The latest span under the gantry appears to have lots of temporary support falsework.
It is obviously lot easier to erect the viaduct on dry land where sections can be lifted by crane or built in situ on temporary supports.
Not sure what plan is, but possibly the big Dominique gantry won't need to pass under the high voltage cables, and end spans will be built from ground up instead of being lifted forward.
I suspected that too, since it's what was done for the Toulouse Metro project recently. One of those spans being assembled on falsework collapsed, with the death of two site workers (which you may remember).
But no, in the PWI presentation on this viaduct (see post #157), on slide 40 (40:20), it says:
- Lower headroom allowing to pass under the HV power lines
I think the lower headroom comes from the fact that the sections, in lifted position, don't need legs as long as in the Hong Kong project to pass through the legs.
There is also a diagram of the power lines clearance geometry, which is far too small to read. But it does have "6.3m > 4.6m = OK" is big letters, which presumably is about the clearance itself. Of course that might apply to other power lines and not this one, but I don't think so.