StephenHunter
Established Member
Why has this tunnel being put in a massive trench at the bottom of the sea rather than TBMs being used like the Channel Tunnel?
Yes it is a shallow sea with substantial glacial deposits on the bed, so it is easier and cheaper to dig a trench for the tunnel segments.Geology?
Indeed, it's apparently approximately 10.9 miles long and the Channel Tunnel is 31.35 miles long.Also consider that “bored tunnels” will desirably be deeper than a cut and cover in the seabed (dredged trench) because boring a tunnel and keeping it water tight is a challenge the closer you are to a water source.
This makes approaches either side more challenging as the trains need more distance to drop to a deeper depth.
An example would be the Tyne Tunnels. The older tunnel is deeper and has a cork screw on the north side. Newer tunnel is shorter.
If the water is shallow enough, you can build a tunnel with a cross section that you could not dream of in a bored tunnel.Why has this tunnel being put in a massive trench at the bottom of the sea rather than TBMs being used like the Channel Tunnel?
The area is silt and glacial deposits. Would have to go long way down to find suitable material to bore through.Why has this tunnel being put in a massive trench at the bottom of the sea rather than TBMs being used like the Channel Tunnel?
As discussed in this thread, most of the German part of the route doesn't have planning approval, let alone construction start, some sections aren't even applied for yet. I wouldn't believe any opening date of 2030 or earlierGermany is building a new 200km/h (124mph) double track electrified railway from Lubeck to the tunnel, about 30km is rebuilt existing lines and about 55km new alignment. Due to open in 3-4 years time.
As discussed in this thread, most of the German part of the route doesn't have planning approval, let alone construction start, some sections aren't even applied for yet. I wouldn't believe any opening date of 2030 or earlier
This is Germany. The reputed efficiency, if it ever truly existed, died long ago.I have just had an e-mail from someone I know who is well informed about this and he says that opening of the link has been delayed until 2032 for road traffic and shortly after that for rail traffic. So maybe they will complete the line in Germany in time, you never know!