I'm just travelling from Chippenham to Swindon and there is a lot of SPS on pallets in the down cess just before Wootton Bassett, so it looks like there is some work going on there. After the junction a lot of the SPS looks to be installed along with the earthing wire, albeit on temporary pulleys.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

bastien

Member
Joined
14 Aug 2016
Messages
427
Temple Meads is quite a bizarre station isn't it. On the one hand it is easily one of the UK's most beautiful, but it's really awkwardly placed in relation to the city and the streetscape, but the the platform-access underpass, and draughty-open nature of it (in winter) are not great for the principle station of one of our major cities. Is any serious refurbishment/rebuild being planned except for these minor 'tweaks'?

In fairness there used to be a lot more 'city' around Temple Meads before the Luftwaffe came along. Not to mention 1960s planners, the docks closing, etc.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
No, you are right. There are TTCs in both directions on the P1/2 island for platforms 1, 2 and 3 (and presumably the avoiding line south of P1). The P4 ones are just for that platform (and maybe that avoiding line too).
That is what I thought - I did forget the Up Avoider though! I'll note that all down.
I'm just travelling from Chippenham to Swindon and there is a lot of SPS on pallets in the down cess just before Wootton Bassett, so it looks like there is some work going on there. After the junction a lot of the SPS looks to be installed along with the earthing wire, albeit on temporary pulleys.
Fab news - I'll put that in the changelog.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,601
Location
Nottingham
Temple Meads is quite a bizarre station isn't it. On the one hand it is easily one of the UK's most beautiful, but it's really awkwardly placed in relation to the city and the streetscape, but the the platform-access underpass, and draughty-open nature of it (in winter) are not great for the principle station of one of our major cities. Is any serious refurbishment/rebuild being planned except for these minor 'tweaks'?
I think the main issue is the cramped entrance/booking hall, which will get worse if P0/P1 blocks the alternative access and creates an extra flow of passengers interchanging between P0/1 and the main subway by the quickest route. The subway itself seems quite spacious, even with several shops in it.

There was a Network Rail document a few years ago that floated the idea of extending the subway underneath the forecourt to reach P0/P1. I'm not sure whether that is going ahead, and if so it won't on its own solve the congestion in the booking area. I'm not sure if anywhere else was/is planned for that - perhaps some of the buildings between P3 and the forecourt could become a ticket hall?
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,461
Location
Preston Lancs
Perhaps slightly OT but I think not, I am actually quite enthusiastic and hopeful about the progress London -Cardiff- I feel better about this than the sad tragedy of Manchester- Blackpool - which is what - 47 miles of route electrification?. Work started in 2012 on that route - so I am really pleased about the GWML. I also think there is much to be learned from what is happening. Keep energizing sections - up to Maidenhead, then Reading, then Didcot - etc. Just got to hope when finished they will do Didcot - Oxford, then BPW-BTM and then backwards/forwards via Bath etc. Love these updates thanks to all.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Perhaps slightly OT but I think not, I am actually quite enthusiastic and hopeful about the progress London -Cardiff- I feel better about this than the sad tragedy of Manchester- Blackpool - which is what - 47 miles of route electrification?. Work started in 2012 on that route - so I am really pleased about the GWML. I also think there is much to be learned from what is happening. Keep energizing sections - up to Maidenhead, then Reading, then Didcot - etc. Just got to hope when finished they will do Didcot - Oxford, then BPW-BTM and then backwards/forwards via Bath etc. Love these updates thanks to all.
Reading the Enhancements Delivery Programme (Thanks @jimm for posting the link), it looks like the Bristol wiring and the Oxford wiring is set to occur in CP6; the resignalling schemes in the next half a year will pave the way for the improvements in those areas. The Thames Valley Branches (not Greenford), along with Southcote Junction to Basingstoke have also been deferred to then, according to the EDP slideshow - I'm eagerly awaiting the March '18 update.

Cardiff-Swansea doesn't seem to be so lucky however.
I have the memory of a sieve when it comes to why the section west of Cardiff got "Graylinged"; I assume cost overruns combined with a lack of concrete answers on what the Welsh Gov't wanted in the Valleys had something to do with it. (If anyone knows more about it, do post it down - I'm sure I'm not the only one who needs a reminder!)
 

mr_jrt

Established Member
Joined
30 May 2011
Messages
1,574
Location
Brighton
Would it ever be worth buying up the large light industrial properties over the Avon on the west side of Bath Road to realign the tracks through Temple Meads to eliminate most of the reverse curvature? They could be easily replaced on the other side of the new tracks...
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Reading the Enhancements Delivery Programme (Thanks @jimm for posting the link), it looks like the Bristol wiring and the Oxford wiring is set to occur in CP6; the resignalling schemes in the next half a year will pave the way for the improvements in those areas. The Thames Valley Branches (not Greenford), along with Southcote Junction to Basingstoke have also been deferred to then, according to the EDP slideshow - I'm eagerly awaiting the March '18 update.

Cardiff-Swansea doesn't seem to be so lucky however.
I have the memory of a sieve when it comes to why the section west of Cardiff got "Graylinged"; I assume cost overruns combined with a lack of concrete answers on what the Welsh Gov't wanted in the Valleys had something to do with it. (If anyone knows more about it, do post it down - I'm sure I'm not the only one who needs a reminder!)

Here is the original statement to the Commons on the cancellation of Swansea:

https://www.parliament.uk/business/.../written-statement/Commons/2017-07-20/HCWS85/

and here is the press release:

https://www.gov.uk/government/news/...assengers-in-wales-the-midlands-and-the-north

The announcement on Oxford, the two routes to Bristol TM and the two Thames branches (Windsor and Henley) was made eight months earlier, in Nov 2016. If I remember correctly, the term used was "deferred". It is widely expected that some or all of them will be revived in CP6 but this has not been promised and they will have to re-make their case.

I think Basingstoke dropped out at the time of the Hendy review???

If the Marlow and Greenford branches were ever included then they were dropped longer ago.
 
Last edited:

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Would it ever be worth buying up the large light industrial properties over the Avon on the west side of Bath Road to realign the tracks through Temple Meads to eliminate most of the reverse curvature? They could be easily replaced on the other side of the new tracks...
Not without major reconstruction of Bath Road itself, along with the roundabout.

Here is the original statement to the Commons on the cancellation of Swansea:

https://www.parliament.uk/business/.../written-statement/Commons/2017-07-20/HCWS85/

and here is the press release:

https://www.gov.uk/government/news/...assengers-in-wales-the-midlands-and-the-north

The announcement on Oxford, the two routes to Bristol TM and the two Thames branches (Windsor and Henley) was made eight months earlier, in Nov 2016. If I remember correctly, the term used was "deferred". It is widely expected that some or all of them will be revived in CP6 but this has not been promised and they will have to re-make their case.
[POLITICS] I find it almost amusing that the website said that "Disruptive electrification works would no longer be needed"; it would be funny if I wasn't so disappointed by the announcement.
Grayling's approach to this seems to be akin to an undergraduate who wants to put the absolute minimum into his studies and still graduate with a 2:1 - personally I feel that if the cancellation excuse was worthy enough then yes, it should have been cancelled, but with the excuse submitted to the Commons I would suggested postponement.
I suspect that, if the Senedd gets their act together (could take a night, could take 5 years), they might push for the job to be finished. [/POLITICS]
 
Last edited:

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
In fairness there used to be a lot more 'city' around Temple Meads before the Luftwaffe came along. Not to mention 1960s planners, the docks closing, etc.
That's not true, if you mean 'city' to mean offices and business. The area around TM was mainly goods yards and factories pre-war. People then tended to bus, walk and cycle to the factories (cigarette packets, breweries. and other drug industries!). Yes, some used the local railway connections.

TM is now almost the centre of Bristol in the make and in any case, one can walk to what people consider the Centre in about 10 minutes, due to a much improved walking route across Queens Square. (I know, it's Queen Square but nobody in Bristol says that). Also, many frequent buses now start from the Incline, including frequent coach to the airport. The Metrobus will be less convenient, sadly, I admit.

TM has never been so well connected but one could waste a lot of the time saved by the IET in getting from Temple Way to Platform 13 - 15, which is why starting the fast service from Platform 0 and 1 will be key to its success.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
Would it ever be worth buying up the large light industrial properties over the Avon on the west side of Bath Road to realign the tracks through Temple Meads to eliminate most of the reverse curvature? They could be easily replaced on the other side of the new tracks...
That's already there -it's the SPM avoiding line and surrounding depots! Leaving aside the 'Arenal' project, it doesn't solve the need for the entrance from Filton, unless even more demolition would be envisaged. In fairness, the St Phillips /St Philip's Marsh area is nearly all light industry and physically could easily be removed, but Bristol's strength is its light industry and start-ups (think Wallace and Gromit - now so big it's moved!).
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,229
I think Basingstoke dropped out at the time of the Hendy review???

If the Marlow and Greenford branches were ever included then they were dropped longer ago.

Southcote Jn to Basingstoke was separated from the "Thames Valley branches" a few years ago, but still appears further on in the latest EDP document as a distinct project and is still "assumed CP6'.

Bourne End and Marlow was included initially, but removed once the difficulties with rolling stock and existing platform lengths became clear. To the best of my knowledge Greenford was never considered in any published list of GWML based projects.
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
Reading West to Southcote Review.

Activity at Reading West appears to be just Murphy's work on the new footbridge and reinstatement of the down side access. There are no piles in yet for the overhead masts.
No one on site today, appears main work activity will be Saturday nights.
DSC00681.JPG
Views of station and old FB towards Oxford Road Junction.
DSC00699.JPG DSC00694.JPG
View from down platform towards the to be reinstated Oxford Road access.
DSC00695.JPG
Piles for the new FB on the up side.
DSC00698.JPG DSC00696.JPG
Two views towards Southcote from the station and one each way from Tilehurst Road bridge.
DSC00697.JPG DSC00679.JPG DSC00680.JPG DSC00683.JPG
Second photo, right side opposite platform is the first pile south of Oxford Rd Jn.
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
Reading West to Southcote cont.

It is possible to view the whole section from lineside locations. Next bridge after Tilehurst Road is the A4 Bath Road bridge.

First is back towards Tilehurst Road and the other are towards Southcote just short of the actual junction.
DSC00684.JPG DSC00688.JPG DSC00686.JPG DSC00687.JPG
FP along the side of Southcote Junction looking back towards Reading West.
DSC00690.JPG DSC00691.JPG DSC00692.JPG DSC00693.JPG
Five masts on the up side are recent.

Southcote Jn towards Newbury. Nearest mast has been up a while but the support is recent.
DSC00689.JPG
 

coppercapped

Established Member
Joined
13 Sep 2015
Messages
3,315
Location
Reading
SNIPPED

Cardiff-Swansea doesn't seem to be so lucky however.
I have the memory of a sieve when it comes to why the section west of Cardiff got "Graylinged"; I assume cost overruns combined with a lack of concrete answers on what the Welsh Gov't wanted in the Valleys had something to do with it. (If anyone knows more about it, do post it down - I'm sure I'm not the only one who needs a reminder!)

From published articles the issue with electrifying the Cardiff-Swansea section was the paucity of suitable trains which would use it. Certainly there would be one train per hour off-peak through to Paddington and possibly one or two more during the peak travel times. Any electrically operated local services to and from Swansea would be limited to the stretch through Cardiff to Newport, there being no real source or sink for local traffic east of Newport which electric trains could reach with the exception of Bristol but that only when the wires up Filton Bank and through Temple Meads were completed. It would be possible to use bi-modes for services through Temple Meads to, say, the south coast but this means that the trains would spend most of their time off the wires.

If the Valley Lines were to be electrified at 25kV then a couple more local trains along the South Wales main line might be feasible.

All this means that the Cardiff to Swansea electrification would power about one full-length train and between two and four short(ish) trains per hour in each direction.

It would seem that making a convincing case for spending so much money on what is essentially a relatively lightly used stretch was difficult.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
FWIW, I didn't mean that, hence the inverted commas.
Ah, I see. In fact of course, it was the old covered goods depot's rebuilding that has led the charge of offices towards TM and this type of development has spread out from there. The Luftwaffe, as you say, 'cleared' the site on the southern side of Temple Way, sadly still containing the tatty developments of the 50s and 60s, but I predict they will go in the next decades, if not sooner.
 

Hellzapoppin

Member
Joined
16 Jan 2016
Messages
266
If you look up at the bridge over Avon street you can still see the shrapnel holes in the steelwork when the station was bombed.
 

Envoy

Established Member
Joined
29 Aug 2014
Messages
3,126
Last night, Bristol City Council decided that a new concert hall/arena would be built on the waste land that is just east of Temple Meads = the old diesel depot. (Some councillors wanted it to go to Filton).

The Cardiff to Swansea line is actually quite busy. As well as the 800’s, local stopping trains would also have benefited from electrification - possibly offering a service between Swansea & Bath. It now looks like the Maesteg line will not be electrified because that was dependent on the Cardiff to Bridgend section of the mainline getting wired. According to posts on the South Wales Metro forum, it looks like the Welsh Government wish to take over the valley lines running north from Cardiff Queen Street and electrify them at 750volt DC for use by trams or tram/trains.

https://www.railforums.co.uk/threads/south-wales-metro.117763/page-58#post-3375632
 
Last edited:

Sean Emmett

Member
Joined
9 Mar 2015
Messages
522
Bristol City Council vote re Arena at Temple Meads was only advisory. Decision will be made by Mayor Marvin Rees in May.
 

Thatcham Xing

Member
Joined
1 Nov 2016
Messages
173
The down side platform extension at Aldermaston looked to be structurally nearly complete when I passed yesterday.

As has been mentioned, progress at Thatcham (where both up and down sides are being extended) seems a bit slower, and when I arrived there the guys in orange looked to be working to re-locate cabling (contained within plastic piping) in the area where the down-side extension will go.

I also understood that the platforms at Theale are being extended, but no sign of any work on that yet as far as I could see.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
The down side platform extension at Aldermaston looked to be structurally nearly complete when I passed yesterday.

As has been mentioned, progress at Thatcham (where both up and down sides are being extended) seems a bit slower, and when I arrived there the guys in orange looked to be working to re-locate cabling (contained within plastic piping) in the area where the down-side extension will go.

I also understood that the platforms at Theale are being extended, but no sign of any work on that yet as far as I could see.
That work may well be occurring in one of the next blockades.
 

Thatcham Xing

Member
Joined
1 Nov 2016
Messages
173
That work may well be occurring in one of the next blockades.

Indeed, I do realise there are several more to come - although hopefully not as many as have currently been scheduled will be needed - as a casual/interested observer there seemed to be a lot of progress made (in many different locations) during the first one :)
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
B&H Southcote to Theale.

Most of the masts are up, odd ones missing throughout. Same with cantilevers, booms/portals, odd ones missing throughout. A lot of SPS going up between MP38 1/2 and the M4 bridge.

Views Theale towards Reading.
DSC00735.JPG DSC00734.JPG

Theale loop platform, masts and base.
DSC00733.JPG DSC00732.JPG DSC00725.JPG

Concrete piles down platform.
DSC00728.JPG DSC00727.JPG DSC00726.JPG

View west.
DSC00723.JPG DSC00731.JPG
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
Theale to Ufton Towney UWC

SPS started to go up between Theale and Wigmore Lane.
Wigmore Lane to Ufton Lane looks nearly ready for wires (mast by Ufton bridge still to be fitted with SPS).

East end of Ufton loop area looks good. West end, where the missing masts recently went up, has at least a cantilever and a boom missing, plus SPS.

New fence and gates at the UWC.

Photos start from east of Ufton Lane.
DSC00721.JPG DSC00722.JPG DSC00718.JPG DSC00717.JPG DSC00716.JPG DSC00715.JPG DSC00714.JPG DSC00711.JPG DSC00712.JPG DSC00713.JPG
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
Ufton Towney to Aldermaston.

Patches of SPS still to go up.
Platform to finish, joint to existing platform, one concrete panel missing.

DSC00710.JPG DSC00709.JPG DSC00708.JPG DSC00707.JPG DSC00705.JPG DSC00704.JPG DSC00703.JPG DSC00702.JPG DSC00701.JPG DSC00700.JPG

Hopefully, during April 23rd block they can get Midgham to Theale wired!
 