Thanks, retracted. Other arguments still stand.That's not true, as bb21 said above - maybe you are thinking of the SVS (Off-Peak Single), to which this applies?
Thanks, retracted. Other arguments still stand.That's not true, as bb21 said above - maybe you are thinking of the SVS (Off-Peak Single), to which this applies?
The Devon Day Ranger indeed offers excellent value. That said, if you only need to make one return journey within the county off-peak, it is effectively capped at the price of the Ranger, leading to some exceptional value fares, such as Gunnislake - Barnstaple, a journey of 105 miles each way, at £9.80.
Bristol TM to Severn Beach is only £3 for >25 mile round trip
A Merseyrail 'nothwirrallines' ticket (could someone who knows the area well confirm?) is only £4.80, Is this valid on all Merseyrail services?
Some people have questioned whether Anytime (Day) SDS/SOR tickets (which the 'Belfast' tickets are listed as) may have BoJ restrictions imposed on them at all, but, all the same, I would not recommend trying it, particularly as it would be a pity if the tickets were withdrawn.
Getting to Devon to use the ticket might not be straightforward at the minute though...
It's shame the sleeper that the sleeper arrival at 0722 doesn't make an official connection with the 0730 departure to Ayr, meaning I had to wait until 1130.
It's not an Advance so there is no reason why you couldnt board the 07:30?
as it seemed better to spend a couple of hours in Glasgow rather than Ayr/Cairnryan.As I understand it a break of journey overnight is accepted on via Cairnryan tickets where the journey can't be completed on the day - otherwise you are being sold a ticket for a journey you cannot complete. Another poster did Belfast - Kyle breaking overnight in Inverness with no issues at all.
Clause 16.2 in NRCOC has been quoted as entirely appropriate here - a break of journey "to stay in overnight accommodation where you cannot reasonably complete your journey in one day
This may well be the agreed practice. The problem is that this is not documented anywhere that I can see so if a member of staff takes exception, you will be royally screwed unless you have an appropriate itinerary to validate your journey
I was very happy with £16 off peak day return Shrewsbury to West Kirby route any permitted.
I don't know the mileage but I went via Crewe and Liverpool. Off peak day return Shrewsbury to Crewe is £13 so hell of a lot if extra mileage for three quid!
I'm fairly sure it would be valid via Wrexham as well.
Is it actually permitted via Runcorn!?
Of course. Shrewsbury-West Kirby costs the same as Shrewsbury-Birkenhead, so that's a valid routeing point.Is it actually permitted via Runcorn!?
I'd say that definitely falls outside the category of 'non-loophole' tickets...I'm not sure I'd have the nerve to try it, but on paper it seems to be perfectly legal, if absurd.
Is there any logic behind it??