HS2: Should it have been a single tunnel?

Status
Not open for further replies.

LesF

Member
Joined
25 Mar 2014
Messages
113
Location
Coventry
Eh? So a completely remodelled Rugby, improved speeds and signalling was catching up on maintenance?
Rugby remodelling was a success story. But HS2 claimed the flyover at the west end of Rugby was "life expired", a two-word term that engineers like. It's still in daily use so cannot be life expired. How can we trust anything they say?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,700
Rugby remodelling was a success story. But HS2 claimed the flyover at the west end of Rugby was "life expired", a two-word term that engineers like. It's still in daily use so cannot be life expired. How can we trust anything they say?
I dont get what that has to do with the rest of the work adding HS2 to the WCML would entail. Its a tiny part of it. Who is to say that the structure won't have to be replaced or have heavy refurbishment in the near to medium future done by NR?
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,830
But HS2 claimed the flyover at the west end of Rugby was "life expired", a two-word term that engineers like. It's still in daily use so cannot be life expired. How can we trust anything they say?

Did they? When? I seem to remember WCRM claiming that. Anyway, even if HS2 did say it, people sometimes get things wrong. Unless you think everyone should be correct 100% of the time, in which case…

Where new tracks were added in the Trent valley, the work went smoothly without disrupting the existing tracks.

…This is patently not correct.
 
Last edited by a moderator:

6Gman

Established Member
Joined
1 May 2012
Messages
9,206
Rugby remodelling was a success story. But HS2 claimed the flyover at the west end of Rugby was "life expired", a two-word term that engineers like. It's still in daily use so cannot be life expired. How can we trust anything they say?
Source?
 

LesF

Member
Joined
25 Mar 2014
Messages
113
Location
Coventry
My mistake. It was Net Rail who claimed in the noughties that the Rugby flyover was "life-expired". I can't find the source but Bald Rick appears to agree. I should qualify what I mean by Rugby remodelling being a success story. I.I r.c. (it was about 20 years ago) Rugby was late and over budget as rail projects generally are, but the plan was changed to one that allowed quicker completion at less cost and less disruption and allowed higher train speeds. It's that aspect that I regard as a success. I'd be amused if someone from the rail industry put forward a counter-argument that Rugby remodelling was a failure. So I'd like to pose a question, and I'm sorry this is off-topic: what's the proposal for renovating or replacing the 1960's Rugby flyover?
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,700
My mistake. It was Net Rail who claimed in the noughties that the Rugby flyover was "life-expired". I can't find the source but Bald Rick appears to agree. I should qualify what I mean by Rugby remodelling being a success story. I.I r.c. (it was about 20 years ago) Rugby was late and over budget as rail projects generally are, but the plan was changed to one that allowed quicker completion at less cost and less disruption and allowed higher train speeds. It's that aspect that I regard as a success. I'd be amused if someone from the rail industry put forward a counter-argument that Rugby remodelling was a failure. So I'd like to pose a question, and I'm sorry this is off-topic: what's the proposal for renovating or replacing the 1960's Rugby flyover?
There isn't one yet. It is being dealt with via normal maintenance. That isn't to say there isn't a longer term plan for it.
 

Lloyds siding

Member
Joined
3 Feb 2020
Messages
626
Location
Merseyside

12LDA28C - no I don't. The West Coast Route Modernisation in the noughties was largely about catching up on maintenance on existing tracks. Where new tracks were added in the Trent valley, the work went smoothly without disrupting the existing tracks.​

No, four completely new tracks were laid to replace the existing two. I should know, I had to model the noise from each of them.
 

LesF

Member
Joined
25 Mar 2014
Messages
113
Location
Coventry
No, four completely new tracks were laid to replace the existing two. I should know, I had to model the noise from each of them.
OK, I was told that work on new tracks progressed while trains ran on the existing adjacent tracks with only a plastic curtain fence between them. NB I left the rail industry in 1963 so what do I know?
 

Lloyds siding

Member
Joined
3 Feb 2020
Messages
626
Location
Merseyside
OK, I was told that work on new tracks progressed while trains ran on the existing adjacent tracks with only a plastic curtain fence between them. NB I left the rail industry in 1963 so what do I know?
I'm sure once the central tracks were laid then they would be used whilst work continued on the remaining ones.
 