My suggestion was thwarted by the fact that the "get-you-home" engines are not powerful enough to run to unwired parts such as Carmarthen and Weston super Mare at a reasonable speed and up Filton Bank.
I can't believe that the get-me-out-of-here diesels are unable to get the train out of the Severn Tunnel at a reasonable speed if the electricity fails inside there. Surely that's one place where it would be needed pronto.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
I can't believe that the get-me-out-of-here diesels are unable to get the train out of the Severn Tunnel at a reasonable speed if the electricity fails inside there. Surely that's one place where it would be needed pronto.

See bold double negative. Is that what you meant? I have an idea you meant the opposite.
 
Last edited:

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,898
Location
North
I think what he really meant was "bring back British Rail exactly as it was, including Deltic 8".

I wish I could go back to the days of Deltics. In 1982 I was briefly the owner of 55008 but due to circumstances beyond my control I had to cancel the sale. Nowadays I would have done things differently. I offered Porterbrook a six figure sum for purple 55018 when that came up for sale but somehow the owning group came up with the money to buy it back.

Watching the railway scene then was much more exciting than the boring stock we see now.

Standing at Pilmoor and listening to Deltics thrash up and down the ECML was amazing. Haven't been to watch trains at Pilmoor since the withdrawal of 47s on Cross Country.
--- old post above --- --- new post below ---
See bold double negative. Is that what you meant? I have an idea you meant the opposite.

Not so sure this is a double negative. He can't believe that 800s are unable to get home on diesel.
 
Last edited by a moderator:

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
See bold double negative. Is that what you meant? I have an idea you meant the opposite.
My take on his post is that he meant it the way he wrote it. "Surely the designers haven't botched it so badly that they can't get a failed train out of the Severn Tunnel?"
 

gsnedders

Established Member
Joined
6 Sep 2015
Messages
1,472
I thought the Class 801's diesel engine was easily capable of climbing steep grades—just, it'll do it much like a Class 08 would: it'll get over anything, eventually.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,898
Location
Mold, Clwyd
Does the Severn tunnel have the option to power either track from either end of the tunnel?

I think I've seen somewhere that the tunnel will be powered from the Newport end normally, but is capable of being fed from the Thingley end if needed.
The tunnel is also bi-di signalled.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,229
I can't believe that the get-me-out-of-here diesels are unable to get the train out of the Severn Tunnel at a reasonable speed if the electricity fails inside there. Surely that's one place where it would be needed pronto.

None of the GWR trains will have just the 'get you home diesels' as they are all bi-modes. Am I missing something in this recent discussion?
 

JamesT

Established Member
Joined
25 Feb 2015
Messages
4,827
None of the GWR trains will have just the 'get you home diesels' as they are all bi-modes. Am I missing something in this recent discussion?

They are all currently specified for bi-mode, however at least originally some were specified as the 'electric only' type, and presumably if/when the electrification gets finished they'll remove the extra engines to go back to just electric.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
None of the GWR trains will have just the 'get you home diesels' as they are all bi-modes. Am I missing something in this recent discussion?

Yes, it was about Deltic08's suggestion that the IEPs now being ordered as bi-modes needn't have been, if his suggestion that the GWR all electric with get you home diesel had gone to VTEC instead. It was way back in the thread now.
 

leomartin125

Member
Joined
15 Nov 2015
Messages
1,058
Location
North West
Yes, it was about Deltic08's suggestion that the IEPs now being ordered as bi-modes needn't have been, if his suggestion that the GWR all electric with get you home diesel had gone to VTEC instead. It was way back in the thread now.

I can vouch for that. Although none of the trains produced by Hitachi's are 801's yet, even Virgin's 9 car set is a Class 800 (800101). The first GWR 9 car set was also a Class 800 (800301) but this set I believe was transferred to Virgin EC when the announcement came that GWR would be needing more diesel IEP's. This I cannot understand, as 800301 was already a Class 800, so had no reason to change ownership...

Can anyone elighten me here?
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,898
Location
North
They are all currently specified for bi-mode, however at least originally some were specified as the 'electric only' type, and presumably if/when the electrification gets finished they'll remove the extra engines to go back to just electric.

Unnecessary expense in the first place had HSTs been retained for a little longer on London-Bristol/Swansea and displaced from both Cotswold and West Country routes earlier for cascade to Scotrail.
 

Clarence Yard

Established Member
Joined
18 Dec 2014
Messages
3,262
Unnecessary expense in the first place had HSTs been retained for a little longer on London-Bristol/Swansea and displaced from both Cotswold and West Country routes earlier for cascade to Scotrail.

Was never going to happen. Agility units use specified depots - Laira and Long Rock are not in the TARA so the units have to revolve around North Pole, Stoke Gifford and Maliphant. That restricts the services they can run on and each of the IEP depots have a mandatory maintenance plan which the TOC has to adhere to.

The IEP units run at a lower power rating than the 802 sets and until the bi-modalisation was authorised were still on the 700 mile limit for fuel with the smaller tanks. That means they couldn't knock out an HST on a "one for one" long train basis on the West Country services, even if they could've met the times in muzzled mode.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
Thanks Clarence_Yard*
TBH, if I were GWR TOC management, I would be breathing a sigh of relief at the delay, that has brought about the all-bi-mode policy. Having genuine bi-modes instead of get-you-home will enable a load of possible electrification teething problems to be overcome with much fewer delays. From a customer relations standpoint, they don't care what powers the train, as I opined earlier in the thread.

*there's one in Southend and one in Gosport. I am intrigued which is yours. :)
 

Clarence Yard

Established Member
Joined
18 Dec 2014
Messages
3,262
Thanks Clarence_Yard*
TBH, if I were GWR TOC management, I would be breathing a sigh of relief at the delay, that has brought about the all-bi-mode policy. Having genuine bi-modes instead of get-you-home will enable a load of possible electrification teething problems to be overcome with much fewer delays. From a customer relations standpoint, they don't care what powers the train, as I opined earlier in the thread.

*there's one in Southend and one in Gosport. I am intrigued which is yours. :)

North London. Just south of Finsbury Park on the downside - now a housing estate.
 

Mintona

Established Member
Joined
8 Jan 2006
Messages
3,592
Location
South West
When I last counted a few weeks ago there were 35 masts erected in the Marshfield area between Newport and Cardiff. Today there were 71. Impressive progress there!
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,898
Location
North
When I last counted a few weeks ago there were 35 masts erected in the Marshfield area between Newport and Cardiff. Today there were 71. Impressive progress there!

Less than impressive. Works out about 5 per night. Pathetic. I thought the schedule was one completed wire length per night.
 

Mintona

Established Member
Joined
8 Jan 2006
Messages
3,592
Location
South West
Less than impressive. Works out about 5 per night. Pathetic. I thought the schedule was one completed wire length per night.

It's pretty impressive. The lines here aren't being worked on every night, they're being done every couple of weeks. There's still a fair amount of piling and groundworks being done at the same time. This section is a few years off completion so I'd say they're doing pretty well to get ahead and get on with it.
 

steverailer

Member
Joined
15 Feb 2013
Messages
169
Less than impressive. Works out about 5 per night. Pathetic. I thought the schedule was one completed wire length per night.

Thats not the schedule, thats what they said the HOPS could do every night !!!! A complete wire rune needs around 20 masts per side of track. Add in that the brackets for the booms will be installed as they put the masts in and any struts installed or laid out too and you're around the 5 mark per shift.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
A couple of press releases:

http://www.networkrailmediacentre.c...e-reopens-on-time-following-extensive-upgrade

Bridge Street Road Bridge, an iconic bridge connecting Newport to its city centre has reopened to motorists today (from 12noon Thursday 1 December) following essential upgrade work.

The 105 year-old road bridge was closed in May 2016 while it was completely reconstructed to prepare it for electrification as part of Network Rail’s Railway Upgrade Plan to provide a bigger, better, more reliable railway for passengers.

The original bridge was demolished in July and the new and improved structure was installed to accommodate the overhead line equipment required to power the new fleet electric trains.

The new bridge is able to accommodate heavier vehicles, to ensure it is fit for modern day city centre traffic and also has a wider footpath for pedestrians and improved road alignment for better accessibility.

http://www.networkrailmediacentre.c...n-as-railway-upgrade-in-south-wales-continues

A new platform at Cardiff Central station designed to help ease congestion will be unveiled in the New Year-all part of Network Rail’s Railway Upgrade Plan.

The brand new platform 8 is located above the modern south-side entrance building at the station and will officially come into use on Tuesday, 3 January 2017 to passengers travelling on the Penarth, Barry Island and Vale of Glamorgan lines. It is all part of the £300m Cardiff area signalling renewals project to modernise the Cardiff and Valleys network. The works are the largest signalling project of its kind to be commissioned on the rail network and will be completed over the festive period.

The track for Platform 8 was installed this year and together with the new signalling system, as well as being bi-directional, it will enable trains to depart westwards from Platforms 7 and 8 simultaneously, improving the operational capacity of the line.

The project also includes upgrading track and signalling on the railway in and around Cardiff Central station, which will help to improve the reliability of the rail services in the area.
 

jimm

Established Member
Joined
6 Apr 2012
Messages
5,274
And in a further attempt to get this thread back on track, ie to talk about the actual electrification project rather than yet another circular discussion about bi-modes, a lot of the small steelwork is now in place on the portals through Reading station and a few randomly-located registration arms have also been fitted.
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,609
Location
Hampshire
And in a further attempt to get this thread back on track, ie to talk about the actual electrification project rather than yet another circular discussion about bi-modes, a lot of the small steelwork is now in place on the portals through Reading station and a few randomly-located registration arms have also been fitted.

Which reminds me...
 

Attachments

  • IMG_1341.jpg
    IMG_1341.jpg
    117.4 KB · Views: 138

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,609
Location
Hampshire
Mostly through platforms 11 & 12 at the moment, with some small steelwork appearing around the curve to Reading West and up and onto the Viaduct.
 