Not au fait with Braintree, but i'll guess its one train in section? What are they assuming as the turnaround at each end? 9 minutes as now? What is the plan with the LCs, as they appear to put a spanner in it? I take it no new infrastructure is to be built and this is cheap as chips? The distances between the stations means that you aren't going to get a lot, if anything, from linespeed to be honest. They need to look at the Witham end and the 10mph to start with IMO.
I was discussing this with my colleague on night shift this week, and I think he said they're assuming a four-minute turnaround.
It is one train in section at the moment, but from the brief he's been given it looks like they want to go to two.
He's been given an outline of four suggestions:
- New platform at Braintree
- New platform at Witham
- Increase in line speed
- Installation of a loop
My knowledge of track geometry is very limited, I suppose it'd be things like easing radii and increasing cant?