I found an article on the tunnelling plans for hs2 phase 1.
http://tunneltalk.com/UK-high-speed-rail-28Oct2014-HS2-procurement-and-TBM-drive-strategy.php
Procurement for the major civils contracts for HS2 is expected to begin at the end of this month (September 2015).
Alistair Cowan, for HS2, told TunnelTalk: “Pre-qualification questionnaires for £6.4 billion of civils contracts, divided into seven packages ranging from £700m to £1bn, will be sent out later this month.”
The procurement timeline now envisages invitations to tender in Spring 2016, followed by the award of contracts later in 2016 or early 2017. This will be timed to follow the granting of Royal Assent for the hybrid bill that is currently proceeding through UK Parliament. Construction of the major civils, including tunnelling is scheduled to begin in 2018.
It is understood that the originally-planned three contracts in the South section have been merged into two larger lots, and it is these that incorporate most of the twin running TBM-bored tunnels for the first phase of HS2.
These include the 7km tunnel out of Euston Station, the 14km Northolt tunnel in the east of the capital, and the 16km Chiltern tunnel from the M25 through Buckinghamshire.
http://tunneltalk.com/UK-high-speed-rail-28Oct2014-HS2-procurement-and-TBM-drive-strategy.php
Procurement for the major civils contracts for HS2 is expected to begin at the end of this month (September 2015).
Alistair Cowan, for HS2, told TunnelTalk: “Pre-qualification questionnaires for £6.4 billion of civils contracts, divided into seven packages ranging from £700m to £1bn, will be sent out later this month.”
The procurement timeline now envisages invitations to tender in Spring 2016, followed by the award of contracts later in 2016 or early 2017. This will be timed to follow the granting of Royal Assent for the hybrid bill that is currently proceeding through UK Parliament. Construction of the major civils, including tunnelling is scheduled to begin in 2018.
It is understood that the originally-planned three contracts in the South section have been merged into two larger lots, and it is these that incorporate most of the twin running TBM-bored tunnels for the first phase of HS2.
These include the 7km tunnel out of Euston Station, the 14km Northolt tunnel in the east of the capital, and the 16km Chiltern tunnel from the M25 through Buckinghamshire.