Are you saying without electrifying Worcester-Dorridge at least and maybe stratford as well it’s not worth it?
It depends why your doing it, who's funding it, whether a franchise/rosco would want to change stock, & what else it could tie in with.
Snow Hill services have end points in multiple locations, in the south-east you've got Stratford & Leamington, but also then points closer in, Dorridge & Whitlocks End.
Lets assume your going to do Stourbridge Junction to Snow Hill/Moor St anyway.
Problem then is, it's too short a distance to make it worth anyone buying bi-modes for, so you need to go south-east. But, there's two routes, & one of those has multiple operators on it.
So you electrify to Tyseley, as thats where both routes are common.
Still not worth changing rolling stock for anyone.
Extend to Whitlocks End.
Not all the services end there, plenty go through to Stratford. Do you assume the wires will get to Stratford within a decade of WE, & so don't order bi-modes?
>Obvious answer is the wires go to Stratford straight away, then you can start ordering EMUs.
Extend to Dorridge.
Same issue as above.
>Obvious answer is the wires go to Leamington straight away, then you can roll out more EMUs.
It does mean a lot of services terminate at Stourbridge. Realistically any extension from there to Worcester needs Worcester to already be done.
Chiltern could then look at bi-modes, or the Chiltern mainline might be being electrified (even easier if Didcot-Oxford-Banbury is done)
You then may as well do Leamington-Coventry-Nuneaton, already then electrified at both ends, & XC could then look at bi-modes.