Great Western Electrification Progress

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
Steventon

Swindon to Steventon on the Up ran last night.
http://www.realtimetrains.co.uk/train/B14191/2018/05/08/advanced

Tonight & tomorrow night there is a working on the down.
http://www.realtimetrains.co.uk/train/B14193/2018/05/09/advanced
http://www.realtimetrains.co.uk/train/B14193/2018/05/10/advanced

Possible that the wire gaps are being done!

The Thursday night working didn't run. Therefore the Down Loop is still not wired from the west end to east of the A34 bridge. The Mains are done.

Steventon Bridge will also need temporary parapet work before a switch on, IMO.

DSC00909.JPG DSC00910.JPG DSC00911.JPG DSC00912.JPG DSC00913.JPG DSC00914.JPG DSC00915.JPG DSC00916.JPG DSC00917.JPG DSC00918.JPG
Views at the Steventon end (7), and Potash Lane bridge (3).
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
^^^Potash Lane is not marked on Google Earth but I assume what is meant is what GE calls 'Milton Park' (the dualled access road), judging by what I see on Street View and comparing with your photos (for which many thanks as always).
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
^^^Potash Lane is not marked on Google Earth but I assume what is meant is what GE calls 'Milton Park' (the dualled access road), judging by what I see on Street View and comparing with your photos (for which many thanks as always).
Correct. Right next to (east of) the A34 bridge.

Also a small temp electrification depot & a access point on the Up side.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
The Thursday night working didn't run. Therefore the Down Loop is still not wired from the west end to east of the A34 bridge. The Mains are done.

Steventon Bridge will also need temporary parapet work before a switch on, IMO.

View attachment 46641 View attachment 46642 View attachment 46643 View attachment 46644 View attachment 46645 View attachment 46646 View attachment 46648 View attachment 46649 View attachment 46650 View attachment 46651
Views at the Steventon end (7), and Potash Lane bridge (3).
So, to clarify - has the gap between the "dead" Steventon-Swindon section and the "live" section east of Milton Jct been wired up on the Mains?
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,522
Slightly confused by the wording of your reply - are you implying that IETs won't use the wires even though the OLE is live?

The OLE being live and the OLE being signed off for use by trains in passenger service are two different milestones.

OLE should be energised for the first time end of May BH weekend. There is a considerable amount of testing to be done before it is signed into passenger use by the ORR - and there is only one person in the country qualified to do so.

While I’ve not read any firm dates lately; likelihood is that sign off will be towards the very end of the year again.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556
Why so long for the sign off? Blackpool was switched on last Sunday 6th May with passenger service expected on 21st May.
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,522
Why so long for the sign off? Blackpool was switched on last Sunday 6th May with passenger service expected on 21st May.

Pass, Maidenhead - Tilehurst was completed July 2017; signed off late December 2017. Tilehurst - Didcot was completed September 2016; signed off late December 2017. As I understand it all the sign offs are done by one inspector from the ORR; so I guess a lot revolves around their scheduling.

The plan had previously - as discussed wayyyyy up thread - been for all of Didcot to Cardiff to be signed off at once. Perhaps that has changed; but not heard anything to suggest it has.
 

jimm

Established Member
Joined
6 Apr 2012
Messages
5,276
Why so long for the sign off? Blackpool was switched on last Sunday 6th May with passenger service expected on 21st May.

Perhaps because there are a lot more route miles, with quadruple-track sections and quite a lot of junctions, from Didcot to Cardiff and Reading to Newbury, as opposed to what is essentially 17.5 miles of double track, with one junction mid-way along and some sidings at the Blackpool end, so there were far fewer things to inspect and test in Lancashire.
 

spark001uk

Established Member
Joined
20 Aug 2010
Messages
2,385
Also the long sign-off of the Tilehurst-Didcot section was due in part (or possibly only?) to the investigation into the interference issues they were having.
 

Ploughman

Established Member
Joined
15 Jan 2010
Messages
3,097
Location
Near where the 3 ridings meet
The OLE being live and the OLE being signed off for use by trains in passenger service are two different milestones.

OLE should be energised for the first time end of May BH weekend. There is a considerable amount of testing to be done before it is signed into passenger use by the ORR - and there is only one person in the country qualified to do so.

That's a bit risky isn't it?
Accidents, Sickness, Holidays and demand being a number of factors.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Update time again!
GWML Electrification: State of Play, week beginning 14/5/2018

Paddington to Didcot - LIVE
  • All main line tracks wired within the M25.
  • TTCs near Ealing Broadway over the Down Main to replace headspans.
  • Everything wired at Reading (bar P4-6 which were never in the plan). Includes the TCD & the curves, down to Reading West (see B&H section).
  • Current *live* wires end at 54m 51ch on the Mains (just short of Milton Jct; 55m 19ch); the section from Steventon has extended eastwards along the Mains to fill the gap. The *live* Didcot Relief Line (Did. RL) OLE ends at Foxhall Jct (53m 55ch); wires have now extended along the Did. RL to the existing wires at Steventon (see below).

Small Points
  • First few yards of Windsor and Marlow branches wired.
  • ATF wires in operation from Maidenhead to Didcot; Kensal Green to Maidenhead currently only using return conductors but will be AT-ready in the near future.
    • In preparation for the Elizabeth Line running to Maidenhead, Hayes & Harlington to Maidenhead was closed off over the Early May Bank Holiday (5/5 to 7/5); this included renewals of S&C at West Drayton & Slough West Jct, alongside HOPS work at Langley. Paddington to H&H was also closed on May 6th, and encompassed final OLE works for Crossrail, alongside (presumably) ATF installation, finishing of Platform Extensions, lift shaft installation, passenger footbridge installation, and ticket hall foundation installation.
  • On May 20th, all lines between Paddington and H&H will be closed until 0800.
  • Twyford platform extensions almost finished, canopy and bridge parapet works complete.
  • Few masts and cantilevers now up on the Didcot Avoiding Line, which finish at Appleford; Appleford LC being the limit of wires for the time being.
  • Oxford Lines west of Didcot Pkwy wired as far as the loco fuelling sdg; Down Oxford as far as 53m31ch, Up Oxford as far as 53m42ch. Didcot avoiding lines have sprouted masts (4 portals, 2 TTCs), with a wire pair over the Down Didcot Avoider.

Didcot - Swindon: due to go live end of May 2018
All steelwork (including SPS) looks to be complete around Milton Junction, the last unwired section between the main Steventon-Swindon wires & the existing live section.
A note on Steventon: Wires up over the Level Crossings & under the High St Bridge (aka the "Brunel Bridge"); however, the bridge may well be demolished in CP6. The discussion continues.
Another note on the OLE west of Didcot - while it may be going live soon enough, it may not be signed off for passenger service until December.

Steventon-Uffington-Swindon
  • In the Steventon area (between MP55 3/4 and MP57 1/4), all wires over the Mains are up, with wires now extending eastwards to the existing live section at Milton Jct.
  • *That* bridge at Steventon might need temporary parapet work, to protect the general public from stray currents after live wires extend to Swindon.
  • The Down Steventon Goods Loop (DSGL; 55m 19ch to 56m 32ch) remains unwired.
  • Wires over the Mains continue to approx MP72 1/4, where a small gap just east of Bourton X-overs remain only on the DM (the UM now being done). Both Bourton & Uffington X-overs wired.
  • West of Bourton the DM wires resume, continuing to the western end of Swindon Station (see below).
    • The USGL at Stratton (Swindon Up Goods Loop) is also wired.
    • East of County Rd underbridge, the USR (Up Swindon Reception) & DSG (Down Swindon Goods) are also wired; on the USR, both wires are up to the east of the NR training centre, catenary only west of there.
Swindon Station
  • Wires (both Catenary & Contact) up through P4 (Down Main) & the through Road (Up Main); these terminate in the Tensorex drums at the western end of the station. Platform 1 (USPL - Up Swindon Passenger Loop) is now wired too.
  • The Catenary wire on the USR runs through P3 and onwards to the Up Relief (UR), opposite the old Swindon 'B' PSB. The UR is then fully wired west of there to the existing wires at Rushey Platt (78m 36ch). A length of contact wire has gone up through P3, but the dropper arms have not yet been fixed to it.
  • All large steelwork and SPS appears to be up through the station.
  • The gaggle of tall masts at the Bristol end of the Main lines now have cables over them; this must be for ATF purposes.
Swindon-Wootton Bassett Jct
  • Wootton Bassett Jct (83m 07ch) is now fully wired. The Up Wootton Bassett Goods Loop (UWBGL) has also been fully wired.
  • Wires on both DM & UM resume around MP 77 3/4; these continue to MP96, just west of Hullavington (see below).

The "Main Line"; Wootton Bassett Jct - Chippenham (Cocklebury Lane Bridge)
Until further notice, the 25kV transmission wires will run in a trough from Cocklebury Lane Bridge (just east of Chippenham) to Thingley Jct. Large steelwork is expected to remain in situ until wiring is authorised west of Thingley, but some specific items may be poached if required elsewhere (and duplicates aren't stored at RAF Wroughton). Details given in the "Postponements" section.
  • In the Down Cess just west of Wootton Bassett Jct, a lot of SPS is stored on pallets, ready to be installed.
  • Track lowering and drainage work at Dauntsey completed.
  • Nr Tockenham Wick, pretty much all the masts are up, TTCs, STCs and portals alike; most have SPS fitted now.
  • First few headspans (?) erected over 25/6th of Feb '17 at Dauntsey Bank (87m ish), and some (not all) of the missing masts have gone up too, plus brackets for fittings.
  • Langley Burrell (east of Chippenham)
    • In the Crossing Rd area, all TTC-bearing masts appear to be up with their booms on. These masts have extended east towards Christian Malford too.
    • Most STCs here have their SPS up, folded out of the way; these masts also have ATF wire brackets fixed at the top.
    • Some of the thicker STC masts, which have TTC-style tubular booms fitted, aren't yet dressed with SPS. The TTC "Tensorex" portals at Langley Burrell don't yet bear the Tensorex drums which will eventually go up there.
    • Works compound established at Langley Green L.C.
    • Single run of earth wire on the Up side between Langley Burrell & Christian Malford.
    • Masts also up (with booms) south of Langley Burrell to Cocklebury Lane Bridge (the new western limit of wiring on the route); SPS starting to appear on the thinner uprights.
    • As yet, no masts west of there but piles are in. Some mast components are in the Down side cess just west of Cocklebury Ln.
Chippenham (Cocklebury Lane Bridge) - Thingley Jct
  • No piles in Chippenham station, nor any masts affixed to the viaduct.
  • All piles in and majority of masts (and cantilevers) up from the western end of the viaduct to Thingley Junction (where the feeder station will be). About 6 masts are up in the vicinity of Thingley Feeder Stn, one of which has a TTC boom affixed.
    • Piles continue westwards to the next bridge.
    • Piles also in (and have been for over a year) at Ashley (beyond Box Tunnel).
Thingley Jct - Bath
No wiring for the foreseeable future, but overbridges between Thingley Jct & Corsham have all had clearance works, along with Box Tunnel (track lowering) and Sydney Gardens (track lowering).
Bath to Bristol
Piles in, particularly around Saltford. Not due to see use for a while after the wiring delay. Track lowered through Bath Spa, Oldfield Park & Keynsham in readiness for future wiring.

South Wales Main Line (Wootton Bassett Jct-Bristol Parkway-Severn Tunnel-Newport-Cardiff)

Wootton Bassett Jct - Bristol Parkway; apparently set to go live in September 2018.
  • 11 odd miles worth of wires up from Wootton Bassett (MP 83 1/2) to around MP96, just west of (and including) Hullavington Loops & crossovers.
    • All masts and most SPS appear to be up around Acton Turville.
    • Retaining walls drilled & bars inserted, ready to fix masts, at the eastern portals of Alderton Tunnel (97m 34ch) and Chipping Sodbury Tunnel (101m 06ch).
    • O/H Conductor rail installed in Chipping Sodbury Tunnel (MP101 to MP103 1/2).
  • Progress as well around Chipping Sodbury/Old Sodbury:
    • most (if not all) masts up, many with booms attached.
    • SPS now appearing too, over all lines; the Down Badminton (DB), the Up Badminton (UB) & Chipping Sodbury Goods Loop (CSGL). Still a lot left to install between the loop (104m 18ch) & the west portal of C.S. Tunnel (103m 48ch); it could be implied that work is more advanced at the Chipping end than the Old end.
  • Wires have now reached the footbridge at Yate (just east of Westerleigh Jct).
  • From Westerleigh Jct to Bristol Parkway; fewer than 20 bases are mastless now. Most SPS is concentrated at the Westerleigh end; the central part between there still needs masts, unbelievably.
    • A run of masts (all boomed) has sprouted on the curve towards Cheltenham Spa.
  • Majority of SPS up on the STCs and TTCs to the west & east of "The Dramway" footbridge nr Ram Hill (Coalpit Heath); a pair of single masts which seem to be destined for a portal boom can be found just east of the bridge (https://flic.kr/p/23WGyV5).
  • Huckford Viaduct has had bespoke mast fittings applied.
  • The "Blue Viaduct" over the M4 just east of BPW now has SPS up on the masts along it.
  • Winterbourne Viaduct is currently mastless.
  • BPW Platforms extensions complete.
    • TTCs up over all platforms as of 20/3, along with the Down Bristol Goods Loop (opposite P1).
    • Portal now up at the eastern end over all lines through the station. Nothing more up further east on the approach though.
Bristol Parkway - Pilning
  • 2 boomed masts are up at the Welsh end of Bristol Parkway, and a concrete foundation awaiting a mast can be seen next to them.https://flic.kr/p/245kEME
  • Stoke Gifford IEP Depot all wired.
  • Patchway Tunnels conductor rail to be installed, 16/6/18 to 6/7/18. Track-lowering and drainage work to be undertaken in the "old" tunnel (on the Cardiff-bound line) in the same time period.
  • Masts, booms and SPS up through Patchway. When the conductor rail is being installed (16/6 to 6/7), wires will also be strung up through Patchway.
    • Cattybrook Brickworks Bridge closed as of 18/3/18.
  • At Pilning, piling and masts appearing towards both Cattybrook & Severn Tunnel (https://flic.kr/p/26twWMw), Platform 2 now closed. SPS going up on some portals and masts too.
Approx. 70% masts now up between BPW and Severn Tunnel.

Severn Tunnel - Newport
  • Severn Tunnel Conductor rail in place .
  • All bridge rebuilding complete from Severn Tunnel Jct (149m 14ch) to Bishton Flyover (152m 30ch).
  • Masts beginning to go up between Severn Tunnel Jct & Bishton Flyover, as of 3/4/18. These include:
    • About 3 west of "the ramp" bridge at Magor; 2 on the Down side, 1 on the Up side (https://flic.kr/p/2333VJs). Another can be found on the Up Side, west of the W End/Main Rd footbridge.
    • Masts (with SPS fitted) up between Bishton Flyover (including over it) and Llanwern West Jct (156m 20ch). 5 masts are currently up on the curve down from the flyover at its eastern end.
      https://flic.kr/p/23NSDKD and https://flic.kr/p/23NSCRp.
  • Some masts have sprouted near Lliswerry pond.
  • 6-track portals, probably TGBUs (aka Thumpin' Great Big-Uns) going up aroung East Usk Yard (approx. MP157 1/2).
  • Between the Maindee Jcts (157m 74ch to 158m 16ch), a cluster of piles is in beside the Down Relief; these are complemented by masted piles on the Main side (adjacent to the Up Main).

Newport
  • P2 & P3 Canopies all cut back; P1 canopies still in progress.
  • Masts and portals now appearing at the western end of the station, some with SPS attached. More started to appear in mid-April; additionally, two at the Cardiff end & two through the P1 canopy on the weekend of April 28th/29th.
  • Some concrete bases in between stn & tunnels, perhaps for portals.
  • Old stn footbridge still in situ.

Newport - Cardiff
  • Approx. 97 masts from Ebbw Jct (160m 7ch) to Marshfield (163m 60ch). Booms & SPS starting to appear in the area too.
  • Green Lane Bridge, nr Marshfield (164m 57ch) reopened to traffic after reconstruction. Masts (with SPS) up around here too.
  • Some of the masts near Duffryn have SPS affixed.
  • Two TTCs, one on each side of the tracks, have been erected by the bridge at Rhymney River Bridge Jct (167m 61ch).
  • About 4 or 5 portals have been erected just west of Pengam Jct (168m 40ch); 5 masts are up on the Up side east of Rover Lane bridge, complemented by 2 on the Down side.
Cardiff Central
  • Re-signalling completed. Platform 0 now open. 3 masts now up over P0/1 with TTC booms.
  • Piling underway at the extreme ends of P1/2 & P3/4 for future masts. One can assume portals will bridge the gap between P2 & P3, over the Through lines.
Swansea IEP Depot
  • New IEP Depot at Maliphant Sidings, Swansea now complete; all steelwork up but no wires.

GWML/SWML Blockades:
  • 14/4 & 15/4 - Swindon; done.
  • 26/5 to 28/5 - Swindon.
  • 23/4 to 25/5 (exc. weekends): Swansea-Padd services will leave Swansea earlier & arrive at Swansea later.
  • 30/4 to 18/5 (exc. weekends): most Cardiff-Taunton services curtailed to run between Bristol Pkwy & Taunton only. All Cardiff-Portsmouth services will run to amended schedules, some calling additionally at Patchway & STJ.
  • 16/6 to 6/7: Bristol Parkway - Severn Tunnel Jct will be under a big possession for wiring.
  • 24/12/18 to 1/1/19: Bristol Parkway - Newport will be blockaded again for more OLE works.
  • More Blockades will follow, but GWR hasn't yet released details.

Berks & Hants Line (Reading-Newbury)
Reading-Newbury set to go live from December 2018; electric trains in service from January 2019.
Reading West-Southcote Junction

  • Through Reading West to Southcote Jct, perhaps 60% (up from 50%) of masts at best up.
    • These are mainly between Tilehurst Rd Bridge and the A4 (Bath Road) Bridge south of Reading West; a cluster of about 6 (5 on the Down side, one on the Up) are also up just short of Southcote Jct (37m 62ch).
    • 4 additional masts on the Up (Reading) side parallel to Southcote Jct.
    • Long-standing mast at Southcote Jct by the Up line from Newbury has recently had a support added.
Southcote Junction - Theale - Wigmore Lane LC
  • From Southcote Jct past Calcot Mill FP crossing to Theale, the remaining masts, portals & cantilevers to be erected are all down to single figures.
  • First SPS up in west of Southcote is around MP 38 1/2; west to Theale, most SPS is either up or beside their assigned mast awaiting installation.
  • Two masts left to go up within Theale station itself; no SPS. TTCs, as predicted, are up over the Down platform.
  • Platform extension works now underway at Theale.
  • From Theale to Wigmore Lane, at the western end of Theale Goods Loop (42m 8ch), SPS is largely complete (except for the loop itself).
Wigmore Lane LC - Aldermaston - Midgham - Thatcham - Newbury Racecourse
  • During the April blockade, wires went up over both lines from Wigmore Lane, through Aldermaston, to the existing wires at Midgham (including Ufton/Towney Loop); this means a continuous run of OLE now runs from Wigmore Lane to just east of Kennet Viaduct (nr Newbury Racecourse).
    • A short wire run from just east of Racecourse to just east of the overbridge linking the RC to Hambridge Lane has appeared on the Up line;
    • there is still a gap between this section and the main wired "Theale to Thatcham Section" over Kennet Viaduct.
  • The Down platform extension at Aldermaston is mostly in, unlike at Thatcham (where work is likely to take longer than the next blockade). The missing concrete panel is now on site awaiting fitment.
  • Work on Thatcham's platform extensions continued during the second blockade; the Down side is more advanced than the Up, but sections of platform are now on site.
  • RC east X-overs still need wiring.
  • All heavy steelwork at Newbury Racecourse (52m31ch) is in; TTCs over the Main lines and a portal over the western throat of the station. (moved from section below)
Newbury Racecourse - Newbury Town
  • About 5x Portal booms & some STCs are left to be installed between Newbury's stations. Most masts between Boundary Rd Bridge & Winchcombe Rd Bridge (the A339) are now up, a gaggle of taller masts (presumably for another ATF feeder station) can be seen opposite the Sainsbury's.
  • The electrical substation/PSU at Boundary Rd looks roughly 60% complete; 1 of the 5 portal spans is due to go up adjacent to it.
  • At Newbury (53m 06ch), the new footbridge is now open (not the lifts yet); piling also taking place within the station, on the platforms. About 4 masts behind P1, along with a handful behind P2/P3 have also sprouted. About 6 masts left to install. Nothing so far between the two footbridges; presumably NR are waiting for the old bridge's removal before adding more masts.
  • Canopies have been cut back during the 2nd Blockade, to allow the old footbridge to be removed.
  • Between the western end of the platforms at Newbury, & Bartholomew St Bridge (at the western throat of the station), all the masts have had portal booms affixed. (It can be assumed that the portal booms will extend throughout the station.)
  • West of Bartholomew St Bridge, the uprights (no booms or SPS) extend past Rockingham Rd Bridge (about 200m west of the station) to roughly MP53 1/2; seems to be only one mast missing (the pile is, however, in).
Proposed Limit of Wiring: 53m 51ch.
Gives ample room to reverse even a 12-car 387 formation.
Immunised signalling continues to about MP55 1/2.

B&H Blockades:
  • 12/3 to 15/3; done.
  • 23/4 to 26/4; done.
  • 14/5 to 17/5; underway.
  • 2/6 to 7/6,
  • 9/7 to 12/7,
  • 16/7 to 5/8,
  • 28/8 to 30/8,
  • 8/10 to 11/10,
  • 19/11 to 22/11.

Project Postponements
  • Thames Valley Branches: Windsor & Henley deferred to CP6. Marlow removed from scope of current programme.
  • Appleford LC to Oxford paused, pending track realignment and resignalling of Oxford (1/7 to 22/7); if CP6 accounts allow for wiring to be extended to Oxford, it would be very likely to happen.
  • Catenary & Contact wires between Chippenham (Cocklebury Lane Overbridge) & Thingley Jct have been deferred until (presumably) CP6; presumably this will wait until Bath-Bristol resignalling is complete. All Large steelwork to remain, unless required elsewhere.
  • Bristol Temple Meads to Bath & Bristol Parkway paused, dependent on Bristol resignalling (Taunton-Parkway over Easter 2018; Temple Meads to Both in October 2018), track remodelling and Filton Bank 4-tracking (to be completed by December 2018).
  • Bristol Temple Meads' "Midland Shed" to be reopened in CP6, after Bristol resignalling is complete and the PSB is demolished.
As always, do let me know if I've missed anything!
(apologies to anyone who saw it in a state of source code chaos too)
 

MarlowDonkey

Established Member
Joined
4 Apr 2013
Messages
1,826
Community Notice Board, looking forward to the introduction of 345's.

Aren't Maidenhead and Twyford keeping a couple of trains an hour off peak running semi-fast to Paddington? Presumably these will remain as 378s? Through trains to Central London destinations would be a mixed blessing if essentially they are all station S8s.
 

gwr4090

Member
Joined
9 Nov 2011
Messages
144
Many thanks to 59CosG95 for keeping us so fully briefed on progress. But there is no mention of Southcote Jn to Basingstoke electrification which is a part of the GWML project. If I understand correctly, it has been deferred like Didcot-Oxford and the various branches ?
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,464
Location
Preston Lancs
Many thanks to 59CosG95 for keeping us so fully briefed on progress. But there is no mention of Southcote Jn to Basingstoke electrification which is a part of the GWML project. If I understand correctly, it has been deferred like Didcot-Oxford and the various branches ?

I thought it was part of electric spine?
 

Phil G

Member
Joined
16 Oct 2017
Messages
183
I don't think anyone has mentioned progress on Bristol Parkway to Temple Meads. There are masts and booms installed along the chord going to Filton Abbey Wood that reach nearly to the junction which will presumably end there until CP6.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,233
Many thanks to 59CosG95 for keeping us so fully briefed on progress. But there is no mention of Southcote Jn to Basingstoke electrification which is a part of the GWML project. If I understand correctly, it has been deferred like Didcot-Oxford and the various branches ?

It was initially, but has since been moved to the Thames Valley wiring programme IIRC. I'll add it in for next week's update.

It was once part of the "Thames Valley branches" sub-project, but currently has its own pages in the CP5 enhancements delivery plan. However it is currently showing "Assumed CP6" but the other branches are "CP6" which is subtly different...
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
I don't think anyone has mentioned progress on Bristol Parkway to Temple Meads. There are masts and booms installed along the chord going to Filton Abbey Wood that reach nearly to the junction which will presumably end there until CP6.
Thanks for that @Phil G, adding in for next week's update.
 

Thatcham Xing

Member
Joined
1 Nov 2016
Messages
173
Progress in the 3rd B&H Blockade: Network Rail have tweeted pictures of wiring work underway between the Newbury stations.

Just been for a quick look, lots of Orange Army at work putting up SPS, and also a wiring train in evidence in the Racecourse Station area.

More work also underway on the up platform extension at Thatcham (platforms closed-off so hard to get a pic).
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
B&H
MPV's from Swindon to Racecourse yesterday evening.
http://www.realtimetrains.co.uk/train/B14196/2018/05/13/advanced
One to the Reading end this evening.
http://www.realtimetrains.co.uk/train/U37701/2018/05/14/advanced

Gathering of road-rail plant at Theale & Burghfield Road. East of Theale to Southcote is open during the day for the passenger service to the loop platform & freight.

Platform lift & Road-Rail crane working Theale Down platform by missing masts.

Murphy's been working at Reading West over the weekend.
DSC00928.JPG DSC00922.JPG DSC00926.JPG DSC00923.JPG DSC00924.JPG DSC00925.JPG DSC00929.JPG DSC00930.JPG DSC00927.JPG
Down canopy roof removed opposite the piles for the footbridge on the Up.
Looks like they may have found asbestos waste on the old down ramp access, yellow signs.
 

Sean Emmett

Member
Joined
9 Mar 2015
Messages
522
Thanks for that @Phil G, adding in for next week's update.

See my post 6883.

To recap:-
1m 18c Easton Rd overbridge completely rebuilt.
2m 12c Narroways footbridge replaced.
3m 11c Ashley Hill footbridge replaced
3m 62c Bonnington Walk overbridge - parapets raised.

Big unanswered question I raised on the Filton 4 tracking visualisation page is whether the works to raise Church Rd overbridge at Lawrence Hill and Constable Rd bridge at 3m 29c will still go ahead as part of the 4 tracking contract. It would appear not, but would be grateful for confirmation.

There's also the footbridge south of Filton Abbey Wood (4m 18c) to be dealt with if electrication is to happen.
 