I did a return trip from London to Cardiff yesterday and I was surprised at the progress made since I last did this trip about four months ago, all the below is looking at the north side of the tracks.
From Airport Junction to just east of Maidenhead a lot of steelwork has gone up recently, I would 50% of the masts are up with many support arms fitted
too, dare I say that we may see some wiring in this area before Easter next year?
From Maidenhead to just east of Reading, little progress, piling about 50% done at best, no steelwork and nothing done at all in the Sonning cutting, maybe a scrap or two at best.
From Reading to the new feeder station just west of Didcot I would say that 90-95% of the masts are up, the most westerly one is just west of the feeder station and of coarse there is the wiring installed in the Pangbourne area, it is basically one run out which is about 1/2 to 3/4 of a mile and it looks the completed article, I think it is only installed on the relief lines as the up fast did not like it had anything but it was hard to see at 125 MPH!
From Didcot to about half way towards Swindon where the four track section ends piling is up to about 80-85% complete, after that only a few installed here and there.
There are about a dozen piles installed just east of Wootton Bassett Junction, lots of new signals around this area awaiting to be commissioned, will the 70 MPH turn off to the South Wales main line be upgraded?
Just past Wootton Bassett junction there is the M4 bridge about five miles past here there are the first piles installed on this section, about four I seem to recall.
The new train depot at Stoke Gifford, just west of Bristol Parkway, is now all wired up.
In the Pilning area between the two single bore tunnels and the Seven Tunnel, piling is about 80-85% done and in the Llanwern area I counted about 40 piles now installed with quiet a few scraps. When they start piling towards Newport there are houses that back onto the railway. so a few sleepless nights awaiting the locals.
This time next year all hell will be just about to start in the Cardiff Station area with the next part of the Cardiff resignalling scheme, this is a big job and will involve a complete shut down between Christmas and New Year I guess.
On the way back I saw a Class 800/801 in the North Pole train shed, well this will not be going very far at the moment on electric power on the GWR!
So good progress I feel, lets hope for a lot more of it in 2016.