What is the rough comparative cost of sleepered rails and concrete slab track?
Why would have, for instance, much of the "East London Line" Overground rebuild been done in the latter? Presumably the concrete will last for, say, 60 years, so very long term, is it cheaper?
The ELL was done in concrete as a noise reduction scheme.
Yd for Yd it is considerably more expensive than conventional track, and brings with it the need for special sub-grade treatment, as well as drainage.
Once down it should last indefinitely.
The section of the Fast lines at Carlton Road Jct and Mortimer St tunnel was installed during 1978, and is still going strong, and represents the first mainline use in the UK. There were a variety of problems at this location including both clearances, as well as stability, issues with the retaining walls in the cuttings.
A test section on open line has been laid on the Manchester Lines just to the north of Crewe within the last few years.
Concrete track is preferred where there is a particularly tight clearance problem, as the track is installed in a permanently fixed position which means that the clearances can be reduced against what is possible on fully ballasted track.