Some details of station piling have been released, and 4 test piles done which are being monitored
www.geplus.co.uk
Early piling work for the Euston station is expected start in Q1 of this year. This programme of approximately 500 piles will take around two years to complete, followed by another three years of piling to finish the total 1,600 piles on site.
On the face of it, 5 years and 1600 piles seems a lot for a 3 level building that is dug into the ground so not on uncompacted soil. Unless there is going to be massive tower blocks over it, seems like it is being built like a nuclear bunker. Didn't Broadgate and all the bits over Liverpool Street get built in about 3-4 years.The HS2 station will be set across three levels, with ten 450m long subsurface platforms. The ground-level concourse will be 300m long and will allow free movement for both passengers and visitors through the station and will open out onto new public spaces at the north and south. The station hall is set to become the largest station concourse in the UK.
The design has reduced the ticketed area of the station by placing platforms and trains below ground, so the station hall can function as a public, sheltered north-south route linking Euston Road and Bloomsbury to Hampstead Road and Camden Town.
Is it just me, or is this just seem to be over complicated design, from the lets make it very expensive to build school of architectureHS2 Ltd revealed new images of its Euston station design at the end of last year, updated from 2015. The Department for Transport had previously revealed that "significant elements" of the original design work on the station "can no longer be used" after the decision was taken for the station to be scaled back from 11 to 10 platforms, as reported by GE’s sister title NCE.
According to HS2 Ltd, the new designs are based on a "less complex, more efficient" ten platform station that can be built in a single stage.
HS2 Euston station prepped for piling with ‘groundbreaking’ load testing system | Ground Engineering
The last of four pile load tests was completed last week on the site of the future High Speed 2 (HS2) Euston station in London. This was done using