Hi all. I visited Glasgow Central High Level station on Thursday 15th and Saturday 17th April 2010 to capture, with the camera, the trememdous progress that is being made on the construction of the new build platforms 12 and 13. Little to say the least, track is now partially, nearly fully laid to accommodate the two new platforms. A double track stretches off from a set of points and straight through the station's famous arch into the station. Overhead electrification portals and two new signals have been erected of which all await testing. Below are 20 photographs taken over my two visits last week. Full information is also provided below with full captions provided for most images on my website itself of which I hope to have all captions complete over the next day or two (for sure).
Photographs From Thursday 15th April 2010:
Passsengers alight from a service which has came into terminate on platform 15
http://jonathanmcgurk.fotopic.net/p64343136.html
Class 334 012 departs platform 15 en - route to Wemyss Bay (ex 10.50 service). The view shows the tremendous progress being made:
http://jonathanmcgurk.fotopic.net/p64343137.html
Platforms 14 and 15 have been rumoured to be receiving improvements in the near future. New track, overhead electrification equipments and new platform surfaces for each platform are objectives that will be carried out if this has to go ahead in the near future. Class 334 011 and Class 334 017 are seen occupying these two platforms waiting to work their next duties:
http://jonathanmcgurk.fotopic.net/p64343144.html
Photographs Taken From The Station Carpark:
Track is now partially, nearly fully laid with overhead electrification portals erected also:
http://jonathanmcgurk.fotopic.net/p64343138.html
http://jonathanmcgurk.fotopic.net/p64343139.html
This view will change over the next week or so:
http://jonathanmcgurk.fotopic.net/p64343140.html
Looking west:
http://jonathanmcgurk.fotopic.net/p64343141.html
TWO EXCLUSIVE VIEWS - Showing the new build platforms 12 and 13 coming to life. Balfour Beatty workmen at work, bricklaying what will be known as platforms 12 and 13. Track has now partially been laid for the two new platforms and it will not be long before this view changes until all the track is laid and all work is complete. Looking above, you can see the new overhead electrification portals have been erected with wires to be added over the next week or so. If you look closely, you can see where the buffers will be installed at the platform ends. The completion date for the new platforms is Sunday 2nd May 2010 and the official opening date when the platforms will be in full working use is Sunday 9th / Monday 20th May 2010:
http://jonathanmcgurk.fotopic.net/p64343142.html
http://jonathanmcgurk.fotopic.net/p64343142.html
Photographs From Saturday 17th April 2010:
The boarding protecting still platform 11 will soon be removed and the new build platforms 12 and 13 will be unveiled next month. Class 156 503 in Saltire livery is seen sitting inside platform 11 waiting to work the 12.37 service to Paisley Canal:
http://jonathanmcgurk.fotopic.net/p64343145.html
Saltire Reflections - Class 156 503 reflects off the train dispatcher box on platform 11:
http://jonathanmcgurk.fotopic.net/p64343146.html
looking west from the top of platform 11 showing the two new double tracks have been laid to accommodate the new build platforms 12 and 13 at Glasgow Central High Level station. The double track, as you can see, is linked to a set of points before carrying on straight through the station's famous arch and into the station. The rail layer vehicle can be seen ahead, sitting stable awaiting its next track laying duties. Overhead electrification portals have been erected and are awaiting to be connected with associated wires. Two new signals, one for each new platform, 'GG 5612' & 'GG 5613' have also been erected and both await testing:
http://jonathanmcgurk.fotopic.net/p64343147.html
A closer view showing the double track laid just before passing under the station's famous arch:
http://jonathanmcgurk.fotopic.net/p64343148.html
The arch now with double track passing through it to accommodate platforms 12 and 13:
http://jonathanmcgurk.fotopic.net/p64343149.html
http://jonathanmcgurk.fotopic.net/p64343150.html
New controlled signal 'GG 5612' will be the new signal for platform, of which has still to be turned on and tested:
http://jonathanmcgurk.fotopic.net/p64343151.html
http://jonathanmcgurk.fotopic.net/p64343152.html
Looking east into the station from the top of platform 11. The view shows the station's atch with double track running through it, new overhead electrification portals erected and lots of work taking place through the arch itself. A class 334 train set is seen sitting inside platform 14 waiting to work its next duties:
http://jonathanmcgurk.fotopic.net/p64343153.html
http://jonathanmcgurk.fotopic.net/p64343154.html
The points which the double track stretches off to accommodate platforms 12 and 13, looking west:
http://jonathanmcgurk.fotopic.net/p64343155.html
More to come over the final few weeks of this project. I hope you enjoyed the updates
Best Regards
Jonathan McGurk
Photographs From Thursday 15th April 2010:
Passsengers alight from a service which has came into terminate on platform 15
http://jonathanmcgurk.fotopic.net/p64343136.html
Class 334 012 departs platform 15 en - route to Wemyss Bay (ex 10.50 service). The view shows the tremendous progress being made:
http://jonathanmcgurk.fotopic.net/p64343137.html
Platforms 14 and 15 have been rumoured to be receiving improvements in the near future. New track, overhead electrification equipments and new platform surfaces for each platform are objectives that will be carried out if this has to go ahead in the near future. Class 334 011 and Class 334 017 are seen occupying these two platforms waiting to work their next duties:
http://jonathanmcgurk.fotopic.net/p64343144.html
Photographs Taken From The Station Carpark:
Track is now partially, nearly fully laid with overhead electrification portals erected also:
http://jonathanmcgurk.fotopic.net/p64343138.html
http://jonathanmcgurk.fotopic.net/p64343139.html
This view will change over the next week or so:
http://jonathanmcgurk.fotopic.net/p64343140.html
Looking west:
http://jonathanmcgurk.fotopic.net/p64343141.html
TWO EXCLUSIVE VIEWS - Showing the new build platforms 12 and 13 coming to life. Balfour Beatty workmen at work, bricklaying what will be known as platforms 12 and 13. Track has now partially been laid for the two new platforms and it will not be long before this view changes until all the track is laid and all work is complete. Looking above, you can see the new overhead electrification portals have been erected with wires to be added over the next week or so. If you look closely, you can see where the buffers will be installed at the platform ends. The completion date for the new platforms is Sunday 2nd May 2010 and the official opening date when the platforms will be in full working use is Sunday 9th / Monday 20th May 2010:
http://jonathanmcgurk.fotopic.net/p64343142.html
http://jonathanmcgurk.fotopic.net/p64343142.html
Photographs From Saturday 17th April 2010:
The boarding protecting still platform 11 will soon be removed and the new build platforms 12 and 13 will be unveiled next month. Class 156 503 in Saltire livery is seen sitting inside platform 11 waiting to work the 12.37 service to Paisley Canal:
http://jonathanmcgurk.fotopic.net/p64343145.html
Saltire Reflections - Class 156 503 reflects off the train dispatcher box on platform 11:
http://jonathanmcgurk.fotopic.net/p64343146.html
looking west from the top of platform 11 showing the two new double tracks have been laid to accommodate the new build platforms 12 and 13 at Glasgow Central High Level station. The double track, as you can see, is linked to a set of points before carrying on straight through the station's famous arch and into the station. The rail layer vehicle can be seen ahead, sitting stable awaiting its next track laying duties. Overhead electrification portals have been erected and are awaiting to be connected with associated wires. Two new signals, one for each new platform, 'GG 5612' & 'GG 5613' have also been erected and both await testing:
http://jonathanmcgurk.fotopic.net/p64343147.html
A closer view showing the double track laid just before passing under the station's famous arch:
http://jonathanmcgurk.fotopic.net/p64343148.html
The arch now with double track passing through it to accommodate platforms 12 and 13:
http://jonathanmcgurk.fotopic.net/p64343149.html
http://jonathanmcgurk.fotopic.net/p64343150.html
New controlled signal 'GG 5612' will be the new signal for platform, of which has still to be turned on and tested:
http://jonathanmcgurk.fotopic.net/p64343151.html
http://jonathanmcgurk.fotopic.net/p64343152.html
Looking east into the station from the top of platform 11. The view shows the station's atch with double track running through it, new overhead electrification portals erected and lots of work taking place through the arch itself. A class 334 train set is seen sitting inside platform 14 waiting to work its next duties:
http://jonathanmcgurk.fotopic.net/p64343153.html
http://jonathanmcgurk.fotopic.net/p64343154.html
The points which the double track stretches off to accommodate platforms 12 and 13, looking west:
http://jonathanmcgurk.fotopic.net/p64343155.html
More to come over the final few weeks of this project. I hope you enjoyed the updates