Is there any in house design teams in NR for designing footbridges etc or is the design as well as the construction outsourced?
I have no knowledge of current NR practice, but steel footbridges are normally designed and detailed by the fabricators, who have their own standard designs, steel sections and details to suit their fabrication processes. The design process involves tailoring these to the particular site requirements.Is there any in house design teams in NR for designing footbridges etc or is the design as well as the construction outsourced?
Unless its quoted specifically, that cost is for everything, not just the structure. So design, staff costs for sponsorship, project management, construction, close out etc... the bridge is only a part of it.
What's the difference between one of NR's project sponsors and a project manager? And why are both roles needed for a "small" project like a footbridge replacement?Unless its quoted specifically, that cost is for everything, not just the structure. So design, staff costs for sponsorship, project management, construction, close out etc... the bridge is only a part of it.
The role of a project manager is, as everyone who has worked in a corporate environment can attest, to fill everyone's calendar with Teams meetings to determine if the project is on track.What's the difference between one of NR's project sponsors and a project manager? And why are both roles needed for a "small" project like a footbridge replacement?
In my experience, the sponsor will be doing things like getting the project onto the shopping list, securing funding, and functioning as the "client". This includes things like determining design requirements for the stakeholders (e.g. does the bridge need to be accessible to horses as well?)What's the difference between one of NR's project sponsors and a project manager?
Network Rail has a standard design with a set of modular parts, presumably procured through a central arrangement. I expect it needs some adjustment on certain sites thoughI have no knowledge of current NR practice, but steel footbridges are normally designed and detailed by the fabricators, who have their own standard designs, steel sections and details to suit their fabrication processes. The design process involves tailoring these to the particular site requirements.
A footbridge will only be one project in their portfolio. Having separate people be "client" and "provider" is good practice.And why are both roles needed for a "small" project like a footbridge replacement?
Exactly so - one of my railway career roles was as client for several major projects.In my experience, the sponsor will be doing things like getting the project onto the shopping list, securing funding, and functioning as the "client". This includes things like determining design requirements for the stakeholders (e.g. does the bridge need to be accessible to horses as well?)
The project manager will be responsible for actually delivering the footbridge that satisfies the requirements within the budget allocated.
== Doublepost prevention - post automatically merged: ==
Network Rail has a standard design with a set of modular parts, presumably procured through a central arrangement. I expect it needs some adjustment on certain sites though
A footbridge will only be one project in their portfolio. Having separate people be "client" and "provider" is good practice.
Legally a footpath diversion, however slight, requires permission from the local authority and can - and often will - be subject to objections.Being even more pedantic than usual, how far can a footpath be moved from its mapped position without official consent? A footbridge of the station type (ie steps at right angles to the bridge) would mean that either the bridge deck was no longer on the old alignment or the path would have to deviate to reach the bottom of the steps. A straight line alignment would require land take for the steps since a right of way is no more than that.
Personally, I would regard any challenge to a realignment for a footbridge mischievous but the law is an odd beast! At least there are no current plans for a footbridge at Altnabreac!
This would, of course, require a cartel of contractors fixing prices.While the complications around installing a 'simple' footbridge are far greater than meet the eye, let's also not pretend that rail contractor costs aren't generally greatly inflated 'because it's the railway = license to print money'!