold water. I have seen reports of them in pipes, swimming pools (disused) tanks, sumps, drains etc
 
Joined
5 Aug 2011
Messages
791
LOL. Well that peaked my interest so I checked the planning permission, submitted in November 2013 and granted in January 2014.

The ecological survey submitted with the planning permission identified that there was a large (and monitored) population of newts relocated from the road to ponds close to the site and that there was a 50% risk of an offence occurring. Despite this the surveyors had only visited the site once, in February 2013. Nothing during the summer of 2013. The council therefore put a pretty severe condition on the planning permission for more detailed ecological work.

They also put a stonking great condition about agreeing detailed plans for drainage because there was a high risk of flooding.

"The 7 Ps" comes to mind. Blaming the newts seems p*** poor to me. If they had monitored the site properly last year, they could have moved the newts before now. But in any case, they would still need to design the drainage properly before starting work.

Surveyors are unlikely to find any Newts in Febuary they more likely to be hibernating.
--- old post above --- --- new post below ---
You've never been to Ilson... :roll:

A shame the project has been delayed... Once built i may be able to use the train to travel for the odd footy match - the ground is close to the railway.

Indeed ;)

Last I heard that football club had gone bankrupt, same as Eastwood Town FC :(
 
Last edited:
Joined
29 Sep 2013
Messages
163
Surveyors are unlikely to find any Newts in Febuary they more likely to be hibernating.(

Well yes that was my point, not much use an ecological surveyor spending one day on the site in February!
--- old post above --- --- new post below ---
If we have a very wet winter the station site will be under water anyway so a Spring opening date could easily be delayed...........

Which reinforces the point about inadequate drainage design submitted with the planning application. Its easy for Derbyshire Council to put out a story about newts (which they've moved to the site anyway) and for them then to gloss over the basic design problems in one sentence.
 
Joined
11 Sep 2012
Messages
748
Location
uk
Having been past last two days there is now activity. The railway lines are fenced off. There is activity on the derbyshire side. On the Nottinghamshire side notable clearance of bushes is taking place and access for the car park site is presumably in hand - well there are vehicles on that side doing work....
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,666
Location
Nottingham
As the county boundary runs through the site it is probably the subject of two separate planning applications, so we may see work going ahead on the car park side while the issues of the station itself are resolved. Clearance of vegetation is subject to restrictions during bird nesting season so if they left this until the newts were sorted they might find they couldn't do it for even longer.
 
Joined
11 Sep 2012
Messages
748
Location
uk
Station Site looking south this morning. Also the car park site.
 

Attachments

  • 20140818_095430.jpg
    20140818_095430.jpg
    387.3 KB · Views: 56
  • 20140818_095438.jpg
    20140818_095438.jpg
    328.9 KB · Views: 48

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,666
Location
Nottingham
Further delays and a bust budget due to flood alleviation. Sounds like someone hasn't done their homework - couldn't they just open the station before the car park?

THE construction of a new railway station has been delayed until next spring over flooding concerns.

The Environment Agency has asked that works take place during the construction of the site to ensure that the car park does not flood during bad weather.

The estimated cost of these additional repairs is £3m.

Now, the project team is being forced to look at the specifications of the station to see where savings could be made.

Read more at http://www.nottinghampost.com/Flood...3211139-detail/story.html#UoMVxsDPgTCVfw0S.99
 

Xenophon PCDGS

Veteran Member
Joined
17 Apr 2011
Messages
35,434
Location
A typical commuter-belt part of north-west England
Last I heard that football club had gone bankrupt, same as Eastwood Town FC :(

Scurrilous rumours such as this are normally only ever found on the Football thread, so I take it upon myself to correct this rumour.

On Monday of this current week in an Evo-Stik Northern League, Premier Division, match, Ilkeston FC drew 2-2 at home against Halesowen Town FC and currently occupy the eight league position.
--- old post above --- --- new post below ---
As the county boundary runs through the site it is probably the subject of two separate planning applications, so we may see work going ahead on the car park side while the issues of the station itself are resolved. Clearance of vegetation is subject to restrictions during bird nesting season so if they left this until the newts were sorted they might find they couldn't do it for even longer.

The matter of vegetation clearance during the bird nesting season being not allowed, was one that was planned for in the Balfour Beatty work scheduling of the preliminary groundworks on the former rail route of the part of the former Tyldesley Loop Line, that will form part of the Leigh Guided Busway.
--- old post above --- --- new post below ---
Ilkeston Town FC went belly up. The new Ilkeston FC have taken their place. Can't see a phoenix Eastwood rising from their ashes anytime soon, though.

To be fair, Ilkeston FC have been in existence under that name since 2010, so it is not exactly a new matter...:roll:
--- old post above --- --- new post below ---
Further delays and a bust budget due to flood alleviation. Sounds like someone hasn't done their homework - couldn't they just open the station before the car park?

A viewing of both postings # 17 and # 20 on this thread might shed some light on the matter.
 
Last edited:

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,666
Location
Nottingham
A viewing of both postings # 17 and # 20 on this thread might shed some light on the matter.

I'm aware of these postings especially #20 which was one of mine!

If it's the construction of the car park that increases the flooding risk, as implied by the Evening Post article, then perhaps deferring the car park would allow the station to be built. Although the budget issue suggests they will have to cut something else to pay for the flood alleviation so maybe that's a reason not to build anything until the budget has been reallocated.
 
Status
Not open for further replies.

Top