Many thanks RD, but what does the highlighted sentence mean. Do you mean the roof? You obviously don't but could you explain please?

Quite difficult to describe (and been looking at photos of P1) - I should have taken a photo!

On P1, and visible from the footbridge, at around the base of the curved roof / above the curved windows, a number of galvanised fixings have appeared with hooks on them, I guess to hold cross wires. They are mid way between the arches, which I found odd. I couldn't see any fittings on P2.

As galvanised metal stands out and was clearly new, I could see no other purpose for them.

Forgot to add, they were also above a mini canopy section at the country end, I did not look elsewhere as I was off to the underground.
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
Quite difficult to describe (and been looking at photos of P1) - I should have taken a photo!

On P1, and visible from the footbridge, at around the base of the curved roof / above the curved windows, a number of galvanised fixings have appeared with hooks on them, I guess to hold cross wires. They are mid way between the arches, which I found odd. I couldn't see any fittings on P2.

As galvanised metal stands out and was clearly new, I could see no other purpose for them.

Forgot to add, they were also above a mini canopy section at the country end, I did not look elsewhere as I was off to the underground.

I just wonder if such is permitted development or whether consent(s) was(were) already obtained. Paddington is grade 1 listed, I believe.
 
Last edited:

w1bbl3

Member
Joined
6 Mar 2011
Messages
325
I just wonder if such is permitted development or whether consent(s) was(were) already obtained. Paddington is grade 1 listed, I believe.

The bridge modification works to enable electrification had been applied for under listed building consent application 16/10069/LBC. The application includes various drawings of the proposed works.
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,609
Location
Hampshire
The bridge modification works to enable electrification had been applied for under listed building consent application 16/10069/LBC. The application includes various drawings of the proposed works.

Speaking of the bridge, here is a photo I took yesterday. I believe it isn't finished yet as the floor is made of wood with an anti slip surface.
 

Attachments

  • IMG_6454.jpg
    IMG_6454.jpg
    146.4 KB · Views: 172

Unclepete

Member
Joined
18 Oct 2011
Messages
76
Location
Newbury
Never.

The Hayes services will remain as Hayes services until they're withdrawn and replaced with Crossrail 4tph to Heathrow (along with Connect)

Peak only running to and from Maidenhead is due to commence in May, subject to all station compatibility testing and verification being completed. The former Bourne End through services (that now terminate at Maidenhead) and a very small handful of stoppers which also start/terminate Maidenhead are the services you're looking for.

I maybe taking a very simplistic view here, but surely if the wires are not energised as far as Reading before December, then why would you want to introduce the IEP's before then? You would want to run on electric to Reading wouldn't you?
 

MarlowDonkey

Established Member
Joined
4 Apr 2013
Messages
1,824
then why would you want to introduce the IEP's before then?


Wouldn't a Maidenhead service use the same type of electric train (387?) as currently used on the Hayes shuttle? These are replacing in part the 165s and 166s used at present. IEPs are replacing the Inter City 125s.
 

Unclepete

Member
Joined
18 Oct 2011
Messages
76
Location
Newbury
Wouldn't a Maidenhead service use the same type of electric train (387?) as currently used on the Hayes shuttle? These are replacing in part the 165s and 166s used at present. IEPs are replacing the Inter City 125s.

Sorry, I was making a more general point about the timing of the IEP introduction.
As I understand it, they were expected to start in July, but due to various issues, we all know about, the latest date mentioned is October.

Will Maidenhead-Reading be switched on by October? If not, why would you introduce them?
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,455
Location
Preston Lancs
Also please please someone post some photos or other good news so we can get back on topic and see some real progress.
 
Last edited:

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,271
Location
Churn (closed)
I maybe taking a very simplistic view here, but surely if the wires are not energised as far as Reading before December, then why would you want to introduce the IEP's before then? You would want to run on electric to Reading wouldn't you?

Because the class 180's go off hire in December 2017 and many HSTs have to be handed back for ScotRail in the autumn too.

The IEPs will just have to get by until each section gets switched on.

Paddington - West Drayton / Tilehurst to Didcot are ON.

West Drayton - Maidenhead should go live in February 2017

Maidenhead - Twyford / Reading Station look good for the early summer.

We can hope for the Sonning gap & west of Didcot, but Steventon is way behind
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
However, the last post to that thread was in June last year, whereas the much more recent #4329 in this thread is relevant:
Just because a thread is old does not prevent it being bumped. We agreed to keep it separate as it was very much in the political sphere. NR will not do anything it doesn't want to, and it doesn't have to do (as it has placed many caveats). We have enough airy fairy stuff on this thread already. I just wish we could discuss the same material as is done on the Ordsall Chord and Other Northern electrification threads.
 

Unclepete

Member
Joined
18 Oct 2011
Messages
76
Location
Newbury
Because the class 180's go off hire in December 2017 and many HSTs have to be handed back for ScotRail in the autumn too.

The IEPs will just have to get by until each section gets switched on.

Paddington - West Drayton / Tilehurst to Didcot are ON.

West Drayton - Maidenhead should go live in February 2017

Maidenhead - Twyford / Reading Station look good for the early summer.

We can hope for the Sonning gap & west of Didcot, but Steventon is way behind

ok, thanks I understand a little better now the reasons.
So, if we have live wires to Maidenhead, are non stopping services going to change power source at line speed?
 

MarlowDonkey

Established Member
Joined
4 Apr 2013
Messages
1,824
So, if we have live wires to Maidenhead, are non stopping services going to change power source at line speed?

I believe it has been announced that the IEPs can do this. I don't think there are any immediate plans to bring them into service. Otherwise the GWR units are electric only.
 

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,218
We now have electric services from Paddington to Hayes. They were described as taking the paths of the Greenford trains, which are now connections cut back to a bay at West Ealing.

Looking at the current timetable, this seems to have been taken literally. Throughout the morning these services arrive at West Ealing at 27 and 57 minutes past the hour. And the trains to Greenford, from over the footbridge, depart at ... 27 and 57 minutes past the hour. So no connection. And indeed, the timetable shows you now need to go on the previous stopping service to get the branch train.

I don't remember it being said that such an extraordinary attitude to the onetime through passengers was ever contemplated.
 
Last edited:

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,589
Location
Nottingham
We now have electric services from Paddington to Hayes. They were described as taking the paths of the Greenford trains, which are now connections cut back to a bay at West Ealing.

Looking at the current timetable, this seems to have been taken literally. Throughout the morning these services arrive at West Ealing at 27 and 57 minutes past the hour. And the trains to Greenford, from over the footbridge, depart at ... 27 and 57 minutes past the hour. So no connection. And indeed, the timetable shows you now need to go on the previous stopping service to get the branch train.

I don't remember it being said that such an extraordinary attitude to the onetime through passengers was ever contemplated.

That's plain daft. Isn't the Greenford branch now fully self-contained? If so the whole timetable could be pushed round the clock by a few minutes to give a decent connection.
 

D1009

Established Member
Joined
22 Feb 2012
Messages
3,166
Location
Stoke Gifford
Because the class 180's go off hire in December 2017 and many HSTs have to be handed back for ScotRail in the autumn too.

The IEPs will just have to get by until each section gets switched on.

Paddington - West Drayton / Tilehurst to Didcot are ON.

West Drayton - Maidenhead should go live in February 2017

Maidenhead - Twyford / Reading Station look good for the early summer.

We can hope for the Sonning gap & west of Didcot, but Steventon is way behind
Does that mean say by Dec 18 we are likely to complete the wiring to Thingley Junction leaving a short gap at Steventon?
 

Ianno87

Veteran Member
Joined
3 May 2015
Messages
15,214
That's plain daft. Isn't the Greenford branch now fully self-contained? If so the whole timetable could be pushed round the clock by a few minutes to give a decent connection.

There a a few freight paths through the day that run between the Reliefs and the Greenford branch, which have to be pathed between the passenger trains. The longish headway on the Greenford branch means that the passenger paths have to coincide at the same time on Relief and branch to get a 'through' freight path. The tight running time of the single unit means that you can't adjust the time for a particular hour to fit a freight as there isn't enough flex at either end - the only other way would be to miss a trip while the freight runs through.
 

Envoy

Established Member
Joined
29 Aug 2014
Messages
3,126
I thought that they were going to put in extra tracks to make Didcot to Swindon 4 tracks? If that is so, why have they only put up headspans for the 2 present tracks only?
 

Domh245

Established Member
Joined
6 Apr 2013
Messages
8,426
Location
nowhere
I am not aware of the style of supports used on that section (but they almost certainly aren't headspans!) - but it is possible that should they 4 track it, they'll go with the seemingly preferred style of 2 twin track cantilevers, assuming that they lay an additional pair of tracks adjacent to it, rather than one new track on either side.
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
There a a few freight paths through the day that run between the Reliefs and the Greenford branch, which have to be pathed between the passenger trains. The longish headway on the Greenford branch means that the passenger paths have to coincide at the same time on Relief and branch to get a 'through' freight path. The tight running time of the single unit means that you can't adjust the time for a particular hour to fit a freight as there isn't enough flex at either end - the only other way would be to miss a trip while the freight runs through.

Or insert some intermediate block signals.
 

ainsworth74

Forum Staff
Staff Member
Global Moderator
Joined
16 Nov 2009
Messages
31,067
Location
Redcar
I dunno what it is about the Goring Gap that gets people so worked up but can we please please use the Goring Gap thread for discussions about it? I've had to move 25 posts out of this thread to get us back on track and ensure that we can see the wires for the masts in this thread!

Many thanks :)
 

Wilts Wanderer

Established Member
Joined
21 Nov 2016
Messages
3,199
We now have electric services from Paddington to Hayes. They were described as taking the paths of the Greenford trains, which are now connections cut back to a bay at West Ealing.

Looking at the current timetable, this seems to have been taken literally. Throughout the morning these services arrive at West Ealing at 27 and 57 minutes past the hour. And the trains to Greenford, from over the footbridge, depart at ... 27 and 57 minutes past the hour. So no connection. And indeed, the timetable shows you now need to go on the previous stopping service to get the branch train.

I don't remember it being said that such an extraordinary attitude to the onetime through passengers was ever contemplated.

What complete and utter rubbish.

The actual arrangement is that a 3-min connection is provided from Greenford into the Hayes-Paddington EMU until about 1300hrs, after which time the branch timetable rotates slightly and provides a 3-min connection towards Greenford out of the Paddington-Hayes EMU until the end of play. Note it is not physically possible to provide the connection both ways, and the EMU paths are fixed by the available slots in/out of London Paddington.
That's the theory anyway. The reality is that some consecutive branch circuits are flexed for freight trains. The tight turnarounds (3/4 mins) at each end mean it takes a few circuits to recover the pattern if one is retimed. It's a known issue and various parties are working to improve the plan. 'Awful planning' it is not!
(If you want to see the ideal pattern look at the Saturday timetable on a date when there isn't engineering work, or in the pocket TT which shows the unamended base timetable.)
 
Last edited: