Passing through Bristol today, I noticed bulldozers hard at work in the triangle at Patchway (between the two Cardiff lines and the Avonmouth line).
I assume this is the start of construction of the GW IEP depot.
It also marks the start of Agility (ie Hitachi) spending big money on the project, rather than Network Rail or DfT.
There was also new trackwork taking shape west of Patchway which I imagine is for the new depot access.
Meanwhile, standing on Temple Meads station, it seems a tall order to get the place and the local area ready to receive electric trains in just 3 years' time (electrification, remodelling and resignalling).
I know the High Output Plant starts work soon on the OHLE route, but it would be interesting to know what other work will have to be done before the wires get switched on, and which can be left until later.
I wonder if NR will manage to wire both routes to Bristol by 2016, or prioritise the Bath route over Badminton until the 4-tracking is done towards Filton?
I assume this is the start of construction of the GW IEP depot.
It also marks the start of Agility (ie Hitachi) spending big money on the project, rather than Network Rail or DfT.
There was also new trackwork taking shape west of Patchway which I imagine is for the new depot access.
Meanwhile, standing on Temple Meads station, it seems a tall order to get the place and the local area ready to receive electric trains in just 3 years' time (electrification, remodelling and resignalling).
I know the High Output Plant starts work soon on the OHLE route, but it would be interesting to know what other work will have to be done before the wires get switched on, and which can be left until later.
I wonder if NR will manage to wire both routes to Bristol by 2016, or prioritise the Bath route over Badminton until the 4-tracking is done towards Filton?