Let's do the numbers. The gradients up to Exeter Central is 1.5% and 2.7%, rising 40m in all.
In round numbers, the eight-car Western sleeper will weigh ~325t. With loco that will be around 400t. To get up the steepest 2.7% slope will require a tractive effort of 110kN. Well within the 290kN capability of a 93. A 99 would be overkill.
On diesel and battery, the 93 generates 1300kW. Allowing 500kW for hotel power gives 800kW for traction, which equates to a speed of 800/110 = ~7m/s up 2.7%. That's 15mph, which should be acceptable late at night. A 1600kW Class 99 would not be much faster.
800kW can lift 400t up 40m in 200s, so the 93 will take 3 1/2 mins to get to Exeter Central. Meaning the batteries will still be three-quarters full at the top.
The biggest hill on line BAE2 is between Cranbrook station and Honiton tunnel, which rises 130m over 20km. Averaging the gradient to 0.65% gives a speed of 800kW/26kN = ~30m/s, around 65mph, ignoring wind and rolling resistance. Taking 660s = 11 minutes to cover 20km. Battery capacity is enough to deliver full power all the way up, but would be exhausted at the top.
Back on topic, a Class 99 woud be overkill for the sleeper, even if it had hotel power. The 99 will be much better suited to hauling heavy aggregate trains from the Mendips to London, or max length 1800t intermodals up the hill from Felixstowe, where the 500kN tractive effort would be put to good use.
Line profile and gradient data from: https://www.railwaydata.co.uk/linefiles/route/?ELR=BAE2
What is the relevance of any of this given that we seem to have established that nothing will be replacing the 57s on the Night Riviera any time soon?