I did another turn between Oxford and Paddington today to view electrification progress (ignoring the Reading station area).
West of Maidenhead (Amey):
Between Tilehurst and Moreton Cutting there are now 77 masts on the south side and 91 on the north - if I've counted right. An average of 84 structures.
I make that 28% complete - still no portals up, or wires of course.
Most of the remainder of the route is piled, but there are still many gaps, with piles lying around waiting to be driven.
Reading-Maidenhead: some marker pegs for eventual bases, and a few piles lying in the cess around Ruscombe on the south side.
Didcot-Oxford: a few piled bases on the curves northward (via the station and also on the avoiding line), but once past Appleford there's nothing except the odd yellow marker peg for eventual bases.
Progress in the 16 weeks since my last trip on July 7, when I recorded 41 structures, has been modest.
Maybe masts are multiplying west of Didcot and towards Newbury, which I didn't see.
Masts do extend round the Reading triangle, but I don't know how far they go.
On the Crossrail contract section (Balfour Beatty):
Between Maidenhead and east of Burnham (alongside the Slough Industrial Estate), there are plenty of piled bases but no masts yet.
Apart from a few bases around Iver there is no evidence of progress east of Burnham.
Plenty of work on the existing electrified route is in progress at Airport Jn (new flyover), Acton (underpass) and at Kensal Green (where the North Pole depot connection to the main line is now partially in place).
Most of these new routes already have masts up with some wiring in place.