Sorry it was only a quick bit of info about the bridge Howard, I've been working nights up on the Parkway job so bit rushed today.
Yes indeed, it was quite poor so needed replacing, it was one of those concrete jobs that looked dodgy from new, the new structure is steel.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,239
Dec 2018 timetable change for the four tracking, but electrification comes later.

From NR's CP5 enhancement delivery plan, Sep 2017 update.
 

duffield

Established Member
Joined
31 Jul 2013
Messages
3,272
Location
East Midlands
Anyone know when the next Filton Bank weekend closure is? I'd like to go round the XC Newport diversion.

Edit: As per the following posts, I meant Bristol Parkway closures.
 
Last edited:

duffield

Established Member
Joined
31 Jul 2013
Messages
3,272
Location
East Midlands
How can XC divert via Newport if Filton bank is blocked? They go via Swindon and Kemble.

Duh! Just having a slight brain failure there. Or course, what I want is the next Bristol Parkway closure, when XC do divert via Newport. And that's assuming there are some further Parkway closures to come, relating to the work for the 4th platform.

But come to think of it the Filton Bank closures and the Swindon diversions would be good as well.

I'll have a further dig around for any info anyhow.
 

D60

Member
Joined
16 Feb 2015
Messages
287
Filton Abbey Wood update.
The realigned pedestrian access from the station car-park in Emma-Chris Way re-opened last week, 31Jan apparently.
Realignment being necessary to provide the space needed for the 4th platform track to go in, for the use of Cardiff-bound services.
The temporary scaffolded pedestrian walkway from Nutfield Close is now closed and is being dismantled, to allow work here to move on to further clearance/excavation and foundational groundworks for platform construction.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,854
Location
Beeston (Notts)
Another update from last weekend. Much of the drainage systems appear to have been installed at the Filton end of the Bank, with freshly laid ballast over the top; presumably that will all now need to bed in in advance of the Easter Blockade. Unsure of the progress at the Dr Day's end though.
 

jhy44

Member
Joined
7 Aug 2008
Messages
202
Location
Marylebone (London)
Apologies if this has already been discussed, but:

1) When is the anticipated/timetabled finish date for the quadrupling?
2) Are all four lines due to be electrified?
3) What, if any, additional services are explicitly planned to operate once this work has been complete (aka, no vaguely muted additional services as part of the 'MetroWest' fantasy)?
 

Mojo

Forum Staff
Staff Member
Administrator
Joined
7 Aug 2005
Messages
21,169
Location
0035
2) Are all four lines due to be electrified?
The line won’t be electrified at all anymore as electrification has been “paused” so only the line via Parkway will be electrified, not even Temple Meads!
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,854
Location
Beeston (Notts)
1) When is the anticipated/timetabled finish date for the quadrupling?
End of this year/start of the next one AIUI.
2) Are all four lines due to be electrified?
At this point, no, due to the wiring being "Graylinged". Only time will tell if the wires get extended down to Temple Meads.
3) What, if any, additional services are explicitly planned to operate once this work has been complete (aka, no vaguely muted additional services as part of the 'MetroWest' fantasy)?
AIUI, the new layout would allow fast & slow services to be segregated; the only new services I'm aware of are the fast BRI-BPW-PAD IETs.
 

duffield

Established Member
Joined
31 Jul 2013
Messages
3,272
Location
East Midlands
Do we know yet when the existing tracks are going to be slewed, and if that will be done in one long closure or several?
 

Sean Emmett

Member
Joined
9 Mar 2015
Messages
522
Network Rail say "The project is due to be completed with the laying of the new tracks during a solid 23-day block of 24 hour engineering work in the autumn of 2018. Further information about this period of engineering work, and alternative travel arrangements, will be published later in 2018."

https://www.networkrail.co.uk/runni...tern/great-western-mainline/bristol-upgrades/

I did see some actual dates quoted in Oct/Nov 2018, but now can't find the link.

Currently the 2 tracks swap from the west to the east side of the formation around Milepost 3 out of Temple Meads. Presumably some of the new tracks will be laid on the east side from Lawrence Hill up to Ashley Hill (MPs 1 to 2 3/4 approx), and on the west side down from Filton Abbey Wood to around Constable Rd (MPs 4 1/2 to 3 1/4 approx) in readiness - with the area around milepost 3 and the new crossovers at Horfield being sorted during the blockade?
 

contractor1

Member
Joined
13 Jul 2016
Messages
17
Network Rail say "The project is due to be completed with the laying of the new tracks during a solid 23-day block of 24 hour engineering work in the autumn of 2018. Further information about this period of engineering work, and alternative travel arrangements, will be published later in 2018."

https://www.networkrail.co.uk/runni...tern/great-western-mainline/bristol-upgrades/

I did see some actual dates quoted in Oct/Nov 2018, but now can't find the link.

Currently the 2 tracks swap from the west to the east side of the formation around Milepost 3 out of Temple Meads. Presumably some of the new tracks will be laid on the east side from Lawrence Hill up to Ashley Hill (MPs 1 to 2 3/4 approx), and on the west side down from Filton Abbey Wood to around Constable Rd (MPs 4 1/2 to 3 1/4 approx) in readiness - with the area around milepost 3 and the new crossovers at Horfield being sorted during the blockade?

blockade is from 26th october to 19th november
 

Sean Emmett

Member
Joined
9 Mar 2015
Messages
522
Sleepers being laid out today on the restored W side of the formation between Constable Rd (3m 29c) and Bonnington Walk (3m 62c) over bridges.

These will eventually form the relief/Cardiff lines.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
Sleepers being laid out today on the restored W side of the formation between Constable Rd (3m 29c) and Bonnington Walk (3m 62c) over bridges.

These will eventually form the relief/Cardiff lines.
Did you happen to get an idea whether the existing tracks will need to be slewed again? I have a feeling they were, after the originals were removed.
 

adrock1976

Established Member
Joined
10 Dec 2013
Messages
4,450
Location
What's it called? It's called Cumbernauld
Is the layout of the 4 tracks going to be (from Bristol Temple Meads) from left to right:

1) to South Wales
2) from South Wales
3) from Westerleigh Junction
4) to Westerleigh Junction

or

1) to South Wales/Westerleigh Junction relief
2) to South Wales/Westerleigh Junction main
3) from South Wales/Westerleigh Junction main
4) from South Wales/Westerleigh Junction relief
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
That's how it was in GWR / BR days, except that freight trains from South Wales and to South Wales from the Rhubarb curve (ie to /from Bath) would cross over near Narroways Junction. I don't know what South Wales to Portsmouth express trains did, although the main platforms at Stapleton Road with facilities and station entrance were the ones on the east side, so perhaps there was an opportunity to cross over further north.
 

Sean Emmett

Member
Joined
9 Mar 2015
Messages
522
Is the layout of the 4 tracks going to be (from Bristol Temple Meads) from left to right:

1) to South Wales
2) from South Wales
3) from Westerleigh Junction
4) to Westerleigh Junction

or

1) to South Wales/Westerleigh Junction relief
2) to South Wales/Westerleigh Junction main
3) from South Wales/Westerleigh Junction main
4) from South Wales/Westerleigh Junction relief
Neither!
From the plans for Ashley Hill station as part of Metro West, from W to E they will be

1) Up Relief to Cardiff
2) Down Relief from Cardiff
3) Up Filton Main to Parkway
4) Down Filton Main from Parkway.

I understand there will be 75 mph crossovers at Horfield to allow PAD - BRI via BPW (& vv) trains to cross from the mains to reliefs if heading to reinstated P1/0 i.e. in the Digby Wyatt train shed.

This was reason I was given that it will be difficult, but not impossible, for Horfield station to be reopened on its original site and (as the then Cllr) I supported a new station at Constable Rd instead, in addition to Ashley Hill / Down.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
^^^Yes, the other poster got that wrong and I didn't notice. (We drive on the left in GB on rail!).
I think you were right on Constable Road. Far more housing of folk who might use local metro services, I suspect, and more housing now going up, I understand.
 

Colly405

Member
Joined
19 Nov 2012
Messages
333
Location
Stoke Gifford
I understand there will be 75 mph crossovers at Horfield to allow PAD - BRI via BPW (& vv) trains to cross from the mains to reliefs if heading to reinstated P1/0 i.e. in the Digby Wyatt train shed.
And presumably also the locals to BPW that call at SRD and LWH, or are the 'main' platforms at those stations beng reinstated?
 

D1009

Established Member
Joined
22 Feb 2012
Messages
3,166
Location
Stoke Gifford
And presumably also the locals to BPW that call at SRD and LWH, or are the 'main' platforms at those stations beng reinstated?
I believe the trains to which you refer will be the main users of the new crossovers, at least initially. Currently the Great Malvern/Gloucester to Westbury serve Stapleton Road and Lawrence Hill going south, and the Weston to Parkway trains going north. This may change with the new timetable next year though.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
And presumably also the locals to BPW that call at SRD and LWH, or are the 'main' platforms at those stations beng reinstated?
See D1009's reply and no they aren't, to answer the second question. I never saw a passenger train stop at Lawrence Hill's platform 4. I suspect the daily trains taking the Rhubarb curve for the shift workers at Fry's Keynsham possibly used to stop at it and possibly excursions.
 