Now that a third track has been restored between the approaches to Glasgow Central and Paisley Gilmour Street, how will it work in practice ?

I presume that it will be used for Glasgow bound non-stop services in the morning peak and Paisley bound non-stop services in the evening week.

How will be be used during the rest of the day ? Alternating 15 mins one way then the other ?, mainly for freight ? hardly used much ? or what ? I have no idea.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

CarterUSM

Established Member
Joined
4 Jan 2010
Messages
2,495
Location
North Britain
I don't know, but the remodelling map at my depot states that no ScotRail services will be using the new track until at least 2014.
 

kylemore

Member
Joined
28 Aug 2010
Messages
1,047
I don't know, but the remodelling map at my depot states that no ScotRail services will be using the new track until at least 2014.

!?
It's obviously only 3/4 months from completion and is very much a "headline" project - can you imagine the political outcry and fallout for the SNP and Transport Scotland if it were to be completed and then not used for the best part of two years!
That said, as a regular user of the Ayrshire services I see demand falling particularly at "Full Fare" times.
 

CarterUSM

Established Member
Joined
4 Jan 2010
Messages
2,495
Location
North Britain
On reflection , I may be wrong about the date, i'm sure it is actually 2012, I'll have look during the week though.
 
Joined
23 Dec 2009
Messages
112
Location
Scotland
Even if First ScotRail never used it at all, its still not an embaresment, as the ammount of coal traffic which uses the line would make good use of this, freeing up paths for ScotRail so win-win kind of. Although for the extra cost, 4 tracking the line should have been done, and lack of investment in government projects can sometimes come back to bite. (Newton)
 

Callum

Member
Joined
25 Jan 2010
Messages
31
I think that re-instating four tracks was out of the question due to tighter restrictions on the distance between lines, which is why we now have the three tracks in place.
 