HS2 Crewe-Manchester Bill Published

Status
Not open for further replies.

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,904
Location
Mold, Clwyd
The government PR machine is in full swing with advance notice that the HS2 Phase 2b Bill for the Crewe-Manchester extension will reach Parliament today.
The details are not yet visible, but it appears to exclude the northern part of the loop from Rostherne back to the WCML at Golborne. Edit: Yes it's included.
The map published on the BBC site shows it as a dotted line, similar to the abandoned eastern leg to Leeds/York.
There's a solid line to Warrington though, and mention of Warrington in the text, plus junctions at Crewe, Manchester Airport and Manchester Piccadilly (the last two for NPR).
It's not clear what all that means.
The "potential" upgraded hub at Crewe doesn't quite make it into the bill either, maybe that is left to NR to develop.
  • government to lay bill to extend HS2 from Crewe up to Manchester and beyond, creating 17,500 direct jobs across the North
  • this is a major phase of the £96 billion commitment in the Integrated Rail Plan to deliver faster and better journeys across the North quicker than under previous plans
  • new High Speed stations will also be built at Manchester Piccadilly and Manchester Airport, making way for new lines to Leeds and Liverpool, as part of Northern Powerhouse Rail


1643008112752.png

The announcement is also on the HS2 web site, where the map does appear to show the Golborne link as part of the Bill.

It also has this unclear paragraph on the Crewe hub:
Investment would also give the green light for a new junction north of Crewe, known as the Crewe Northern Connection, for a future NPR scheme which could allow up to seven high-speed trains per hour to call at the town. As well as boosting connectivity to the heritage railway town, the infrastructure facilitates better links between Chester, North Wales and Birmingham and Shrewsbury and Manchester. Combined with the Government’s plans for Northern Powerhouse Rail, the Crewe Northern Connection could also facilitate faster journeys between Liverpool and the capital.

This is the HoC description of the HS2 Bill:
Bill to make provision for a railway between a junction with Phase 2a of High Speed 2 south of Crewe in Cheshire and Manchester Piccadilly Station; for a railway between Hoo Green in Cheshire and a junction with the West Coast Main Line at Bamfurlong, south of Wigan; and for connected purposes

Maybe we should refer to the Bamfurlong connection to the WCML, rather than Golborne.
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Cheshire Scot

Established Member
Joined
24 Jul 2020
Messages
1,676
Location
North East Cheshire
There's a solid line to Warrington though, and mention of Warrington in the text, plus junctions at Crewe, Manchester Airport and Manchester Piccadilly (the last two for NPR).
There is also a solid line to Marsden - and to East Mids Parkway - which suggests the solid lines reflects the 'new plan' and that to to Warrington is the watered down HS3/NPR.

For me a missing link in the 'new plan' is a triangular junction just south of Piccadilly would enable e.g. Birmingham to Leeds to avoid reversal in Piccadilly and save possibly up to ten minutes journey time rather than be an extension of a Manchester train.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,215
Location
Bolton
Excellent. Still hope for Royal Assent before the planned end of the session in 2024.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
8,005
Location
Surrey
Excellent. Still hope for Royal Assent before the planned end of the session in 2024.
High Speed Rail (West Midlands – Crewe) took nearly four years before it got Royal Assent so unlikely and will probably have a lot more petitioning given the area its plotted though.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,215
Location
Bolton
High Speed Rail (West Midlands – Crewe) took nearly four years before it got Royal Assent so unlikely and will probably have a lot more petitioning given the area its plotted though.
For a larger than expected proportion of that four years, Parliament was heavily distracted with endless Brexit legislation, including the government losing control of business in the house, or even wasn't actually sitting because it was unlawfully prorogued, or dissolved for an election.

If an election takes place earlier than the currently planned end of the session, a further delay is likely. However, as it stands three years should be sufficient.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,904
Location
Mold, Clwyd
The environmental opposition has been mobilised:
It's part of a 'national day of action' to protest against the expansion of high-speed railway – as the Bill for the project is laid out in Parliament on Monday

And Andy Burnham thinks it's the "wrong plan":
https://www.manchestereveningnews.c...chester-news/bill-next-phase-hs2-see-22847640
However Mayor of Greater Manchester, Andy Burnham, has slammed the plans and asked for an underground station to better 'level up' between the north and south.
He added that the development of a HS2 station above ground will mean losing prime development land and its economic opportunity.
Commenting on the current HS2 plan for Greater Manchester, he said: “We remain committed to working with the Government to bring HS2 to our city-region. But we remain of the view that this is the wrong plan, both for Greater Manchester and for the North as a whole.
 
Joined
18 Oct 2017
Messages
215
For a larger than expected proportion of that four years, Parliament was heavily distracted with endless Brexit legislation, including the government losing control of business in the house, or even wasn't actually sitting because it was unlawfully prorogued, or dissolved for an election.

If an election takes place earlier than the currently planned end of the session, a further delay is likely. However, as it stands three years should be sufficient.
There were also some "COVID effects" causing Parliament to no sit for a while when the Bill was in the Lords.
 

Gostav

Member
Joined
14 May 2016
Messages
541
The environmental opposition has been mobilised:


And Andy Burnham thinks it's the "wrong plan":
https://www.manchestereveningnews.c...chester-news/bill-next-phase-hs2-see-22847640
Now? That's an odd timing. I believe most people are working or studying at this time.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,620
Location
Nottingham
The environmental opposition has been mobilised:


And Andy Burnham thinks it's the "wrong plan":
https://www.manchestereveningnews.c...chester-news/bill-next-phase-hs2-see-22847640
Does he want the five years (minimum) delay for re-designing for a through station in Manchester? Either that or the extra cost could kill off the Manchester leg and NPR entirely.
 

Watershed

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
26 Sep 2020
Messages
16,610
Location
UK
There's a delicious irony in the HS2 Crewe-Manchester bill being published on the same day that there are 2 hour gaps between fast services on the same route.

Of course HS2 Phase 2b will only incidentally serve that flow, but it's still amazing to think that a high speed route is being built to "relieve" a line where having no fast services for 2 hours is simply an unfortunate side effect of poorly coordinated timetable reductions.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
8,005
Location
Surrey
For a larger than expected proportion of that four years, Parliament was heavily distracted with endless Brexit legislation, including the government losing control of business in the house, or even wasn't actually sitting because it was unlawfully prorogued, or dissolved for an election.

If an election takes place earlier than the currently planned end of the session, a further delay is likely. However, as it stands three years should be sufficient.
Reading the strategic business case which i quoted in #14 it is based on Royal Assent being achieved by 2024 so barring a general election govt business managers clearly feel its possible. We will see how it plays out from here.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,215
Location
Bolton
Reading the strategic business case which i quoted in #14 it is based on Royal Assent being achieved by 2024
That is what was stated when the design refinement consultation was done yes. Has only been a 4-6 month delay in depositing the bill, following on from the conclusions of the IRP and Union Connectivity Review. The government's responses to that consultation are also published today.

== Doublepost prevention - post automatically merged: ==

There not very ambitious for what is the smallest part of HS2
It sounds pretty reasonable to me if another hybrid bill comes along in 2024 - 2027 to authorise the line to Marsden. It has been suggested that Coleshill - East Midlands Parkway can now be completed concurrently with this timescale via the Nationally Significant Infrastructure process too. But then I guess we shouldn't get ahead of ourselves.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,904
Location
Mold, Clwyd
It's still unclear in the business case what the policy on Edinburgh services is.
The principal HS2 plan with the Bamfurlong connection has 3tph Anglo-Scottish services, 2 from Euston and one from Birmingham, splitting for Glasgow/Edinburgh.
But nothing is said about the ECML level of service.
We are surely not contemplating 4tph London-Edinburgh, 2 via HS2/WCML and 2 via ECML?
The "do minimum" option of not doing the Bamfurlong link would mean the loss of both of the HS2/WCML Edinburgh services, and one of the Glasgow services.

The accompanying map (p6) actually omits the Rostherne-Manchester branch, but does include an upgraded ECML from London to Leeds/Newcastle.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,215
Location
Bolton
It's still unclear in the business case what the policy on Edinburgh services is.
The principal HS2 plan with the Bamfurlong connection has 3tph Anglo-Scottish services, 2 from Euston and one from Birmingham, splitting for Glasgow/Edinburgh.
But nothing is said about the ECML level of service.
We are surely not contemplating 4tph London-Edinburgh, 2 via HS2/WCML and 2 via ECML?
The "do minimum" option of not doing the Bamfurlong link would mean the loss of both of the HS2/WCML Edinburgh services, and one of the Glasgow services.

The accompanying map (p6) actually omits the Rostherne-Manchester branch, but does include an upgraded ECML from London to Leeds/Newcastle.
This map?

Contains some pretty big bombshells for Leicester too. Only 1tph to Derby and Sheffield, only 1tph fast to Nottingham. Not good.
 

Attachments

  • 20220124_181748.png
    20220124_181748.png
    492.2 KB · Views: 199

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,904
Location
Mold, Clwyd
The Bill text (p72) describes two works of about 1km each on the WCML, being "extension and reconfiguration" of Preston and Carlisle stations.
Presumably this is to cater for 400m trains and platforms at these locations.
This map?
Contains some pretty big bombshells for Leicester too. Only 1tph to Derby and Sheffield, only 1tph fast to Nottingham. Not good.

No, it's the colour-coded map on p6 of the Business Case update.
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,330
Location
Nottingham
This map?

Contains some pretty big bombshells for Leicester too. Only 1tph to Derby and Sheffield, only 1tph fast to Nottingham. Not good.
Which document did that chart of potential services come from, please? Seems to show a serious curtailment of services from Grantham and Newark ....
 
Last edited:

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,491
Location
Preston Lancs
I notice that an updated IRP has also been published.
I was just about to comment on this. I have this link but it currently doesn't seem to be working: https://www.gov.uk/government/publications/strategic-alternatives-to-the-hs2-eastern-leg

No sign of the mythical technical annex. Can anyone find it please?
Whats changed???
Well as Starmill says - something is wrong with the website. The Dft homepage says updated January 24 2022 - but I am still searching.

What has supposed to have changed is there is now SUPPOSED to be a Technical Annex attached. So far it has taken on unicorn like features. (edit now found please see bottom of post)


On the HS2 Strategic Outline Business Case I found this in the forward by Andrew Stephenson MP
Our current Victorian rail network is the oldest in the world. After decades of
underinvestment
and rapidly rising demand, it is no longer capable of supporting our 21st
century needs. We need a more resilient, reliable and sustainable railway, that can improve
opportunities for millions of people, particularly in the North and Midlands,

Now he is either being 100% honest and blunt and admitting that all parties/politicians etc are responsible for this or - well words fail me!


EDIT - FOUND IT https://assets.publishing.service.g...or-the-north-and-midlands-technical-annex.pdf
 
Last edited:

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,701
This map?

Contains some pretty big bombshells for Leicester too. Only 1tph to Derby and Sheffield, only 1tph fast to Nottingham. Not good.

But… there will always be winners and losers. one of the reasons the railway is in the state it is is that the politicians want there to be ‘no bad news’.

For what it’s worth, given traffic levels Leicester to each of Derby and Nottingham, hourly is probably enough. There is also the opportunity to change at EMP To give more connected frequency (similar to how you get from Bedford to Leicester via Kettering.)
 

deltic

Established Member
Joined
8 Feb 2010
Messages
3,714
The details are not yet visible, but it appears to exclude the northern part of the loop from Rostherne back to the WCML at Golborne. Edit: Yes it's included.




Maybe we should refer to the Bamfurlong connection to the WCML, rather than Golborne.
Whatever you call it, it will not be in the Bill long as the IRP made clear.
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,330
Location
Nottingham
Union Connectivity review recommended it should be extended further to somewhere south of Preston rather then end in Golbourne
The Revised IRP states (p61):
Future possibilities: • The Union Connectivity Review is considering the case for further improvements for high speed rail services between these nations, including alternatives to the Golborne link from the HS2 Line to the West Coast Main Line.
So I don't think this has been decided yet.
 