I believe the GOB / ECML link at Haringay is commissioned over Christmas.
I believe the GOB / ECML link at Haringay is commissioned over Christmas.
Based on an informed comment in "another place" it seems Gospel Oak to South Tottenham will be energised from 10 December. South Tottenham to Woodgrange Park to be energised from 17 December. Decent progress there with the wiring train and connections into the relevant power feeds. I assume various forms of testing will follow in the period up to reopening in mid January.
I believe the GOB / ECML link at Haringay is commissioned over Christmas.
The line has been open for the last few days in order to provide a diversionary route for freight during the current NLL closure at Highbury.
Slightly off topic but a warning for customers who are diverted via the North London line, that Camden Town will be exit only during the evening peak and most of the afternoon on Weekends from Tuesday (as well as during Night Tube).
Not ideal given that so many Goblin customers are being diverted via the North London line and Northern line changing at Camden Road/Camden Town.
They haven’t even applied for the necessary permissions to do the work let alone even start constructions. All escalators are closed every now and again for works.A shame this work couldn't wait until the new station entrance has been built, I guess they couldn't wait that long
Are there that many Goblin passengers changing at Camden Town? It is only really Upper Holloway where the Northern line is a realistic alternative.
I believe the first one arrives in the early summer. I imagine they will be tested on Watford DC and West Anglia lines if the GOB wiring is not ready.
Yes, it was always the plan to have 172s under the wires for the interim - although I'm pretty sure they're now earmarked for WMR?So will it go back to being diesel 172s under the active wires? Could anything else (maybe any spare 319s from up north?) operate in the interim?
I wouldn't hold your breath waiting for the 710/2s into service ...not if these Aventras have the same level of issues that the 345s have had. It should be hoped that lessons have been learned...but then this a different production line of a different length unit.I thought the new trains were entering service in the spring.
Yes, TfL repeatedly stated (both in board papers that are available on their website, and in Mayoral Q&A responses), that it was not cost effective to train either crew or maintainers on a different fleet for such a short term period.IIRC other electric stock (319 etc) were not taken up since to a need to train drivers on short term stock wasn't considered viable (open to corrections on this).
London Overground’s Gospel Oak to Barking line reopens on Monday 15 January following the installation of new overhead electric lines by Network Rail, that will enable new longer electric trains to run from spring 2018.
- Gospel Oak to Barking line to fully re-open on Monday 15 January
- The new electrified line will be fully tested ahead of new state-of -the-art trains being introduced in spring 2018
The completion of this physical work by Network Rail will now be followed by testing that will, from spring, enable Transport for London (TfL) to run new state-of-the-art electric trains, providing customers with increased capacity and feature walk-through carriages, air conditioning, live network information screens and improved reliability. The new cleaner electric trains will also improve air quality for people living and working along the route.
When services resume next week the existing two car diesel trains will be used until the new four car electric trains have been fully tested and driver training complete.
Customers will again see services running every 15 minutes throughout the day until late evening and at least every 20 minutes after 22:00. Connecting Gospel Oak station in north London with Barking in east London, the re-opened line will again provide convenient interchanges with the Victoria line at Blackhorse Road and Hammersmith & City, District line and c2c services at Barking.
The electrification work on the Gospel Oak to Barking London Overground line is part of TfL’s improvement plans, enabling new longer trains with greater capacity to run from spring 2018, and forms part of Network Rail’s London Railway Upgrade plan, creating new connections and increasing capacity in the peak hour by 30 per cent.
Improvements to the London Overground network are included in the Mayor’s draft Transport Strategy, which aims to create a fairer, greener, healthier and more prosperous city by improving public transport and reducing reliance on car journeys.
Jonathan Fox, TfL’s Director of Rail and Sponsored Services, said: “I welcome the return of services to the Gospel Oak to Barking line and would like to thank customers for their patience while Network Rail completed this stage of the electrification works. A period of testing of the new electrified line will now take place ahead of introducing new, more reliable and longer electric trains in the spring.”
Meliha Duymaz, Network Rail’s route managing director for Anglia, said: “Passengers travelling on the Gospel Oak to Barking line are set to benefit from a transformational, once in a generation upgrade with a new fleet of longer, electric trains so that twice as many people can travel comfortably, once line testing is complete. I’d like to say a big thank you to our railway neighbours and passengers for their enormous patience and understanding while we worked to improve this busy London route.”
Testing of the new electrical infrastructure and the new trains will take place in-between normal services and at night to ensure it does not affect customer journeys.
Network Rail still needs to carry out some improvements to the Crouch Hill Bridge, which crosses the Gospel Oak to Barking line, which means no London Overground services will operate on this line over the weekend of Saturday 7 and Sunday 8 April. Services will restart on Monday 9 April.