Ely - Norwich speed restrictions

Status
Not open for further replies.

mafeu

Member
Joined
20 Mar 2014
Messages
54
There have been delays for some time (months? feels like a long time) between Ely and Norwich. A speed restriction is oft stated.

Does anybody know why and if anything is being done to rectify by Network Rail?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Kneedown

Established Member
Joined
29 Dec 2007
Messages
1,837
Location
Nottinghamshire
There is currently a longish one between Queen Adelaide and Mile End. 20mph in the down direction, 40 in the up. Condition of track I imagine as it is a bit more bouncy and wibbly than it should be. Add to that a couple level crossing related speed restrictions, and another 40mph from Keswick to Eaton, and it puts a good few minutes into the journey. We were 10 late into Norwich this afternoon, but a 5mph ESR had appeared over Chettisham LC.
 

mafeu

Member
Joined
20 Mar 2014
Messages
54
Certainly is more bouncy and wibbly! But it just doesn’t seem NR are doing anything to rectify. By end of year I’m worried we’ll be down to 10mph between Ely and Lakenheath! :D
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,874
Location
East Anglia
bank slip due to the summer temps..
Exactly mate. Usual area drying out. Speed has been 20, 40 & now back to 20 again. Add the delays for much of the same reasons Peterborough-Ely which hits the preceding EMT service & we are looking at an unreliable Norwich-Cambridge service for the time being. The track really does looks interesting along those affected sections.
 

trebor79

Established Member
Joined
8 Mar 2018
Messages
4,908
What sort of timescale is acceptable for this to be repaired? I find it a bit surprising that it's considered ok for reasonably busy regional route to be reduced to lower speeds than in places than a heritage line.
 

mafeu

Member
Joined
20 Mar 2014
Messages
54
What sort of timescale is acceptable for this to be repaired? I find it a bit surprising that it's considered ok for reasonably busy regional route to be reduced to lower speeds than in places than a heritage line.

I'm hoping Network Rail have a plan in place to get repairs in place ASAP. Feels as if the line is in a decline at the moment with these multiple speed restrictions. Surely it'll only get worse if not repaired?
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,828
When the track condition goes ‘off’ because of the dry conditions, it can go in as little as 24hours. But it is rather unpredictable - you can fix it quickly, then a day later it shifts again, or another part just down the line goes instead. It’s like whack-a-mole.

Also, unfortunately, when it gets wet again, it can go ‘off’ again as the banks swell up with the moisture. Typically the engineers wait until the movement has stabilised before fixing it, as anything else is just money down the drain.
 

trebor79

Established Member
Joined
8 Mar 2018
Messages
4,908
I think there are some similar section on the Ely to Peterborough stretch. Certainly last time I used that route, we seemed to absolutely crawl for the last few miles into Ely.
I guess fen is always going to be a bit susceptible to movement.
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
19,874
Location
East Anglia
It's a case of priority I'm afraid. The tamping etc is in high demand at the moment. Whilst the service just copes it will not be top of the list.
 

Wronskian

Member
Joined
7 Dec 2012
Messages
22
Location
Ely
I travelled Peterborough to Ely on the 1859 CrossCountry service last night - there was most definitely a severe speed restriction at Chettisham LC. My other half later drove that way and the barriers were down, she observed another crawling train. So something going on - anyone know any more about works there? (I didn't see any orange jackets though it was dark!)

The level crossing by Ely station is now closed to general traffic, but is still operating - I presume works traffic is using it as they rebuild the underpass. The plan now is that the crossing will not reopen to the public - the conversion works taking the next 12 weeks. Maybe that will give some well-needed leeway in the area.
 

ac6000cw

Established Member
Joined
10 May 2014
Messages
3,911
Location
Cambridge, UK
The level crossing by Ely station is now closed to general traffic, but is still operating - I presume works traffic is using it as they rebuild the underpass. The plan now is that the crossing will not reopen to the public - the conversion works taking the next 12 weeks. Maybe that will give some well-needed leeway in the area.

Yes - that one of the reasons why NR contributed to the cost of the Ely Southern Bypass road (another reason is to avoid the frequent bridge-bashing of the underpass and consequent disruption to trains).
 