Hi guys,
I've just seen this on the BBC site: http://www.bbc.co.uk/news/uk-england-oxfordshire-37908735
"BBC transport correspondent Richard Westcott said: "[Network Rail] pinned their hopes on a new, multi-million pound factory train that digs the holes, puts up overhead wire supports, fills the holes with concrete and hangs the wires.
It was meant to put in 120 piles a week, but for a long time, I'm told, only managed about 30."
Any idea what this 'factory train' thing is? I'd like to know more about it and its failings...
Here goes with a quick description and link...
The High Output Plant system
The HOPS will leave the purpose-built depot in Swindon and split up, to head to different parts of the line at its 60mph top speed. It carries enough supplies and equipment to avoid the need to bring anything to the trackside on lorries. Staff can be picked up at stations en-route.
The different elements to the HOPS train are:
A piling rig (with two multi purpose vehicles with Movax vibro piling heads, to vibrate the steel piles into the soil, two pile carrying wagons, and a Fambo hydraulic percussion hammer multi purpose vehicles for tougher ground)
An excavation and concrete batching unit with an Hitachi excavator plus a Kniele concrete unit to mix concrete from onboard aggregate, cement and water tanks
A structures unit which erects the masts, portal booms and twin track cantilevers
An ancillary conductor to install the earthing wires, return wires and small parts such as registration arms and other equipment
The contact and catenary unit to string up the remaining wires under tension. Another unit installs other things such as contenary wires under low bridges, and records information such as height and stagger
Each of the above elements includes two multi purpose vehicles with full driving cabs, powered by MTU power packs, which can be driven at 60mph off-site. On site driving cabs means the train can be driven very slowly when installing contact wire.
http://www.networkrail.co.uk/news/2...-slashes-years-off-electrification-programme/
Best to search this thread for the term "HOPS" - High Output (electrification) Plant System. It's lack of performance compared to spec has been discussed quite a few times since 2013...