Great Western Electrification Progress

Status
Not open for further replies.

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,898
Location
Mold, Clwyd
I think you could be wrong there Phil? Looks like earth wire to me as its sliver colour and under the boom, although don't know why its going into a insulator?

The NR press item says it is indeed an earth wire.
http://www.networkrailmediacentre.c...ication-wiring-on-the-great-western-main-line
Last night, Thursday 12 November, Network Rail engineers installed the first overhead wires for the electrification of the Great Western Main Line.
One mile, or 1.6km, of earth wire was installed on the lines west of Reading between Pangbourne and Tilehurst, part of the track that will serve as a test section for the new Class 800 Intercity Express trains.
This is the first section of the new-design overhead line to be erected on the operational railway, and the first overhead line anywhere on the route beyond the existing wires at Airport Junction in Stockley, London. The first 1,000 metres were installed in only 35 minutes
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,229
I think you could be wrong there Phil? Looks like earth wire to me as its sliver colour and under the boom, although don't know why its going into a insulator?

Isn't it on insulators because on an ATF system it has a slightly different purpose, therefore it isn't fitted the same way as a conventional earth return conductor? Hopefully someone will know the exact reason.
 

steverailer

Member
Joined
15 Feb 2013
Messages
169
Isn't it on insulators because on an ATF system it has a slightly different purpose, therefore it isn't fitted the same way as a conventional earth return conductor? Hopefully someone will know the exact reason.

All the ones I've installed the earth is direct to steel, no insulator at all. Thats in NW and WCML. Undertand series one is the same
 

Philip Phlopp

Established Member
Joined
31 May 2015
Messages
3,003
I think you could be wrong there Phil? Looks like earth wire to me as its sliver colour and under the boom, although don't know why its going into a insulator?

Yeah, earth wire as per PR release. I was going to go back and fix my post but got sidetracked trying to find out who's doing the Maidenhead to Reading (and slightly beyond) wiring.
 
Last edited:

steverailer

Member
Joined
15 Feb 2013
Messages
169
Yeah, earth wire as per PR release. I was going to go back and fix my post but got sidetracked trying to find out who's doing the Maidenhead to Reading (and slightly beyond) wiring.

Believe its Amey, being installed coventionally by SRS Rail is the rummour I have heard, just waiting for piling to get far enough infront so my contacts say
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,898
Location
Mold, Clwyd
Believe its Amey, being installed coventionally by SRS Rail is the rummour I have heard, just waiting for piling to get far enough infront so my contacts say

It says Keltbray on the RRV in the pic.
They pop up everywhere (Norton Bridge for instance, which has significant wiring work).
 

steverailer

Member
Joined
15 Feb 2013
Messages
169
It says Keltbray on the RRV in the pic.
They pop up everywhere (Norton Bridge for instance, which has significant wiring work).

From what I understand Keltbray are doing Tilehurst to Pangbourne, SRS Pangbourne to Didcot and Maidenhead to Reading.

My comment was in reply to Phillip asking about the Maidenhead to Reading section, not the picture. And yes they do get everywhere, but don't have the best reputation they were on the WCML PSU work until ABC took over as it was 12 months behind
 
Last edited:

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,897
How about livening it up to stop the scroats nicking it?

A scroat was once fried trying to nick the OHLE from the disused Godley sidings on the Woodhead route.

At his inquest the coroner asked why the wires were still alive if the sidings were out of use. The railway witness said truthfully "to deter thieves".

The coroner said (words to the effect), "what a good idea".

Imagine that in today's compensation culture world.
 

Tw99

Member
Joined
25 Aug 2015
Messages
227
Location
Reading
I'll have to go for a walk tomorrow and do some wire-spotting. This must be within a mile of my house.
 

Envoy

Established Member
Joined
29 Aug 2014
Messages
3,126
Deleted - loaded to wrong forum.
 
Last edited:

sprinterguy

Veteran Member
Joined
4 Mar 2010
Messages
11,565
Location
Macclesfield
When HS 2 is built, are we going to have larger trains that would not be able to 'fit' on the north Wales Main Line in any case - thus requiring a change of trains at Crewe? Alternatively, would they build a fleet to smaller dimensions for travelling off the new HS 2 route?
Getting a fair way off topic from GWML electrification here (Was this post intended for this thead here? http://www.railforums.co.uk/showthread.php?t=123233), but the HS2 train fleet will comprise both "captive" trainsets that take advantage of the larger loading gauge, and "classic compatible" sets that will be able to continue their journeys on the existing network.
 
Last edited:

Tw99

Member
Joined
25 Aug 2015
Messages
227
Location
Reading
I went out and had a look at this first stretch of wiring this morning. They seem to have done a bit more since that tweet, as there's three wires up in the area I was looking at. It's located a few hundred metres west of the Westbury Lane bridge at Purley on Thames, so between there and Pangbourne.

There are quite a few different types of portal with different equipment attached, not all of which I understand, so perhaps someone can fill in the details.

This is one of the braced portals with the tensioning spools on it:

DPP_4783.JPG


Quite a lot of the portals are like this, with pairs of cantilevered booms, one set on each side, so eight in total.

DPP_4784.JPG

DPP_4785.JPG


Others just have a single set of booms:

DPP_4786.JPG


And then there's this odd one that has no cantilevers, but just individual poles above each track. It's braced, too.

DPP_4788.JPG
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,229
There are quite a few different types of portal with different equipment attached, not all of which I understand, so perhaps someone can fill in the details.

They'll have two complete sets of insulators and registration arms (hence 8 sets per gantry) during the overlap between adjacent wiring runs, where there is a distance with 8 catenaries and 8 contact wires..

Not sure about the design distance between the sets of tensioning gear and line terminating equipment, but they'll be a few hundred yards apart so the doubling up will include a few successive gantries.

The wires shown in your pictures are the catenary wires that run above the insulated arm, the contact wires will be vertically below them attached by the droppers and laterally restrained by the registration arms. The registration arms are visible but tied up, and there are a few droppers shown, the small coils clipped to the catenary here and there.

I'd recommend the series of photos lower down on this web page that show the various components in their eventual positions: http://www.furrerfrey.ch/en/systems/Series-1.html
The second image shows a two track cantilever and probably explains what you are looking at - you just have to imagine it doubled up for a four track gantry and then doubled again for the wiring run overlap.

Hope that helps.
 
Last edited:

Philip Phlopp

Established Member
Joined
31 May 2015
Messages
3,003
Not sure about the design distance between the sets of tensioning equipment, but they'll be a few hundred yards apart so the doubling up will include a few successive gantries..

The system is designed for a single span overlap, to avoid too many portals and doubled up catenary elements. Operation requirements will require changes in places.

The curious looking gantry is for sectioning and feeding arrangements.
 

steverailer

Member
Joined
15 Feb 2013
Messages
169
The system is designed for a single span overlap, to avoid too many portals and doubled up catenary elements. Operation requirements will require changes in places.

The curious looking gantry is for sectioning and feeding arrangements.

Think the majority of the line from Tilehurst to Didcot has 3 span overlaps Phillip, i.e 2 portals in between the sets of tensorex ones.

The last picture is the mid-point anchor portal, its missing the registration arms on the insulators below the boom
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,229
Think the majority of the line from Tilehurst to Didcot has 3 span overlaps Phillip, i.e 2 portals in between the sets of tensorex ones.

I was wondering if the tensorex units are fitted at both ends of each wire run? I'm assuming that at both ends would be the best way of doing it - so that the mid point of a wire run didn't move much - but it would be interesting to know for certain.
 

steverailer

Member
Joined
15 Feb 2013
Messages
169
I was wondering if the tensorex units are fitted at both ends of each wire run? I'm assuming that at both ends would be the best way of doing it - so that the mid point of a wire run didn't move much - but it would be interesting to know for certain.

Yes there is a set at each end of a run, the caterary is fixed at the mid point and 'z' droppers used to fix the Contact (a length of catenary wire fastened near the mid point connection at the catenary then tensioned down to the contact roughly 20m away) The fixing at the mid point stops the 2 sets of tensorex fighting against each other, one with more and one with less ect, same as on a balance weight set up

There will only be one set on a cross over or short run such as a sidings ect
 
Last edited:

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,229
Yes there is a set at each end of a run, the caterary is fixed at the mid point and 'z' droppers used to fix the Contact (a length of catenary wire fastened near the mid point connection at the catenary then tensioned down to the contact roughly 20m away) The fixing at the mid point stops the 2 sets of tensorex fighting against each other, one with more and one with less ect, same as on a balance weight set up

There will only be one set on a cross over or short run such as a sidings ect

Thanks for the info, I should nearly be in a position to put my own system up... :D
 

Philip Phlopp

Established Member
Joined
31 May 2015
Messages
3,003
Think the majority of the line from Tilehurst to Didcot has 3 span overlaps Phillip, i.e 2 portals in between the sets of tensorex ones.

The last picture is the mid-point anchor portal, its missing the registration arms on the insulators below the boom

It's being done with 3 span overlaps through Berkshire too, but that really isn't what was intended, not that it makes any difference.

Yeah, had a proper look at the bottom picture (first one I've had a proper look at in-situ) and as you say, it's missing the cantilevers and from what I can see, it's got the wire mounting insulators pointing in the wrong direction for the wire runs at the moment, but that will just be to keep them out of the way for now.
 

Mintona

Established Member
Joined
8 Jan 2006
Messages
3,592
Location
South West
In a different area, piling appears to be nearly finished between Pilning station and Patchway tunnel, and is now starting to appear the other side of Pilning down towards the Severn Tunnel. There are also far more piles around Llanwern West than previously too, almost extending to Bishton crossing alongside the up main. Seem to be getting on with it down that way fairly quickly now.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
In a different area, piling appears to be nearly finished between Pilning station and Patchway tunnel, and is now starting to appear the other side of Pilning down towards the Severn Tunnel. There are also far more piles around Llanwern West than previously too, almost extending to Bishton crossing alongside the up main. Seem to be getting on with it down that way fairly quickly now.

Does Bristol box control Pilning? If so, I assume that the location of cabling is not as mysterious as @Philip Phlopp fears, in another post of his.

Is there a date for when Bristol box is to be removed? I shall rejoice when that happens and the old station is available for update.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,898
Location
Mold, Clwyd
Does Bristol box control Pilning? If so, I assume that the location of cabling is not as mysterious as @Philip Phlopp fears, in another post of his.
Is there a date for when Bristol box is to be removed? I shall rejoice when that happens and the old station is available for update.

No to the former, the line from Patchway westwards was resignalled relatively recently into South Wales CC at Cardiff, and the line is now formally part of NR's Wales Route.
It's also why NR has started piling work along this stretch - they know where the cables are.

On the latter - dunno.
The Badminton-Patchway section is being resignalled now, but I don't think anywhere else is very advanced.
 

Tw99

Member
Joined
25 Aug 2015
Messages
227
Location
Reading
The contact wire is now installed over the up relief line on that same short section.
 