Thank you, but has it yet been established by how much that will reduce the east-west paths?Currently there may be spare paths across Newark Flat Crossing but from December 2021 the ECML services will increase to 8 paths each hour to/from Kings Cross.
(7.5 paths an hour each way across with the flat crossing and the remaining 0.5 path being the Lincoln-Kings Cross which doesn't actually use the flat crossing)
It depends as the junction margins vary by direction and how close up and down trains are at the crossing., but if the first move is a E-W or W-E train then you cannot pass on the ECML until 4½ minutes after. If an Up train is first then its a 3 minute margin before a crossing move. Conceivably, if there are two opposing ECML moves within a short time then it eats up capacity.Thank you, but has it yet been established by how much that will reduce the east-west paths?
Given that post No.10 informs us that there are at least two spare paths an hour, I'd have thought a good opening theory would have been one train an hour from Lincoln all stops to Matlock and one fast train stopping only at Newark Castle, Nottingham, Leicester, Birmingham New Street and continuing south-west to somewhere like Gloucester.
On a constrained railway, it is unreasonable to keep insisting on prioritising minority flows to the detriment of the majority.
I would say it would come down to what gets the best BCR, but BCR as we know it is pretty close to getting binned.
A BCR is just a number anyway. It comes out at the end of your modelling. The critical part is the actual methodology, which is based on the the relevant Transport Analysis Guidance, and the quality of your inputs. That will probably require very significant revision. At some point further down the line, coordination of the transport appraisal response to Covid-19 will surface. It will be very interesting.
I recall reading somewhere that it was proposed, but BR (RailTrack?) didn't have the money.A bridge should have been built at the same time as the A46 Newark By-Pass
I had a look at the thoughts of Midlands Connect (that's a soft-of equivalent to TfN, albeit lower-key and much less grand ambitions). Nottingham-Lincoln is on their wish list, and they want to go up to 2tph. The flat crossing is noted as the key obstacle, but their ideas for what to do aren't any more specific than asking Network Rail for possible solutions.
However, the most discouraging note is that they don't seem interested in doing this until HS2 is up and running. It is not clear whether this is because they think they need HS2 to raise the demand or because they're hoping this lead to a reduction in traffic on the ECML. I'm sceptical about both. Anyway, it looks like we're going to have to count on an ongoing ECML upgrade for any hope of getting grade separation off the "later" pile in the next decade.
Exactly.By getting off the "later" pile, I mean getting started, never mind actual completion. Midlands Connect is seems to be pushing far more heavily with its "Midland Hubs" scheme with details of what they want to achieve, how they intend to achieve it, and estimates of cost and timescale. Compared to the vague aspirations for Lincoln-Nottingham, there doesn't seem to be much doubt where their interest is.


[CRAYON]Here's my scheme.
[/CRAYON]
ISTR the Bottesford option was being discussed back in the 80s[CRAYON]Here's my scheme.
1. Rebuild the old Bottesford line, mostly unobstructed former double track formation, no intermediate stations, heading south from Newark (yellow). Create a new higher-speed curve and junction to join Nottingham - Grantham line (magenta).
View attachment 77154
2. New layout at Newark North Gate with diamond removed and catering for Nottingham - Lincoln trains between the fasts. so each crossing movement passes over only one fast line at a time. Also caters for direct London - Lincoln, and potential new North East - Nottingham axis.
View attachment 77155
3. Remains of Newark Castle line largely singled and diverted via new connection built into North Gate station via new river bridge and tight 150m radius chord (cyan). Possibly one intermediate passing loop somewhere between Newark and Nottingham for 30 minute interval all stations service terminating at Newark. All Lincoln trains to run via North Gate.
View attachment 77156
[/CRAYON]
If you are going to build all that you may as well take it over the ECML rather than bend it round![CRAYON]Here's my scheme.
1. Rebuild the old Bottesford line, mostly unobstructed former double track formation, no intermediate stations, heading south from Newark (yellow). Create a new higher-speed curve and junction to join Nottingham - Grantham line (magenta).
View attachment 77154
2. New layout at Newark North Gate with diamond removed and catering for Nottingham - Lincoln trains between the fasts. so each crossing movement passes over only one fast line at a time. Also caters for direct London - Lincoln, and potential new North East - Nottingham axis.
View attachment 77155
3. Remains of Newark Castle line largely singled and diverted via new connection built into North Gate station via new river bridge and tight 150m radius chord (cyan). Possibly one intermediate passing loop somewhere between Newark and Nottingham for 30 minute interval all stations service terminating at Newark. All Lincoln trains to run via North Gate.
View attachment 77156
[/CRAYON]
ISTR the Bottesford option was being discussed back in the 80s
So my scheme is very similar, improving the speed of the curve and junction at the southern end of the reinstated line, and adding the new chord for the Fiskerton line to reach North Gate station for Lincoln and ECML connections. A grade separation south of Newark would be possible, but clearly very expensive, and would probably have to be the Bottesford line diving under the ECML to avoid the road overbridges nearby. Note there's only room for three tracks through the A46 bridge, so a segregated Lincoln line would have to be single for a short distance, although pointwork might be simplified considerably compared to my previous station layout. Something like this perhaps:That's correct. Under that scheme Nottingham - Newark services would have terminated at Newark Castle. Nottingham - Lincoln trains would have run via the junction at Bottesford.
The only drawback would have been for any passengers wanting to travel from places like Fiskerton and Rolleston to Lincoln - but I don't suppose there were/are many in that category.
Okay, I found this in page 32 of this document:
It's talking about linespeed on the ECML central section in general:
"By upgrading the infrastructure between Peterborough and York, linespeeds can be improved and journey times reduced by 4.5 minutes between Peterborough and York.The improvements would see a step-change in the reliability of overhead line electrification equipment, where the equivalent of thousands of working days in delay could be avoided each year. Providing 140mph running would require the removal of the at-grade crossing at Newark. Replacing this with a fly-over would unlock capacity for additional hourly services linking Lincoln to Nottingham and the Midlands.This package would rely on the introduction of digital signalling technology which would also bring improvements in headways (safe space between trains) and junction margins (amount of time between trains using a junction), making the operation of trains at Doncaster and York stations more efficient"
This seems to reveal the following about Network Rail's thinking:
So I guess it comes down to how serious Network Rail / the Government are about making 140 mph line speed happen.
- Removing the Newark flat crossing would be needed for 140 mph running.
- A flyover is the only way of achieving this. (This contrasts with Midlands Connect which acknowledges the flat crossing as an issue but stops short of specifying a flyover as the solution.)
- They don't seem particularly interested in grade separation at Doncaster, which I'd have rated at the Newark flyover's main competitor.
- They expect the flyover to be difficult and expensive.
South of Rockhampton, the QR line is electrified and higher speeds are permitted than further north. In order to increase track speeds for the "tilt trains", this drawbridge arrangement was devised so there is no break in the running rails for QR. All signals are color light.
At Newark could there be another way to remove the diamonds? I present for you the 'Queensland solution':
Assuming that it would be the Lincoln line going over the ECML, while it would be unusual, it wouldn't be conceptually any different to any other swing or drawbridge. The same signalling would need to be applied and it would need to be held in the closed position and fail to open.Good grief! The safety boys and girls would have a fit at that!
Assuming that it would be the Lincoln line going over the ECML, while it would be unusual, it wouldn't be conceptually any different to any other swing or drawbridge. The same signalling would need to be applied and it would need to be held in the closed position and fail to open.
That may be becasue the moving infrastructure itself is crossed by the train in question, unlike this example. You could deploy obstacle detection technology (radar/lidar) as well as conventional limit-switch detection of the mechanism and even supplemental Mk1 human eyeball 'crossing clear' checking via CCTV! I'm not recommending it though you must understand! I don't think there was ever an upper speed limit on MCB crossings.Someone will no doubt correct me, but I can’t think of any swing or drawbridge that has a linespeed of more than 75mph. And I know that 140mph wouldn’t be permitted where there are ‘permitted’ obstructions on the line even if they are proved clear (like level crossings).