Really seems like they are ramping up the pace now. 1 bored tunnel already completed and several more in progress. I was wondering just how much earthworks are going on now on the main route (are we starting to see a railway take shape?).
A few other random question popped into my head recently and I thought this would be a good thread to ask them:
1. Is the intention to open Phase 1 (apart from Euston) and 2a simultaneously almost as if they are one section of railway?
2. How far behind is Euston from the rest of the Phase 1/2a project? Ie if OOC is delayed could it open at the same time?
I am also a bit of an electrification geek so was interested to know if they had decided what cantenary and signalling system to use. Maybe a replica of HS1 or the newer LGV routes in France.
That's probably enough for today haha. I will be in Birmingham next month so I will probably pop down to Curzon street, though it is probably still a hole in the ground at the moment.
You can see from the various drone videos (from Sept/Oct) mentioned in this thread that there is work in progress on virtually all the HS2 trace (tunnels not visible of course).
But most of it so far is clearance and enabling works for the real thing (eg road/rail/footpath/utility diversions).
The Colne Valley viaduct is taking shape, and you can see the various headhouse/ventilation shaft works for the tunnels if you plot the HS2 route underneath.
The deep cuttings at Calvert and near Brackley are under construction, and some smaller viaducts are taking shape (piers at least).
The station sites (Euston, OOC, Interchange and Curzon St) areas are huge but very complicated, so far without any hint of the future railway.
Google maps shows some of this but is mostly a year or two out of date, so doesn't really reflect what's on the ground now.
Generally the HS2 work sites are marked (with the name of the contractor), and you can often trace the line of route in the area between the sites.
There was/is an aim to open Phase 2a with Phase 1, but 2a was 4 years behind in the process when it was approved.
The aim is to merge some of the contracts so that 2a can catch up, but it's impossible to know how it will go.
Phase 1 is a much higher risk project, with all the tunnelling and station work to do.
If you hadn't realised, Phase 1 goes to Lichfield (Handsacre) where it joins the WCML, with Birmingham as a branch.
Royal Assent for Phase 2a doesn't automatically get it funded (although that seems not to be in doubt now) or gets spades in the ground immediately.
They are still involved in land purchase and ground investigations for Phase 2a, plus planning the Network Rail changes necessary at Crewe.
I believe the tunnel and railway from OOC to Euston have to be finished before OOC can open.
It's just the station construction at Euston that is holding it back, and they are not through the planning process yet.
I don't think anyone is aiming for Euston and OOC to be ready at the same time.
The electrification and signalling haven't been contracted yet - nor the track for that matter.
The electrification contract doesn't give anything away on the design, but the contractor shortlist includes all the usual suspects, often as JVs, together with "China Railway Electrification".
Signalling has Alstom, Siemens and Hitachi on the short list, and we know it will be ETCS.