• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Fife Circle and Borders Railway - electrification update

Status
Not open for further replies.

och aye

Member
Joined
21 Jan 2012
Messages
1,013
The Scot. Gov. Infrastructure Investment Plan 2021-22 to 2025-26 Major capital projects progress update (August 2024) has been published, with news about the Fife Circle and Borders Railway electrification.


Project: Borders Railway Decarbonisation​

Business case approved stages: Project to facilitate the decarbonisation of rolling stock emissions on the Borders Railway through the installation of railway electrification infrastructure. This infrastructure will allow the replacement of the diesel rolling stock which currently operate on the route with new battery electric rolling stock. The OBC outlined that the total project cost was estimated to be £32 million and that the project was estimated to commence construction in 2023 and be operational in May 2027 (£14.4 million of total project cost is attributable to the Tweedbank Feeder Station).

Progress at December 2023 : A refresh of the Rail Services Decarbonisation Action Plan is underway (as reported in March 2023 update). The outcome of this will allow for the project to be replanned. Timescales for this project will be determined by the wider programme and the rolling stock procurement exercise.

A contract to provide a new Feeder Station at Tweedbank has been placed with National Grid PLC, with the Feeder Station planned to enter service in September 2026. This will be used to provide power to the planned railway electrification at the south end of the Borders Line. The anticipated final cost of these works is £14.4 million. A contract has also been placed with National Grid PLC for a new Feeder Station at Portobello. This is due to enter service in December 2025. The primary purpose of this Feeder Station to provide additional power and network resilience in the Edinburgh area. In addition, it will support the planned decarbonised Borders Line rail services. The anticipated cost of these works is £32.4 million.

Progress at August 2024: A refresh of the Rail Services Decarbonisation Action Plan continues and the outcome of this will allow for the project to be re-planned. Timescales for project will be determined by the associated rolling stock procurement exercise and the needs of the wider rail projects pipeline.

Once the new Feeder Station at Tweedbank has entered service, this will be used to provide power to the planned railway electrification at the south end of the Borders Line. Once the new Feeder Station at Portobello has entered service, this will provide additional power and network resilience in the Edinburgh area and in addition it will support the planned decarbonised Borders Line rail services. Costs will be re-estimated as part of the replanning process.

Contact for public enquiries: email: info@transport.gov.scot

Project: Fife Decarbonisation​

Business case approved stages: Project to facilitate the decarbonisation of rolling stock emissions on the Fife Railway through the installation of railway electrification infrastructure. This infrastructure will allow the replacement of the diesel rolling stock which currently operate on the route with new Battery Electric rolling stock. The OBC outlined that the total project cost was estimated to be £210 million (exclusive of Feeder Station costs) with the full project estimated be operational in December 2025.

Progress at December 2023: A refresh of the Rail Services Decarbonisation Action Plan is underway (as reported in March 2023 update). The outcome of this will allow for the project to be re-planned. Timescales for this project will be determined by the wider programme and the rolling stock procurement exercise.

A contract to provide a new Feeder Station at Thornton has been placed with National Grid PLC. With the Feeder Station planned to enter service in September 2026. This will be used to provide power to the planned railway electrification in Fife. The anticipated final cost of these works is £29.4 million.

Progress at August 2024: A refresh of the Rail Services Decarbonisation Action Plan continues and the outcome of this will allow for the project to be re-planned. Timescales for project will be determined by the associated rolling stock procurement exercise and the needs of the wider rail projects pipeline.

Once the new Feeder Station at Thornton has entered service, this will be used to provide power to the planned railway electrification in Fife. Costs will be re-estimated as part of the replanning process.

Contact for public enquiries: email: info@transport.gov.scot


The BBC are saying that the electrification has been paused:


The report also provides updates on other projects.

It said electrification of the Borders rail line and of the Fife Circle rail line had been paused due to an ongoing "refresh" of a decarbonisation action plan.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,492
Location
Preston Lancs

Project: Fife Decarbonisation​


Progress at August 2024: A refresh of the Rail Services Decarbonisation Action Plan continues and the outcome of this will allow for the project to be re-planned. Timescales for project will be determined by the associated rolling stock procurement exercise and the needs of the wider rail projects pipeline.

A contract to provide a new Feeder Station at Thornton has been placed with National Grid PLC. With the Feeder Station planned to enter service in September 2026. This will be used to provide power to the planned railway electrification in Fife. The anticipated final cost of these works is £29.4 million.

Once the new Feeder Station at Thornton has entered service, this will be used to provide power to the planned railway electrification in Fife. Costs will be re-estimated as part of the replanning process.

To me, that is still positive.
 

moffatcalum

Member
Joined
27 Apr 2024
Messages
30
Location
Burntisland, Fife, Scotland, UK
Seems that above my house (near the station in Burntisland), the PDG aviation services helicopter was doing a couple of rounds of the fife circle line. It also flew north as far as ladybank. I can only infer or hope rather this may be regarded as a positive sign perhaps?
Seeing as the line of thier flight path matches up with the latest plans I think
 

Attachments

  • IMG_3158.png
    IMG_3158.png
    919.4 KB · Views: 59
  • IMG_3157.png
    IMG_3157.png
    682.9 KB · Views: 58

kkong

Member
Joined
8 Sep 2008
Messages
1,146
The Scot. Gov. Infrastructure Investment Plan 2021-22 to 2025-26 Major capital projects progress update (August 2024) has been published, with news about the Fife Circle and Borders Railway electrification.

The "refresh" of the Rail Services Decarbonisation Action Plan has been underway since March 2023.

it's now October 2024 (19 months later) and there's still no word on when the "refreshed" plan will be published.

I'll be expecting a very "fresh" plan if/when it sees the light of day!
 

rower40

Member
Joined
1 Jan 2008
Messages
579
Seems that above my house (near the station in Burntisland), the PDG aviation services helicopter was doing a couple of rounds of the fife circle line. It also flew north as far as ladybank. I can only infer or hope rather this may be regarded as a positive sign perhaps?
Seeing as the line of thier flight path matches up with the latest plans I think
Is it just me, or does the idea of electrified helicopter lines fill anyone else with dread?
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,276
Seems that above my house (near the station in Burntisland), the PDG aviation services helicopter was doing a couple of rounds of the fife circle line. It also flew north as far as ladybank. I can only infer or hope rather this may be regarded as a positive sign perhaps?
Seeing as the line of thier flight path matches up with the latest plans I think
Isnt that just normal infrastructure surveillance? The Network Rail helicopter regularly goes along the main line toward Basingstoke.
 
Status
Not open for further replies.

Top