I don't do twitter but came across this the other day. https://twitter.com/chittimarco/status/1496871259237457925?s=21
It appears the city is getting 6km of Metro including eight stations for the price of Headbolt Lane station in Merseyside.

Genova is a particularly difficult place to build a public transport infrastructure since any journey that doesn't parallel the coast depends on a fascinating but inevitably uncoordinated mixture of lifts, funiculars and zig-zag bus routes.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,228
Location
Bolton
The price quoted in the tweet is €389 million. This is approximately £325 million. Is Headbolt Lane going to cost £325 million?
 

urbophile

Established Member
Joined
26 Nov 2015
Messages
2,480
Location
Liverpool
The price quoted in the tweet is €389 million. This is approximately £325 million. Is Headbolt Lane going to cost £325 million?
That was more or less the figure quoted. Admittedly including some double-tracking and rebuilding a bridge, but even then!
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,765
The £300m+ figure was for the Skelmersdale extension, not Headbolt Lane.
 

urbophile

Established Member
Joined
26 Nov 2015
Messages
2,480
Location
Liverpool
The £300m+ figure was for the Skelmersdale extension, not Headbolt Lane.
Correction accepted. Nevertheless that is only about 1 or 2km of new track, whereas Genova is getting for the same price, 6km of track and eight stations.
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,765
Correction accepted. Nevertheless that is only about 1 or 2km of new track, whereas Genova is getting for the same price, 6km of track and eight stations.
I know, it's insane how much things cost here. Building an elevated metro in a congested city should of course cost more than a flat field in Lancashire
 